Revises 790625 Order,Extending Deadline by 15 Days for Request Re Hearing & Filing of Transmission Tariff
ML19207A359
Person / Time
Site: Davis Besse, Perry  
Issue date: 07/16/1979
From: Harold Denton
Office of Nuclear Reactor Regulation
To:
Shared Package
ML19207A354 List:
References
NUDOCS 7908170266
Download: ML19207A359 (2)


Text

-

4 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISJION In the Matter of

)

)

THE TOLEDO EDISON COMPANY and

)

THE CLEVELAND ELECTRIC ILLUMINATING

)

NRC Dkt. No. 50-346A COMPANY

)

(Davis-Besse Nuclear Power Station,

)

Unit 1)

)

)

THE CLEVELAND ELECTRIC ILLUMINATING

)

NRC Dkt. Nos. 50-44CA COMPANY, ET AL.

)

50-441A (Perry Nuclear Power Plant, Units

)

1 & 2)

)

ORDER On June 25, 1979 this office issued an " Order Modifying Antitrust License Condition No. 3 of Davis-Besse Unit 1, License No. NPF-3 and Perry Units 1 and 2, CPPR-148, CFPR-149" in the captioned matter.

That Order amended, effective immediately, Antitrust License Condition No. 3 contained in the above listed 1: cense and construction permits.

The amendment required the Cleveland Electric Illuminating Company (CEI) to file a specific transmission tariff with the Federal Energy Regulatory Commission (FERC). CEI was given twenty days from the receipt of the Order to request a hearing with respect to all or any part of the amend-ment and twenty-five days from the receipt of the Order to file the specific transmission tariff with the FERC.

7908170

?cor?

' Pursuant to 10 CFR 12.204 of the Commissions Rules of Practice IT IS HEREBY ORDERED THAT:

The times afforded to CEI to request a hearing and to file the transmission tariff with the FERC are extended for fifteen (15) days respectively from the receipt of this Order.

FOR THE NUCLEAR REGULATORY COMMIS5 ION A

Harold Denton, Director Office of Nuclear Reactor Regulation Dated at Bethesda, Maryland this 16th day of July,1979.