ML19210A782
| ML19210A782 | |
| Person / Time | |
|---|---|
| Site: | Crane |
| Issue date: | 08/15/1978 |
| From: | Herbein J METROPOLITAN EDISON CO. |
| To: | Mcdonald W NRC OFFICE OF MANAGEMENT AND PROGRAM ANALYSIS (MPA) |
| Shared Package | |
| ML19210A783 | List: |
| References | |
| GQL-1353, NUDOCS 7910310674 | |
| Download: ML19210A782 (2) | |
Text
6 Er Wh
. REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)
DISTRIBUTION FOR INCOMING MATERIAL 50-209 REC: MADONALD W G ORG: HERSEIN J G DOCDATE: 08/15/78 NPC METROPOL EDISON DATE RCVD: 08/22/7?
DOCTYPE: LETTER NOTARIZED: NO COPIES RECEIVED
SUBJECT:
LTR 1 ENCL 1 FORWARDING SUBJECT FACILITY"S MONTHLY OPERATINO REPT FOR THE MONTil OF JULY.
1978.
PLANT NAME: THREE MILE ISLAND - UNIT 1 REVIEWER INITI AL:
XJM DISTRIBUTOR INITIAL:
- DISTRIBUTION OF THIS MATERIAL IS AS FOLLOWS ****'*************
ANNUAL, SEMI-ANNUAL & MONTHLY OPCRATING RPTC (OL STAGE)
(DISTRIBUTION CODE AGO'8)
FOR ACTION:
BR CHIEF ORB #4 EC**W/6 ENCL INTERNAL:
LE**W NRC PDR**W/ ENCL I a c m.u ; c.acL MIPCa*W/2 ENCL HANAUER**W/ ENCL DIRECTOR DOR **W/ ENCL AD FOR SYS & PROJ**W/ ENCL ENGINEERIf;G BR**W/ ENCL REACTOR SAFETY ER**W/ ENCL PLANT SYSTEMS BR**W/ ENCL EEB**W/ ENCL CORE PERFORMANCE BR**W/ ENCL EFFLUENT TREAT SYS**W/ ENCL EXTERNAL:
LPDR'S HARRISBURG, PA**W/ ENCL NATL LAB ANL**W/ ENCL TERA **W/ ENCL NSIC**W/ ENCL ACRS CAT B**W/15 ENCL
) F ' C) 0\\
JU DISTRIBUTION:
LTR 41 ENCL 41 CONTROL NBR:
782160207 SIZE: 1P+4P THE END 7
7910810(^J y,d\\T
127M GC na. - u
/
METROPOLITAN EDISON COMPANY m
POST OFFICE BOX 542 RE ADING, PENNSYLVANI A 19603 TELEPHONE 215 - 929G01 August 15, 1978 GQL 1353 Office of Management Infor ation & Program Centrol Attn:
'4. G. Mcdonald c/o Distribution Services Branch DPC, ADM U. S. Nuclear Regulatory Cc==issicn
'4ashington, D. C.
20555
Dear Sir:
Three Mile Island Nuclear Station Unit 1 (TMI-1)
Operating License No. DPE-50 Docket No. 50-289 Enclosed please find two (2) copies of the July Operating Repcrt for Three Mile Island Nuclear Statien, Unit 1.
Sincerely,
/
/
/
J.
Herbein 2.
Vice President-Generation JGH:DGM:dkf Enclosures cc:
Mr. 3. E. Grier, Director Office of Inspection and Inforcement U. S. Nuclear Regulatory Cc= mission 631 Park Avenue King of Prussia, PA 19hC6 Mr. Ernst Volgenau, Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Comission
'4ashington, D. C.
20555 Ted Cintula (2 copies)
}{g) h 12105 MNEB,U. S. Nuclear Regulatory Cc==issicn
'Jashingten, D. C.
20555
-'3 160207 (To be opened by Addressee On'ly)
TMI-I OPERATING
SUMMARY
JULY 1978 The Unit operated at essentially 100% full power the entire month except for the following planned reductions.
On July 3rd and 4th, the Unit reduced power to 90% due to a reduced system load r'.quirement. These reductions lasted approximately 4.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> and 2./5 hours respectively, after which the Unit escalated back to 100% full power.
On July 19, 1978, the Unit reduced power to 95% to perform Physics testing (Reactivity Coefficients). This planned reduction lasted 0.75 hours8.680556e-4 days <br />0.0208 hours <br />1.240079e-4 weeks <br />2.85375e-5 months <br />.
MAINTENANCE
SUMMARY
The casing vent line on makeup pump (MU-P-1A) required repairs because of a fitting leak. MU-P-1A was taken out of service after the other make up pumps were aligned for normal operation. The following work was performed:
1.
Vent line removed 2.
Repair vent line 3.
Installed vent line 4.
MU-P 'i A te:;ted After thc MU-P-1A was tested satisfactorily, the pump was returned to service.