ML19207A470

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-336/79-10 on 790402-05 & 09-12.No Noncompliance Noted.Major Areas Inspected:Inservice Insp Activities & Nondestructive Examinations of Steam Generator Tubes & Sleeved Guide Tubes in Control Element Assemblies
ML19207A470
Person / Time
Site: Millstone 
Issue date: 06/14/1979
From: Jernigan E, Lester Tripp, Walton G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML19207A471 List:
References
50-336-79-10, NUDOCS 7908200060
Download: ML19207A470 (7)


See also: IR 05000336/1979010

Text

.

.

U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

Region I

Report No. 50-336/79-10

Docket No. 50-336

License No.

DPR-65

Priority

-

Category

C

Licensee:

Northeast Nuclear Energy Company

P. O. Box 270

Hartford, Connecticut 06101'

Facility Name:

Millstone Point 2

Inspection at:

Waterford, Connecticut

Inspection conducted-

ril 2-5 and 9-12,1979

Inspectors:

. M yr/ VA,

'M/ /M ' # '7 6

.

E. F. Qernigan, R actor Inspector

date sigried

$04Ll7Ah_

w ) 'l. I 9 79

G. A. Walton, Reactor Inspector

date signed

date signed

/

,

Approved by: .

- - '

~I

. W

4['1

'

L. E. Tripp, Chief, Engineering Support

date sigried

Section,hc

1. RC&ES Branch

Inspection Summary:

Inspection on Apri;

-E, and April 9-12, 1979 (ReDort No. 50-336/79-10)

Areas Inspected: Routine, unannounced inspection by regional based inspectors

of inservice inspection activities and nondestructive examinations of steam

generator tubes and sleeved guide tubes in the Control Element Assemblies.

The inspection involved 64 inspector-hours onsite by two NRC regional based

inspectors.

Results: No items of noncompliance with regulatory requirements were identified.

.

809

b37%0

Region I Form 12

eg S

(Rev. April 77)

7 3082co ogg

,

.

.

DETAILS

1.

Persons Contacted

Principal Licensee Employees

  • E. Farrell, Superintendent, Unit 2
  • S. Scace , Engineer

R. Rothgeb, Engineer

J. Keenan, Outage Coordinator

J. Opeka, Station Superintendent

M. Black

S. Sedigala, Assistant Reactor Engineer

J. Stankosky, Level III

  • denotes those present at the exit interview.

Universal Testing Laboratories

N. Goodenough, Quality Assurance Engineer

Hartford Inspection and Insurance Company

R. Smith, Authorized Inspector

,

The inspector also interviewed several other licensee / contractor

employees during the course of the inspection. They included quality

assurance, quality control inspectors and welders.

2.

Plant Tour

The inspector observed various work activities in progress, completed work

and plant status in several areas of the plant during a generai tour.

The inspector examined work items for obsious defects or noncomfliance

with regulatory requirements.

No items of noncompliance were identified.

3.

Inservice Inspection - Procedure Review

The inspector audited selected implementing NDE procedures for technical

adequacy and compliance with the requirements of ASME Section XI,1971

Edition, including the Summer 1973 addenda.

,

809

038

3

The procedures audited were:

NES Procedure 80AlC35

--

NES Procedure - NIP-035, Revision 4, dated March 21, 1979, Ultrasonic

--

Examination Procedures for Reactor Vessel to Nozzle Welds

NIP-033, Reactor Pressure Vessel to Flange Weld, Ultrasonics.

--

NIP-055, Revision 5, dated March 21, 1979, Ultrasonic Examination,

--

Primary Pipe

--

NIP-036, Revision 4, dated March 21, 1979, Ultrasonic Examination

Procedure for Reactor Vessel Inner Radius Areas

--

C. E. Procedure NLE-082-08, Revision 8, Eddy Current Testing of Steam

Generator Tubes

--

C. E. Procedure NLE-034, Revision 3, Visual Examination Procedure

ft Inservice Inspection.

The inspector considered the above procedures with regard to criteria

delineated in 10 CFR 50.55a(g) and the ASME Boiler and Pressure Vessel

Code,Section XI.

This included, but was not limited to the parameters

described below for ultrasonic, visual, and eddy current examinations.

Ultrasonic Examination Technique

a.

The type of apparatus, including frequency range, is specified.

b.

Examination coverage, beam angle and transducer size are specified.

c.

Calibration is accomplished on notches and scanning sensitivity is

defined and is consistent with ASME Code requirements.

,

d.

Evalution, recording and acceptance standards for flaw indications

are specified and consistent with the applicable ASME Code requirements.

Visual Examination

a.

Type of visual examination used, direct or remote, is specified.

b.

Lighting levels are adequate.

c.

Cleanliness of surface t'o be examined is defined.

.

t

809

039

.

4

d.

Measurement of clearan::es, tightness of bolting, physical displacement,

structural adequacy, freedom of motion and verification of settings

as appliccble are defined.

e.

Results are compared to acceptance criteria and required corrective

measures taken where applicable.

Volumetric Examinations Usino Eddy Current Technique

a.

