MONTHYEARL-2024-118, Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1)2024-10-0808 October 2024 Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1) L-2024-157, Response to Requests for Additional Information Regarding License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles2024-10-0303 October 2024 Response to Requests for Additional Information Regarding License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles L-2024-147, Submission of Periodic Reports2024-10-0101 October 2024 Submission of Periodic Reports L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-136, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-16016 September 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-122, Core Operating Limits Report2024-08-12012 August 2024 Core Operating Limits Report L-2024-106, Fifth and Sixth 10-Year Inservice Testing Interval Relief Request No. VR-022024-08-12012 August 2024 Fifth and Sixth 10-Year Inservice Testing Interval Relief Request No. VR-02 L-2024-089, Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP- 17 451-P. Revision 1. Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections2024-07-25025 July 2024 Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP- 17 451-P. Revision 1. Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal L-2024-112, Condition Prohibited by Technical Specifications2024-07-10010 July 2024 Condition Prohibited by Technical Specifications L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update L-2024-100, Withdrawal of License Amendment Request 274, Reactor Protection System, Engineered Safety Features Actuation System, and Nuclear Instrumentation System Replacement Project2024-06-19019 June 2024 Withdrawal of License Amendment Request 274, Reactor Protection System, Engineered Safety Features Actuation System, and Nuclear Instrumentation System Replacement Project L-2024-076, Reply to Notice of Violation; NOV 05000250, 05000251/2024010-052024-05-29029 May 2024 Reply to Notice of Violation; NOV 05000250, 05000251/2024010-05 L-2024-082, 2023 Annual Radiological Environmental Operating Report2024-05-15015 May 2024 2023 Annual Radiological Environmental Operating Report L-2024-060, 10 CFR 50.59(d)(2) Evaluation and 10 CFR 50.71(e)(2) Technical Specification Bases Summaries Report2024-05-0909 May 2024 10 CFR 50.59(d)(2) Evaluation and 10 CFR 50.71(e)(2) Technical Specification Bases Summaries Report L-2024-072, Cycle 33 Core Operating Limits Report2024-05-0101 May 2024 Cycle 33 Core Operating Limits Report L-2024-073, Cycle 34 Core Operating Limits Report2024-05-0101 May 2024 Cycle 34 Core Operating Limits Report L-2024-048, Divider Plate Assemblies Bounding Analysis Evaluation for Subsequent License Renewal Commitment Revision2024-04-30030 April 2024 Divider Plate Assemblies Bounding Analysis Evaluation for Subsequent License Renewal Commitment Revision L-2024-069, Radiological Emergency Plan Revision 762024-04-22022 April 2024 Radiological Emergency Plan Revision 76 L-2024-066, Sixth 10-Year Inservice Testing Interval Relief Request No. PR-022024-04-17017 April 2024 Sixth 10-Year Inservice Testing Interval Relief Request No. PR-02 L-2024-057, 0 for Turkey Point, Unit 3 - Condition Prohibited by Technical Specifications2024-04-11011 April 2024 0 for Turkey Point, Unit 3 - Condition Prohibited by Technical Specifications L-2024-013, Submittal of Periodic Reports2024-03-28028 March 2024 Submittal of Periodic Reports L-2024-040, Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP-17451-P, Revision 1, Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections2024-03-28028 March 2024 Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP-17451-P, Revision 1, Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections L-2024-047, Proposed Use of a Subsequent ASME Code Edition and Addenda2024-03-28028 March 2024 Proposed Use of a Subsequent ASME Code Edition and Addenda L-2024-044, Revised Steam Generator Tube Inspection Reports2024-03-19019 March 2024 Revised Steam Generator Tube Inspection Reports L-2024-011, and Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2024-03-13013 March 2024 and Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications L-2024-014, 2023 Annual Radioactive Effluent Release Report2024-02-29029 February 2024 2023 Annual Radioactive Effluent Release Report L-2024-025, Notification of Improved Standard Technical Specifications (ITS) Implementation2024-02-22022 February 2024 Notification of Improved Standard Technical Specifications (ITS) Implementation L-2024-008, Supplement to License Amendment Request 278. Incorporate Advanced Fuel Products. Extend Surveillance Intervals and 10 CFR 50.46 Exemption Request to Facilitate Transition to 24-Month Fuel Cycles2024-02-0909 February 2024 Supplement to License Amendment Request 278. Incorporate Advanced Fuel Products. Extend Surveillance Intervals and 