t e-TENNESSEE VALLEY AUTHORITY CH ATTANOOGA. TENNESSEE 37401 400 Chestnut Street Tower II Septe=ber 12, 1979 Mr.JamesP.\0'Reilly, Director Office of Insgection and Enforcement U.S. Nuclear Regulatory Commission Region II - Sul e 3100 101 Marietta Se et Atlanta, Georgia 30303

Dear Mr. O'Reilly:

SEQUOYAH NUCLEAR PLANT UNITS 1 AND 2 - PENN VENTILATOR QA PROGRAM -

NCR QEB 79 SECOND INTERIM REPORT The subject deficiency was initially reported to NRC-0IE Inspector M. Thomas on June 18, 1979, in accordance with 10 CFR 50.55(e).

Our first interim report was submitted on July 16, 1979. Enclosed is our second interim report. We expect to submit our next report before fuel loading in unit 1. This deficiency has also been reported on Bellefonte and Watts Bar Nuclear Plants as NCR's QEB 79-4 and QEB 79-3, respectively.

If you have any questions concerning this matter, please get in touch with D. L. Lambert at FTS 854-2581.

Very truly yours, TENNESSEE VALLEY AUTHORITY L. M. Mills, Manager Nuclear Regulation and Safety Enclosure ,/

cc: Mr. Victor Stello, Jr., Director (Enclosure)V Office of Inspection and Enforcenent U.S. Nuclear Regulatory Counnission Wast Mgton, DC 20555 qh v