Describes Expansion of Technical Review Per IE Bulletin 79-04 to Include Velan Check Valves of Other than 1500 Psi in safety-related Systems.Valve Weights Conform to Drawings & Cause No Problem in Seismic Analysis
ML19207C248
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 08/06/1979
From: Leonard J
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
To: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
JAFP-79-402, NUDOCS 7909100549
Download: ML19207C248 (2)


Text

's

  • ffg POWER AUTHORITY OF THE STATE OF NEW YORK J AMES A. FIT 2 PATRICK NUCLEAR POWER PLANT JOHN D. LEON ARD, JR. P.O. 80X 41 Resident Manager '" ni ng, Nm York 13M3 August 4,1975 JAFP 79-402 33332384o Mr. Boyce H. Grier, Director United States Nuclear Regulatory Commission Region I 6 1 Park Avenue King of Prussia, PA. 19406

SUBJECT:

NRC I&E BULLETIN 79-04 INCORRECT WEIGHTS FOR SWING CHECK VALVES MANUFACTURED BY VELAN ENGINEERING CORPORATION

REFERENCES:

Letter from John D. Leonard, Jr. to Boyce H. Grier Dated April 16, 1979 (JAFP 79-181)

Letter from John D. Leonard, Jr. to Boyce H. Grier Dated May 9, 1979 (JAFP 79-231)

Dear Mr. Grier:

Based on a telephone call from Mr. Durr of your staff regarding our answer to NRC I&E Bulletin 79-04, the staff at the FitzPatrick huclear Power Plant extended its review to include Velan check valves of other than 1500 psi which may be installed in safety-related systems.

These valves were identified and information requested both from the Architect-Engineer and the Velan Valve Corporation. We have been informed by the Velan Valve Corporation tnat the weights of the valves in question are the weights which are identified in our on-site drawings. In addition, we have been informed by the Architect-Engineer that these weights have created no problems in the seismic analysis since they are either equal to or possibly somewhat less than, the valve weights utilized in the analysis.

This information is available at the Site for review by ihe Inspector, if desired.

Very truly ours (Mi JDL:brp JOHf D. LEONARD, JR.

330.C/+

7900100679

Mr. Boyce H. Grier, Director August 4, 1979 United States Nuclear Regulatory Commission JAFP 79-402

SUBJECT:

NRC I&E BULLETIN 79-04 Page DISTRIBUTION:

G. T. Berry, PASNY, NY0 G. A. Wilverding, PASNY, NYO P. W. Lyon, PASNY, NY0 M. C. Cosgrove, PASNY, JAF R. J. Pasternak, PASNY, JAF J. Helland, PASNY, NYO Document Control Center SUCC L

/