ML19209D152

From kanterella
Jump to navigation Jump to search
Forwards Lers 79-005/03L-1,79-028/03L,79-045-03L-1 & 79-086/03L-1
Date released: 08/11/2019 Download: ML19209D152


LER 79-086/03L-1:on 790725,train 2 of Control Room Emergency Ventilation Sys Was Inoperable.Cause by One of Three Thermistors in Compressor Motor Winding Failing to Open Circuit.Compressor Repaired & New One Will Be Installed
ML19209D171
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 08/21/1979
From: Rudolph J
TOLEDO EDISON CO.
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
Download: ML19209D171 (2)
LER 79-045/03L-1:on 790330,borated Water Storage Tank Low Level Trip Setpoint in Safety Feature Actuation Sys Channel 2 Was Out of Tolerance.Caused by Noisy Constant Current Test Potentiometer.Potentiometer Replaced
ML19209D164
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 04/25/1979
From: Nelson J
TOLEDO EDISON CO.
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
Download: ML19209D164 (3)
LER 79-028/03L-1:on 790217,high Level Fail Alarm Received for Borated Water Storage Tank Level on Safety Features Actuation Sys Channel 1.Caused by Inadequate Insulation of Instrument Piping & Poor Location of Heat Trace Temp Sensor
ML19209D160
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 03/15/1979
From: Naylor R
TOLEDO EDISON CO.
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
Download: ML19209D160 (3)
LER 79-005/03L-1:on 790106,borated Water Storage Tank Bistable Was Tripped & Decay Heat Valves DH9A Opened & DH7A Closed.Cause by Component Failure of Output Relay K51A in Safety Feature Actuation Sys Channel 4
ML19209D156
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 10/13/1979
From: Nelson J
TOLEDO EDISON CO.
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
Download: ML19209D156 (3)
Forwards Lers 79-005/03L-1,79-028/03L,79-045-03L-1 & 79-086/03L-1
ML19209D151
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 10/13/1979
From: Murray T
TOLEDO EDISON CO.
To: KEPPLER J G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
Download: ML19209D151 (1)