10 CFR 50.46 Exemption Request to Facilitate Transition to 24-Month Fuel Cycles L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) L-2024-007, Inservice Inspection Program Owners Activity Report (OAR-1)2024-01-18018 January 2024 Inservice Inspection Program Owners Activity Report (OAR-1) L-2023-173, Quality Assurance Topical Report (FPL-1) Revision 30 Update2023-12-15015 December 2023 Quality Assurance Topical Report (FPL-1) Revision 30 Update L-2023-172, Supplement to Exemption Request Regarding Enhanced Weapons. Firearms Background Checks. and Security Event Notifications Final Rule2023-11-29029 November 2023 Supplement to Exemption Request Regarding Enhanced Weapons. Firearms Background Checks. and Security Event Notifications Final Rule L-2023-155, Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-06542023-11-28028 November 2023 Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, L-2023-146, Part 73 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-11-16016 November 2023 Part 73 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule L-2023-078, License Amendment Request 278, Incorporate Advanced Fuel Products, Extend Surveillance Intervals and 10 CFR 50.46 Exemption Request to Facilitate Transition to 24-Month Fuel Cycles2023-11-15015 November 2023 License Amendment Request 278, Incorporate Advanced Fuel Products, Extend Surveillance Intervals and 10 CFR 50.46 Exemption Request to Facilitate Transition to 24-Month Fuel Cycles L-2023-077, License Amendment Request 277 Updated Spent Fuel Pool Criticality Analysis2023-10-11011 October 2023 License Amendment Request 277 Updated Spent Fuel Pool Criticality Analysis L-2023-110, Response to Requests for Additional Information Regarding License Amendment Request No. 276, Revise Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project2023-08-25025 August 2023 Response to Requests for Additional Information Regarding License Amendment Request No. 276, Revise Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project L-2023-115, Inservice Inspection Program Owner'S Activity Report (OAR-1)2023-08-21021 August 2023 Inservice Inspection Program Owner'S Activity Report (OAR-1) L-2023-114, Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update2023-08-17017 August 2023 Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update L-2023-098, and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 22023-08-0707 August 2023 and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 2 L-2023-094, Response to Requests for Additional Information Regarding License Amendment Request No. 276, Revise Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project2023-07-27027 July 2023 Response to Requests for Additional Information Regarding License Amendment Request No. 276, Revise Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project L-2023-087, Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452)2023-06-29029 June 2023 Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452) L-2023-086, Request Temporary Suspension of Turkey Point License Amendment Request 274, Reactor Protection System, Engineered Safety Features Actuation System, and Nuclear Instrumentation.2023-06-28028 June 2023 Request Temporary Suspension of Turkey Point License Amendment Request 274, Reactor Protection System, Engineered Safety Features Actuation System, and Nuclear Instrumentation. L-2023-074, Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update2023-06-0202 June 2023 Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update L-2023-069, Response to Requests for Additional Information Regarding License Amendment Request No. 276, Revise Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project2023-05-31031 May 2023 Response to Requests for Additional Information Regarding License Amendment Request No. 276, Revise Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project L-2023-072, Preparation and Scheduling of Operator Licensing Examinations2023-05-22022 May 2023 Preparation and Scheduling of Operator Licensing Examinations L-2023-071, NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal2023-05-22022 May 2023 NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal L-2023-061, 2022 Annual Radiological Environmental Operating Report2023-05-12012 May 2023 2022 Annual Radiological Environmental Operating Report 2024-09-25
[Table view] |
Text
June 27, 2019 L-2019-125 U. S. Nuclear Regulatory Commission Attn.: Document Control Desk Washington, D.C. 20555 Re: Turkey Point Unit 3 and Unit 4 Docket Nos. 50-250 and 50-251 Flooding Protection Features Planned Changes Implementation Plan Commitment Update Notification
References:
- 1. NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendations 2.1, 2.3 and 9.3 of the Near Term Task Force Review of Insights from the Fukushima Dai-ichi Accident, dated March 12, 2012, ADAMS Accession Number ML12056A046.
