Text
7/ C--
T, 4-DAIRYLAND POWER COOPERATIVE Ba Crona, OVisconsin 54601 September 5, 1979 In reply, please refer to LAC-6492 DOCKET NO. 50-409 Mr. James G. Keppler Regional Director U. S. Nuclear Regulatory Commission Directorate of Regulatory Operations Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137
SUBJECT:
DAIRYLAND POWER COOPERATIVE LA CROSSE BOILING WATER REACTOR (LACBWR)
PROVISIONAL OPERATING LICENSE NO. DPR-45 IE BULLETIN NO. 79 SEISMIC ANALYSES FOR AS-BUILT SAFETY RELATED PIPING SYSTEMS
Reference:
(1)
NRC Letter, Keppler to Linder, dated July 2, 1979.
(2)
DPC Letter, LAC-2788, Madgett to Giambusso, dated October 9, 1974.
(3)
AEC Letter, Skovholt to Madgett, dated September 26, 1972.
Dear Mr. Keppler:
The subject bulletin (Reference 1) requested that certain information be submitted to ascertain that the seismic analysis input information conforms to the actual configuration of safety-related systems.
Reference 2 discussed seismic design of LACBWR in relation to Safety Guides 12 and 29 dated June 7, 1972.
Reference 2 committed the licensee to proceed with seismic analysis of those piping systems which are required for reactor safety, in order to determine the type and location of additional seismic restraints.
Seismic analysis was completed on Feedwater, Main Steam, Forced Recirculation and the suction and discharge of the High Pressure Core Spray piping systems.
Since LACBWR is operating under a provisional operating license (POL),
a request for a full term license (FTL) was made by Reference 2.
The request for a FTL is being reviewed under the USNRC's Safety Evaluation Program (SEP), which when completed, will provide an adequate safety basis for making a decision regarding, granting of an FTL.
1053 1i8 1-0010l.g'$
SEP 7fr Q
7 91
/
LAC-6492 Mr. James G. Keppler September 5, 1979 Regional Director s
Currently, there is no site specific seismic design basis for but DPC is continuing with seismic analysis of essential
- LACBWR, piping systems, and components building structures, equipment, based on the_ guidelines of the NRC Standard Review Plan, Section 3.8.4.
With regard to Items 1, 2 and 3 of IE Bulletin No. 79-14, the input information for the seismic analysis will be the actual including the pipe run geometry; configuration of system components, location and clearance; pipe embedments and pipe support design, attachments; and valve and valve operator locations and weights, as the information is needed for each system analysis under the SEP.
With regard to Item 4 of the bulletin, there are no bases for non-conformances, as the seismic analyses on the four above mentioned systems was done for information and evaluated to a design basis earthquake that is not site specific.
If there are any questions regarding this submittal, please contact us.
Very truly yours, DAIRYLAND POWER COOPERATIVE cf At Frank Linder, General Manager FL: HAT:af Director, Office of Inspection and cca Enforcement Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D. C.