7590-01 UNITED STATES NUCLEAR REGULATORY C0f1 MISSION DOCKET NO. 50-321 GEORGIA POWER COMPANY, ET AL.
lsTICE OF PROPOSED ISSUANCE OF AMENDMENTS TO FACILITY OPERATING LICENSES The United States Nuclear Regulatory Cocmission (the Commission) is con-sidering issuance of an amendment to Facility Operating License Nos. DPR-57 and NPF-5, issued to Georgia Power Company, Oglethorpe Electric Membership Corporation, Municipal Electric Association of Georgia, and City of Dalton, Georgia (the licensee), for operation of the Edwin I. Hatch Nuclear Plant, Unit Nos. 1 and 2 located in Appling County, Georgia.
The amendments would revise the Technical Specifications to reflect an increase in spent fuel capacity at Hatch Unit Nos. 1 and 2.
The Hatch No. 1 pool capacity will be increased from 840 to 3181 fuel assemblies.
The Unit 2 capacity will be increased from 1120 to 2845 assemblies.
The amendments might require revision of design features and operating limits for the storage pools, to accommodate the increased storage capacity.
The licenses would be revised to permit storage of elements from each reactor in either pool. The licensee's application for the amendments was submitted by letter dated July 9, 1979.
Prior to issuance of the proposed license amendments, the Commission will have made findings required by the Atomic Energy Act of 1954, as amended (the Act) and the Conmission's regulations.
By September 14, 1979, the licensee may file a request for a hearing with respect to issuance of the amendments to the subject facility operating licenses and any person whose interest may be affected by this proceeding and who wishes to participate as a party in the proceeding must file a written petition for leave to intervene.
Requests for a hearing and petitions for ff30C03 7 9 0010 O ff,7
7590-01 leave to intervene shall be filed in accordance with the Commission's
" Rules of Practic? for Domestic Licensing Proceedings" in 10 CFR Part 2.
If a request for a hearing or petition for leave to intervene is filed by the above date, the Commission or an Atomic Safety and Licensing Board, designated by the Comission or by the Chairman of the Atomic Safety and Licensing Board Panel, will rule on the request and/or petition and the Secretary or the designated Atomic Safety and Licensing Board will issue a notice of hearing or an appropriate order.
As required by 10 CFR 62.714, a petition for leave to intervene shall set forth with particularity the interest of the petitioner in the proceeding, and how that interest may be affected by the results of the proceeding.
The petition should specifically explain the reasons why intervention should be permitted with particular reference to the following factors:
(1) the nature of the petitioner's right under the Act to be made a party to the proceeding; (2) the nature and extent of the petitioner's property, financial, or other interest in the proceeding; and (3) the possible effect of any order which may be entered in the proceeding on the petitioner's interest. The petition should also identify the specific aspect (s) of the subject matter of the pro-ceeding as to which petitioner wishes to intervene. Any person who has filed a petition for leave to intervene or who has been admitted as a party may amend the petition without requesting leave of the Board up to fif teen (15) days prior to the first prehearing conference scheduled in the proceeding, but such an amended petition must satisfy the specificity requirements described above.
e J
.o*
7590-01
, Not later than fifteen (15) days prior to the first prehearing conference scheduled in the proceeding, a petitioner shall file a supplement to the petition to intervene which must include a list of the contentions which are sought to be litigated in the matter, and the bases for each contention set forth with reasonable specificity.
Contentions shall be limited to matters within the scope of the amendment under consideration.
A petitioner who fails to file such a supplement which satisfies these requirements with respect to at least one contention will not be permitted to participate as a pa rty.
Those permitted to intervene become parties to the proceeding, subject to any limitations in the order granting leave to intervene, and have the opportunity to participate fully in the conduct of the hearing, including the opportunity to present evidence and cross-examine witnesses.
A request for a hearing or a petition for leave to intervene shall be filed with the Secretary of the Commission, United States Nucleai Regulatory Commission, Washington, D. C.
20555, Attention:
Docketing and Service Section, or may be delivered to the Commission's Public Document Room, 1717 H Street, N. W., Washington, D. C. by the above date.
Where petitions are filed during the last ten (10) days of the notice period, it is requested that the petitioner or representative for the petitioner promptly so inform the Commission by a toll-free telephone call to Western Union at (800) 325-6000 (in Missouri (800) 342-6700). The Western Union operator should be given Datagram Identification Number 3737 and the following message addressed to Thomas Ippolito:
(petitioner's name and telephone number); (date petition was mailed); (plant name); and (pub-lication date and page number of this FEDERAL REGISTER notice). A copy of 8'.}O265 1
7590-01 the petition should also be sent to the Executive Legal Director, U. S.
Nuclear Regulatory Comnission, Washington, D. C.
20555, and to G. F. Trowbridge, Esquire, Shaw, Pittman, Potts and Trowbridge, 1800 ti Street, M. W., Washington, D. C.
20036, attorney for the licensee.
Nontimely filings of petitions for leave to intervene, amended petitions, supplemental petitions and/or requests for hearing will not be entertained absent a determination by the Commission, the presiding officer or the Atomic Safety and Licensing Board designated to rule on the petition and/or request, that the petitioner has made a substantial showing of good cause for the granting of a late petition and/or request.
That determination will be based upon a balancing of the factors specified in 10 CFR B2.714(a)(i)-(v) and 52.714(d).
For further details with respect to this action, see the application for amendments dated July 9, 1979, which are available for public inspection at the Commission's Public Document Room,1717 H Street, N. W., Washington, D. C.,
and at the Appling county Public Library, Parker Street, Atlanta, Georgia 31513.
Dated at Bethesda, Maryland this 7th ( ay of August 1979.
FOR THE NUCLEAR REGULATORY C0!', MISSION De f
's
/
i
's jf ' Gd1k: 4.Q 4
Thoma sO A'.* Ippoli to, Chi ef Operating Reactors Branch 73 Division of Operating Reactors g~.,p r%,,