Submits Revised Schedule for Completing Evaluation of Category II & III Items Re Review of Tech Spec Setpoints
ML19209B135
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 09/25/1979
From: Swart F
PUBLIC SERVICE CO. OF COLORADO
To: Varga S
Office of Nuclear Reactor Regulation
References
P-79221, NUDOCS 7910090216
Download: ML19209B135 (2)


Text

.

TTl public Service Company f CeH@Indo 4

%Z>

September 25, 1979 Fort St. Vrain Unit No. 1

-P-79221 Mr. Steven A. Varga, Acting Assistant Director for Light Water P.eactors Division of Project flanagement Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Docket No. 50-267

Subject:

Review of Technical Specification Setpoints

References:

1) PSC Latter P-79120, F.E. Swart to T.P. Speis, June 12, 1979 ,
2) PSC Letter P-78192, l C.K. Millen to T.P. Speis, i December 5,1978 I
3) NRC Letter T.P. Speis to l J.K. Fuller, August 28, 1978 i
4) PSC Letter P-77196, i C.K. Millen to R.P. Denise, -

September 20, 1977 . l Gentlemen:

Preliminary evaluations of all Category II instrument settings and absolute trip values, conducted under the PSC program for the review of Technical Specification Setpoints as outlined in Reference 4, have been completed and are now being finalized. The analysis of unresolved Category I items is proceeding.

The PSC effort required to complete this phase of the program has far exceeded original expectations, however. Therefore, PSC is unable to meet the schedule for completing the evaluations of Category II items (Reference 1).

The schedule for completing the evaluation of Category II and III items is revised as follows:

A. Category II and unresolved Category I items will be evaluated with the intent of identifying absolute ~ trip values and instrument settings for submittal to the NRC by January 1,1980.

1112 284 7910090  :

P . - . . -, ,

~

Mr. Steven A. Varga September 25, 1979 Page 2 B. Evaluation of Category III items will be initiated within thirty (30) days of receiving NRC approval of the absolute trip values and instrument trip settings for Category II items.

PSC would appreciate receiving any NRC comments or responses regarding the results previously submitted.

Very truly yours, G i O .

Frederic E. Swart-Nuclear Project 14anager FES/ RAP:ler .