UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION II
245 PEACHTREE CENTER AVENUE NE, SUITE 1200
ATLANTA, GEORGIA 30303-1257
June 11, 2019
Orlando Hernandez
Security Manager, St. Lucie Nuclear Plant
Florida Power & Light Company
6501 South Ocean Drive
Jensen Beach, FL 34957
SUBJECT: ST. LUCIE NUCLEAR PLANT, UNITS 1 AND 2 - NRC SECURITY INSPECTION
REPORT 05000335/2019410 AND 05000389/2019410
Dear Mr. Hernandez:
On May 16, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed a security
inspection at your St. Lucie Nuclear Plant, Units 1 and 2, and discussed the results of this
inspection with Dan DeBoer and other members of his staff. The results of this inspection are
documented in the enclosed report.
No NRC-Identified or self-revealing findings were identified during the inspections.
This letter will be made available for public inspection and copying at
https://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room,
in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Binoy Desai, Chief
Plant Support Branch
Division of Reactor Safety
Docket Nos: 50-335 and 50-389
License Nos: DPR-67 and NPF-16
Enclosure:
NRC IR 05000335/2019410, and 389/2019410
cc: (See page 3)
O. Hernandez
2
cc:
Andrew Brady
Nuclear Fleet Security
Florida Power & Light Company
Mail Stop: NT3/JW
15430 Endeavor Drive
Jupiter, FL 33478
Mano Nazar
President and Chief Nuclear Officer
Nuclear Division
Florida Power & Light Company
Mail Stop EX/JB
700 Universe Blvd.
Juno Beach, FL 33408
Michael J. Snyder
Licensing Manager
St. Lucie Nuclear Plant
Florida Power & Light Co.
6501 S. Ocean Drive
Jensen Beach, FL 34957
Dan DeBoer
Site Director
Florida Power & Light Company
6501 S. Ocean Drive
Jensen Beach, FL 34957
SUNSI REVIEW COMPLETE
FORM 665 ATTACHED
OFFICE
RII:DRS/PSB
RII:DRS/PSB
RII:DRS/PSB
RII: DRS/PSB
RII:DRS/BR3
RII:DRS/PSB
SIGNATURE
ICH
OXS
JHW2
BBD
RXM1
BBD
NAME
I, Hall
O. Smith
J. Wallo
B. Desai
R. Musser
B. Desai
DATE
06/ 6 /2019
06/ 6 /2019
06/ 7 /2019
06/ 7 /2019
06/ 10 /2019
06/ 10 /2019
E-MAIL COPY
YES
NO
YES
NO
YES
NO
YES
NO
YES
NO
YES
NO
Enclosure
U.S. NUCLEAR REGULATORY COMMISSION
Inspection Report
Docket Numbers:
50-335 and 50-389
License Numbers:
Report Numbers:
05000335/2019410 and 05000389/2019410
Enterprise Identifier:
I-2019-410-0007
Licensee:
Florida Power and Light Company
Facility:
St. Lucie Nuclear Plant, Units 1 and 2
Location:
Jensen Beach, FL
Dates:
April 13 - 17, 2019
Inspectors:
Jon Wallo, Senior Physical Security Inspector
Otis Smith Jr., Senior Physical Security Inspector
Ivan C. Hall, Physical Security Inspector
Approved by:
Binoy Desai, Chief
Plant Support Branch
Division of Reactor Safety
2
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees
performance by conducting a Baseline Security Inspection at St. Lucie Nuclear Plant, Units 1
and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is
the NRCs program for overseeing the safe operation of commercial nuclear power reactors.
Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings were identified.
3
INSPECTION SCOPE
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in
effect at the beginning of the inspection unless otherwise noted. Samples were declared
complete when the IP requirements most appropriate to the inspection activity were met
consistent with Inspection Manual Chapter (IMC) 2201, Security Inspection Program for
Commercial Nuclear Power Reactors. The inspectors reviewed selected procedures and
records, observed activities, and interviewed personnel to assess licensee performance and
compliance with Commission rules and regulations, license conditions, site procedures, and
standards.
SAFEGUARDS
71130.05 - Protective Strategy Evaluation (2 Samples)
The inspectors evaluated the Protective Strategy and Security Performance Evaluation
Program. The following elements were evaluated from this IP dated January 1, 2019:
Protective Strategy Evaluation (2 Samples)
(1)
TIER I: all requirements
TIER II: 02.05 (a); 02.06 (a - g), (l - n); 02.07 (a - c)
TIER III: 02.08; 02.09 (b), (c); 02.11 (a)
(2)
The inspectors observed the performance of a licensee conducted exercise.
EXIT MEETINGS AND DEBRIEFS
On April 13, 2019, the inspectors presented the Baseline Security Inspection results to
Mr. DeBoer and other members of the licensee staff.
4
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description of Title
Revision No.
Procedures
Security Drills and Exercises
11
Adversary Force Training
3
Tampering
8
Vehicle and Material Searches
10
Weapons Maintenance
6
Security Posts and Patrols
5
Controlling Gates and Vehicle Barriers
4
Security Duty Performance
3
Escorting Vehicles and Materials
4
Condition
Reports
02298783
02216092
2208900
02227015
02249410
02260399
02267103
02267988