The two channel Eddy Curresit Examination equirment has been identified

including indicator, meter, tube, strip recorcer and tape (whichever is

applicable).

b.

Method for maximum sensitivity is specified.

c.

Method for detennining material permeability of material to be examined

is specified.

d.

Method of examination (Impedance, Phase-Analysis or Modulation Analysis)

is provided.

Examination equipment calibrated in accordance with the applicable

e.

performance reference.

f.

Anplitude and phase has been calibrated with the proper applicable

reference and is recalibrated at predetermined frequency.

(Reference

flaw simulates length, depth and shape.)

g.

Correct coverage of steam generator tubes occurs during the examination.

No items of noncompliance were identified.

Eddy Current Inspection Data Review and Tube Pluacing

The inspector reviewed the eddy current examination results of steam

generator tube inspections performed during the current refueling cutage.

This inspection was performed in compliance with the licensee's " Technical

-

Specification" by eddy current inspecting greater than 99 percent of the

total number of tubes.

The inspection was performed in accordance with

Combustion Engineering eddy current proc 9 dure number NLE-082-08, Revision

8.

Based on the results of these examinations, the licensee's contractor,

Combustion Engineering, has determined the following tubes would be plugged.

Steam Generator #2

Hot Side L80, Row R92 - The .540 inch eddy current probe would not

pass through the tube at number 11 tube support plate.

.

809

040

.

5

Hot Side L34, Row RlCO - The .540 inch eddy current probe would not

enter the tube on the hot side.

Hot Side L40, Row R78 - This tube was a suspect leaker.

Steam Generator #1

50 Row 92 - Blockage of tube.

In addition, one end of one tube required plugging.

It was found

that the other end had been plugged during the last refueling outage.

The inspector witnessed test welding of the steam generator tube plugging

performed by Combustion Engineering. The weld was made using a tungsten-

inert-gas automatic weld process.

No items of noncompliance were identified.

4.

Inservice Inspection (I _) Observation of Work Activities

The inspector witnessed instrument calibration for ultrasonic examination

of the reactor pressure vessel primary nozzle welds.

The calibration was

performeo in accordance with the approved procedure NIP-035, Revision 4.

The personnel performing the calibration were qualified in accordance

with ASNT-TC-1A. The calibration block was fabricated in accordance with

AS!iE B&PV Code Section XI and III.

No items of noncompliance were identified.

5.

Examination of Fuel Eiement Assembly Guide Tubes

a.

Testing and Evaluation of Guide Tube Wear Areas

,

During the first Millstone 2 refueling outage (the first cycle) it

was observed that the guide tubes located under control element asse~~s

(CEA's) had sustained wear. Subsequently, an extensive inspection

program has been developed using eddy current testing (ET), a

technique to determine the amou.it cf wear experienced by guide tubes

of control rodded fuel assemblies.

Evaluation by the licensee's

contractor indicated that assemblies located under CEA's for cycle

2 were to be sleeved.

809

041

.

6

.

b.

Sleeved Con _ trol Element Assembly (CEA) Inspection Program

In order to demonstrate that continued operation with sleeved guide

tubes during cycle 3 will be acceptable, an inspection program has

been developed. This program utilizes a combination of ET and visual

Examinations to confirm that the use of sleeves is an acceptable

method of mitigating the consequences of guide tube wear.

The inspector reviewed the program established for the current cutage.

The review included the following documents:

Sleeved CEA Guide Tube Inspection Program

--

Eddy Current Test Procedure for Sleeved CEA Guide Tubes in Fuel

--

AssemD1 Ms No. 00000-ESS-134, Revision 0, dated March 21, 1979.

The inspector found that the program outlined and identified each fuel

assembly to be examined and the method of examination and referencing

acceptance criteria. The above inspection program has been designed

to address all aspects of sleeved guide tube inspection.

The licensee plans to sleeve all assemblies located under CEA's except

for four (4) demonstration assemblies utilizing reduced flow guide

tubes.

No items of noncompliance with regulatory requirements were identified.

c.

Testing and Evaluation of Guide Tube Sleeves

The inspector witnessed ET of sleeved guide tubes prior.to fuel movement.

The ET techniques employed both the bobbin test and pancake coil test.

The equipment was calibrated using a specimen with a .003 deep notch

machined in the inside diameter. The test was performed in 20 degree

increments around each sleeve examined.

Preliminary results showed that

no sleeve had experienced detectable wear.

This inspection technique

is designed to detect and measure inner surface wear in the expanded

region (including the transition) of sleeved guide tubes. The inspector

audited personnel qualification certificates to verify that qualification

requirements had been met.

Portions of the raw test data were audited

by the inspector. These data indicated that the test techniques employed

were adequate for their intended ourposes.

No items of noncompliance with regulatory requirements were identified.

809

042

.

7

,

6.

Exit Meeting

At the conclusion of the inspection on April 12, 1979, a meeting was held

at the Millstone Point Nuclear Power Station site with representatives of

the licensee organization. The attendees' names are asterisked in paragraph 1.

The inspector sumarized the results of the inspection as described in this

report. The licensee representatives acknowledged the inspector's sumarization.

.

$

as