Responds to NRC Re Violations Noted in IE Insp Rept 50-358/79-22.Corrective Actions:Ball Bushings Cleaned, Restored Parts Cleaned,Hanger Parts Removed from Floor & Uncleaned Parts Quarantined
ML19209B427
Person / Time
Site: Zimmer
Issue date: 09/06/1979
From: Borgmann E
CINCINNATI GAS & ELECTRIC CO.
To: Fiorelli G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML19209B426 List:
References
QA-1197, NUDOCS 7910090686
Download: ML19209B427 (2)


Text

~

yc. -

AT THE CINCINN ATI GAS & ELECTRIC COMPANY M

CINCIN N AVI OHIO 4 5 201 v ct ea ot September 6,1979 QA-1197 U. S. Nuclear Regulatory Comission Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137 Attention: Mr. Gaston Fiorelli, Chief Reactor Construction and Engineering Support Branch RE: WM. H. ZIMMER NUCLEAR POWER STATION - UNIT I IE INSPECTION REPORT N0. 79-22, DOCKET NO.

50-358, CONSTRUCTION PERMIT N0. CPPR-88, W.0. #57300-957, JOB E-5590 Gentlemen:

This letter constitutes our formal reply to the subject inspection report.

It is our opinion that nothing in the report or in this letter is of a proprietary nature.

The following is our response to the item of noncompliance identified in Appendix "A" of the subject report.

1.

Corrective Action Taken and Results Achieved A procedure has been prepared for cleaning, reconditioning and making acceptable for installation, the hanger components whose condition is unacceptable. The acceptable components will be stored on shelves with an appropriate sign identifying their status as usable parts.

The following defines the cleaning and reconditioning that will be done.

a) The ball bushings on hanger struts will be cleaned and

.,7 coated with petroleum jelly.

On those parts which were cCD j received from the hanger supplier with paint on the ball bushings, the paint will be removed prior to coating.

b) All parts which were observed as requiring restoration i 1 'I 7 0'02 have been cleaned and placed in the racks.

Those hanger parts such as spring cans and hanger struts

_y j g Jg

?

which have been exposed to the elements and have rust areas on external surfaces will be cleaned and repainted prior to identification as usable parts.

7910090 886

Mr. Gaston Fiorelli U.S. Nuclear Regulatory Comission Region III September 6,1979 - QA-1197 Page 2 c) All hanger parts will be removed from the concrete floor and walkways will be cleaned up.

d) Those parts which have not been cleaned will be placed in a quarantine area. Approximatel3 50% of the deficient components have been cleaned or reconditioned.

2.

Corrective Action to be Taken To Avoid Further Noncompliance The action which will be taken to avoid further noncompliance will be a periodic surveillance of the storage facility by Henry J. Kaiser Company inspectors.

3.

Date When Full Compliance will be Achieved Full compliance will be achieved by September 15, 1979.

We trust that the contents of this letter will serve as an acceptable response to your Inspection Report No. 79-22.

Very truly yours, THE CINCINNATI GAS & ELECTRIC COMPANY Y

VQ~

E. A. BORGMANN SENIOR VICE PRESIDENT JFW:pa 1117 003 i h i}}