- 2. FPL Letter, L-2014-087, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Flood Hazard Reevaluations for Recommendation 2.1, dated March 11, 2013, ADAMS Accession Number ML13095A216.
- 3. NRC Letter, Turkey Point Nuclear Generating, Unit Nos. 3 and 4 - Staff Assessment of Response to Title 10 CFR 50.54(f), Information Request -
Flood Causing Mechanism Reevaluation (TAC NOS MF1114 and MF1115),"
dated December 4, 2014, ADAMS Accession Number ML14324A816.
- 4. NRC Letter, Turkey Point Nuclear Generating, Unit Nos. 3 and 4 -
Supplement to Staff Assessment of Response to 10 CFR 50.54(f) Information Request-Flood-Causing Mechanisms Reevaluation (CAC Nos. MF1114 and MF1115), dated November 4, 2015, ADAMS Accession Number ML15301A200.
- 5. NRC Staff Requirements Memoranda to COMSECY-14-0037, "Integration of Mitigating Strategies for Beyond Design-Basis External Events and Reevaluation of Flooding Hazards," dated March 30, 2015.
- 6. NRC Letter, Coordination of Requests for Information Regarding Flooding Hazard Reevaluations and Mitigating Strategies for Beyond-Design-Basis External Events, dated September 1, 2015.
- 7. NEI 16-05, Revision 1, External Flooding Assessment Guidelines, dated June 2016, ADAMS Accession Number ML16165A178.
9760 S.W. 344 Street Homestead, FL 33 035
Turkey Point Units 3 and 4 L-2019-125 Docket Nos. 50-250 and 50-251 Page 2 of 3
- 8. U.S. Nuclear Regulatory Commission, JLD-ISG-2016-01, Guidance for Activities Related to Near-Term Task Force Recommendation 2.1, Flood Hazard Reevaluation; Focused Evaluation and Integrated Assessment, Revision 0, dated July 11, 2016, ADAMS Accession Number, ML16162A439.
- 9. FPL Letter, L-2017-124, Flooding Focused Evaluation Summary, dated June 29, 2017, ADAMS Accession Number ML17212B180.
On March 12, 2012, the NRC issued Reference 1 to request information associated with Near Term Task Force (NTTF) Recommendation 2.1 for Flooding . Enclosure 2 of Reference 1, requested that licensees reevaluate flood hazards using present day methods and regulatory guidance and to submit the Flood Hazard Reevaluation Report (FHRR) . For Turkey Point Units 3 and 4, the FHRR was submitted on March 11, 2013, Reference 2, and supplemented by FPL letters dated January 31, 2014, February 26, 2014, and April 25, 2014, and August 7, 2014, ADAMS Accession Numbers ML14055A365, ML14073A065, ML14149A479 and ML14234A085, respectively. The NRC Staff completed its review as documented in the Staff Assessment, Reference 3, and in the Supplement of the Staff Assessment, Reference 4.
Following the Commission's directive to NRC Staff in Reference 5, the NRC issued a letter to industry (Reference 6) indicating that new guidance is being prepared to replace instructions in Reference 5 and provide for a "graded approach to flooding reevaluations" and "more focused evaluations of local intense precipitation and available physical margin in lieu of proceeding to an integrated assessment."
