OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 June 19, 2019 Mr. Mike Annacone Vice President, Columbia Fuel Operations and Manager, Columbia Plant Westinghouse Electric Company 5801 Bluff Road Hopkins, SC 29061

SUBJECT:

WESTINGHOUSE ELECTRIC COMPANY - CALENDAR YEAR 2020 SAFEGUARDS INSPECTION SCHEDULE

Dear Mr. Annacone:

Enclosed is the schedule of inspections to be performed by the US. Nuclear Regulatory Commission (NRC) inspectors at the Westinghouse Columbia Fuel Fabrication Facility for calendar year 2020. The inspection schedule is provided in advance to minimize the resource impact on your staff and allow for the resolution of any scheduling conflicts and personnel availability issues, well in advance of inspector arrival onsite.

Please note that inspections related to non-safeguards inspections are included in a separate letter. In addition, any other regional initiative or reactive inspection is not included. If circumstances arise which cause us to change the dates of the planned inspections, we will contact you to discuss the change as early as possible. Please contact Tom Vukovinsky at (404) 997-4622 with any questions or concerns you may have regarding this letter or the inspection schedule.

In accordance with Title 10 of the Code of Federal Regulations Section 2.390 of the NRC's Enclosure(s) transmitted herewith contain(s) SUNSI. When separated from enclosure(s),

this transmittal document is decontrolled.

LIMITED INTERNAL DISTRIBUTION PERMITTED OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION

OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION M. Annacone 2 Rules of Practice and Procedure, this letter and its enclosure contain sensitive information, and therefore, are exempt from public disclosure.

Sincerely,

/RA/

Eric C. Michel, Chief Projects Branch 2 Division of Fuel Facility Inspection Docket No. 70-1151 License No. SNM-1107

Enclosure:

Westinghouse CY 2020 Safeguards Inspection Schedule cc: (See page 3)

OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION

OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION M. Annacone 3 cc:

Ed Wills Manager Environment, Health and Safety Electronic Mail Distribution Nancy Parr Manager Licensing Electronic Mail Distribution Christine Kneece Manager Industrial Safety Electronic Mail Distribution Susan E. Jenkins Assistant Director, Division of Waste Management Bureau of Land and Waste Management Department of Health and Environmental Control Electronic Mail Distribution OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION