Email to Tknowles, NFS Re Extension of Time to Submit Funding Instruments
ML19189A350
Person / Time
Site: Erwin
Issue date: 07/08/2019
From: Kevin Ramsey
NRC/NMSS/DFCSE/FLB
To: Knowles T
Nuclear Fuel Services
KMRamsey NMSS/FCSE/FLB 415.7506
References
Download: ML19189A350 (1)


Text

From:

Ramsey, Kevin To:

Knowles, Timothy A Cc:

Lopez-Santiago, Omar; Pitts, Leonard; Rivera Diaz, Carmen; Harris, Larry; Kline, Kenneth; Zimmerman, Jacob; Bartlett, Matt; Schwartzman, Adam

Subject:

Nuclear Fuel Services - Extension of time for submittal of funding instruments Date:

Monday, July 08, 2019 10:07:00 AM On June 24, 2019, we issued a letter providing interim approval of your decommissioning cost estimate and requesting submittal of funding instruments within 30 days of the date of the letter (ADAMS no. ML19172A121). We have considered your request for more time to obtain funding instruments from the Navy and financial institutions. We find good cause to extend the due date to 90 days from the date of the letter (September 23).

Please let me know if you have any questions.

Kevin M. Ramsey Senior Project Manager U.S. Nuclear Regulatory Commission 301-415-7506