NEI prepared the new "External Flooding Assessment Guidelines" in NEI 16-05 (Reference 7), which was endorsed by the NRC in Reference 8. NEI 16-05 indicates that each flood-causing mechanism not bounded by the design basis flood (using only stillwater and/or wind-wave runup level) should follow one of the following five assessment paths:
- Path 1: Demonstrate Flood Mechanism is Bounded Through Improve Realism
- Path 2: Demonstrate Effective Flood Protection
- Path 3: Demonstrate a Feasible Response to LIP
- Path 4: Demonstrate Effective Mitigation
- Path 5: Scenario Based Approach Non-bounded flood-causing mechanisms in Paths 1, 2, or 3 would only require a Focused Evaluation (FE) to complete the actions related to external flooding required by the March 12, 2012 10 CFR 50 .54(f) letter. Mechanisms in Paths 4 or 5 require an Integrated Assessment Turkey Point Units 3 and 4 followed Path 2, Demonstrate Effective Flood Protection, in accordance with NEI 16-05, Rev. 1, and utilized Appendices B and C to that document for guidance on evaluating the site strategy.
Turkey Point Units 3 and 4 L-2019-125 Docket Nos. 50-250 and 50-251 Page 3 of 3 On June 29, 2017, FPL submitted the Flooding Focused Evaluation for Turkey Point Units 3 and 4 (Reference 9), which included a list of planned changes (Reference 9, Table 2) to be implemented to ensure adequate Available Physical Margin (APM) and reliability of flood protection features credited for the reevaluated le'(els during a Probable Maximum Storm Surge (PMSS). The planned changes included changes to the manholes and conduit penetrations, which support the Local Intense Precipitation (LIP).
Based on the discussions with NRC Staff on May 22, 2019, FPL documents herein a commitment update by providing in the Enclosure the implementation plan for completing the planned changes for the identified (Reference 9, Table 2) flood protection features.
Should you have any questions regarding this submittal, please contact Mr. Robert J.
Hess, Turkey Point Licensing Manager, at 305-246-4112.
Si ess Licensing anager Turkey Point Nuclear Plant Enclosure cc: USNRC Regional Administrator, Region II USNRC Project Manager, Turkey Point Nuclear Plant USNRC Senior Resident Inspector, Turkey Point Nuclear Plant
Enclosure to L-2019-125 Turkey Point Units 3 and 4 Flooding Focused Evaluation Protection Feature Planned Changes Implementation Plan Flooding Implementation Planned Changes Protection Complete (Reference 9, Table 2)
Feature Due Date (Tracked via condition report AR 01977 483-03)
(Reference 9)
Install a removable 4 ft concrete block barrier at Stoplogs 1, 06/01 /21 Jersey Barriers 2, 16, 17, 18, 19, 20, 21, 22, 23, 24, SL-1, SL-2, and SL-4.
06/01/21 Flood Barrier Replace the existing CMU wall with a stronger/taller CMU Wall wall.
06/01/21 Stop logs Add additional weld metal to Stoplogs 16-22.
06/01/21 Stop logs Add reinforcing stiffeners to Stoplogs 16-24.
06/01/21 Replace existing anchors on Stoplogs 23 and 24 with Stop logs higher capacity mechanical/epoxy anchors.
06/01/21 Reinforce the CMU flood wall with rebar around Stoplogs 1 Stop logs and 15.
06/01/21 Stop logs Caulk/seal the identified Stoplogs before a flooding event.
06/01/21 Procure a new 12 in. drain plug rated for at least 10 ft of Drain Plug back pressure.
06/01/21 Install watertight sealing solution on the 23 manholes Manholes identified in NEE016-PR-001.
06/01/21 Conduit Install watertight seals on the 209 conduits identified in the Penetrations Flooding Hazards Modifications