August 7, 2019 MEMORANDUM TO: Dennis C. Morey, Chief Licensing Processes Branch Division of Licensing Projects Office of Nuclear Reactor Regulation FROM: Leslie Perkins, Project Manager /RA/

Licensing Processes Branch Division of Licensing Projects Office of Nuclear Reactor Regulation

SUBJECT:

SUMMARY

OF JULY 16, 2019, PUBLIC MEETING BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND NUCLEAR ENERGY INSTITUTE AND INDUSTRY REPRESENTATIVES TO DISCUSS A DRAFT AUDIT PLAN IN SUPPORT OF CONFIRMATION of LICENSEES IMPLEMENTATION OF NEI-19-02 (NRC BULLETIN 2012-01)

On July 16, 2019, a Category 2 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of the Nuclear Energy Institute (NEI) and the nuclear power plant industry. The purpose of the meeting was to discuss a draft audit plan for performing audits related to the Open Phase Condition Voluntary Industry Initiative (VII). The audits will assess implementation of an option provided in Revision 3 of the VII, along with the associated guidance developed by NEI, NEI-19-02, Guidance for Assessing Open Phase Condition Implementation Using Risk Insights. The industry offered Ginna and Nine mile as pilot plants for these audits.

During the meeting, NEI provided their comments on the draft audit plan and indicated they would provide the NRC staff with a markup of the draft audit plan for the staffs consideration following the meeting. The NRC staff and NEI discussed some logistics for scheduling the audits. The NRC staff indicated that an on-site audit is preferable to an audit at corporate headquarters. A representative from Exelon agreed to provide potential dates for the staff to conduct the audits by July 26, 2019. The NRC staff provided some clarification on the materials that they would need to review, and indicated that draft documents can be used if revisions to procedures are not finalized. Additionally, NEI provided information regarding how many plants plan to implement the risk-informed option.

D. Morey NRC staff will have additional discussions internally to determine the schedule and path forward for the closure of Bulletin 2012-01. The staffs draft audit plan can be found in ADAMS at Accession No. ML19191A176.

Enclosures:

As stated Meeting Participants Draft Audit Plan Meeting Notice CONTACT: Leslie Perkins, DLP/PLPB (301) 415-2375

ML19202B145 Mtg. Summary ML19191A176 Draft Audit Plan ML19184A203 Mtg. Notice ML19206B163 Package *concurred via email NRR-106 OFFICE NRR/DLP/PLPB PM NRR/DE/EEOB* NRR/DLP/PLPB/BC* NRR/DLP/PLPB/PM NAME LPerkins DWilliams DMorey LPerkins DATE 8/7/2019 8/7/2019 8/7/2019 8/7/2019 Meeting Participants Names Organization Eric Benner NRC Mike Franovich NRC Alex Schwab NRC Donna Williams NRC Antonius Zoulis NRC Juan Lopez NRC Bill Orders NRC Leslie Perkins NRC Vijay Goel NRC Eric Bowman NRC Glen Dentel NRC David decker NRC Michael G. Wiwel PSEG Nuclear Greg Krueger NEI Stephen Geier NEI Robert M. Carritte MPR Associates Susan Richards AEP, DC Cook Nuclear Andy Ratchford Jensen Hughes Larry Naron Exelon Kazimierz Leja Exelon Gary Van Cleave Exelon David Wilson Exelon, Ginna Station Mitchel Mathews Exelon Cory Johnson Exelon Mohamed Mustafa Entergy Gregory Norris Entergy Ayodele Ishola-Salawu NextEra Gabriel E. Alvarez NextEra Fred Madden Certrec Corporation Michael Urbina Sargent and Lundy Saed Almajdoubah Wolf Creek Nuclear Operating Corporation Creighton Adsit Dominion Energy Allen Moldehauer Dominion Energy Joseph DeMarco Dominion Energy Hank Kirkland VC Summer Nuclear Station Matthew Hoholek AEP, Cook Nuclear Plant Steve Nelson Cook Nuclear Station Jordon Vaughan Duke Energy Robert Boyer Duke Energy Nasim Gizi DTE Energy Tamatha Womack TVA Brad Dolan TVA Jana Bergman Curtiss-Wright Sara Scott Xcel Energy Enclosure