UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 June 19, 2019 Mr. Mike Annacone Vice President, Columbia Fuel Operations and Manager, Columbia Plant Westinghouse Electric Company 5801 Bluff Road Hopkins, SC 29061

SUBJECT:

WESTINGHOUSE ELECTRIC COMPANY - CALENDAR YEAR 2020 INSPECTION SCHEDULE

Dear Mr. Annacone:

Enclosed is the schedule of inspections to be performed by the U.S. Nuclear Regulatory Commission (NRC) inspectors at the Westinghouse Columbia Fuel Fabrication Facility for calendar year 2020. The inspection schedule is provided in advance to minimize the resource impact on your staff and allow for the resolution of any scheduling conflicts and personnel availability issues, well in advance of inspector arrival onsite.

Please note that inspections related to Safeguards are not included in this schedule. In addition, any regional initiative or other reactive inspection is not included. If circumstances arise which cause the NRC inspectors to change the dates of the planned inspections, we will contact you to discuss the change as early as possible. Please contact Tom Vukovinsky at (404) 997-4622 with any questions or concerns you may have regarding this letter or the inspection schedule.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice and Procedure, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's

M. Annacone 2 document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Eric C. Michel, Chief Projects Branch 2 Division of Fuel Facility Inspection Docket No. 70-1151 License No. SNM-1107

Enclosure:

Westinghouse 2020 Inspection Schedule cc: (See page 3)

M. Annacone 3 cc:

Ed Wills Manager Environment, Health and Safety Electronic Mail Distribution Nancy Parr Manager Licensing Electronic Mail Distribution Christine Kneece Manager Industrial Safety Electronic Mail Distribution Susan E. Jenkins Assistant Director, Division of Waste Management Bureau of Land and Waste Management Department of Health and Environmental Control Electronic Mail Distribution

ML19170A342 SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DFFI RII:DFFI RII:DFFI SIGNATURE KHS1 TAV1 ECM2 NAME KMcCurry TVukovinsky EMichel DATE 6/17/2019 6/ 18 /2019 6/ 19 /2019 E-MAIL COPY? YES NO YES NO YES NO

WESTINGHOUSE COLUMBIA FUEL FABRICATION FACILITY 2020 INSPECTION/ACTIVITY PLAN CALENDAR NRC Inspection 1 Dates February 24 - 28, 2020 Number of Inspectors 3 IP 88025 Maintenance and Surveillance of Safety Controls (1)

IP 88035 Radioactive Waste Processing, Handling, and Inspection Procedures (IPs)

Transportation (1)

IP 88050 Emergency Preparedness (1)

NRC Inspection 2 Dates May 11 - 15, 2020 Number of Inspectors 4 IP 88045 Effluent Control and Environmental Protection (1)

Inspection Procedures (IPs)

IP 88054 Fire Protection (Triennial) (3)

NRC Inspection 3 Dates June 15 - 19, 2020 Number of Inspectors 3 IP 88015 Nuclear Criticality Safety Program (1)

Inspection Procedures (IPs) IP 88020 Operational Safety (1)

IP 88030 Radiation Protection (1)

NRC Inspection 4 Dates November 30 - December 4, 2020 Number of Inspectors 3 IP 88015 Nuclear Criticality Safety Program (1)

Inspection Procedure (IP) IP 88020 Operational Safety (1)

IP 88070 Plant Modifications (1)

Enclosure