ML19208B193

From kanterella
Jump to navigation Jump to search
Forwards First Interim Deficiency Rept Re Ice Condenser Heat Loads Exceeding Design Heat Loads
ML19208B193
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 09/11/1979
From: Mills L
TENNESSEE VALLEY AUTHORITY
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML19208B194 List:
References
NCR-NER-79-1, NUDOCS 7909190337
Download: ML19208B193 (1)


Text

'

TENNESSEE VALLEY AUTHORITY CH ATTANOOGA. TENNESSEE 374ot 400 Chestnut Street Tower II September 11, 1979 Mr. James P. O'Reilly, Director Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Region II - Suite 3100 101 Marietta Street Atlanta, Georgia 30303

Dear Mr. O'Reilly:

SEQUOYAH NUCLEAR PLANT UNITS 1 AND 2 - ICE CONDENSER HEAT LOADS EXCEED DESIGN HEAT LOADS - NCR NES '9 FIRST INTERLM REPORT The subject deficiency was initially reported to NRC-0IE Inspector G. A. Belisle on August 14, 1979, in accordance with 10 CFR 50.55(e).

Enclosed is our first interim report. We expect to submit our next report by November 19, 1979.

If you have any questicas concerning this matter, please get in touch with D. L. Lambert at FTS 854-2581.

Very truly yours, TENNESSEE VALLEY AUTHORITY L. M. Mills, Manager Nuclear Regulation and Safety Enclosure j