ML19123A133
ML19123A133 | |
Person / Time | |
---|---|
Site: | Summer |
Issue date: | 05/01/2019 |
From: | Renee Taylor NRC/RGN-II/DRP/RPB3 |
To: | Randy Musser NRC/RGN-II/DRP/RPB3 |
Rayn Taylor, RII/DRP | |
References | |
Download: ML19123A133 (3) | |
Similar Documents at Summer | |
---|---|
Category:Meeting Summary
MONTHYEARML24262A1082024-10-11011 October 2024
[Table view]September 9, 2024, Summary of Public Meeting Regarding Potential License Amendment Request Change to Core Operating Limits Report and Implement WCAP-17661 for V.C. Summer Nuclear Station, Unit No. 1 ML24222A6992024-08-16016 August 2024 August 6, 2024, Summary of Regarding Potential License Amendment Request Change to Surveillance Requirements for Moderator Temperature Coefficient for Millstone, Unit No. 3, North Anna, Unit Nos. 1 and 2, and Summer, Unit No. 1 - ML24124A1272024-05-0606 May 2024 April 22, 2024 Public Meeting Summary - 2023 Annual Assessment Meeting Re Virgil C. Summer Nuclear Station ML24036A2942024-02-13013 February 2024 Virgil. C. Summer Nuclear Station, Unit No. 1 - Summary of January 25, 2024, Public Meeting with Dominion Energy South Carolina, Inc. Concerning Review of New Seismic Hazard Information ML23325A2432023-11-13013 November 2023 Regulatory Conference Summary ML23325A2452023-11-13013 November 2023 Enclosure 2 - Dominion Slides ML23325A2442023-11-13013 November 2023 Enclosure 1 - Attendance List ML23331A7892023-11-0909 November 2023 Nov. 2023 Enviro Scoping Meetings Related to the V.C. Summer Subsequent License Renewal Application Meeting Summary ML23171A9172023-06-20020 June 2023 Summary of Meeting Concerning the V.C. Summer Nuclear Station, to Discuss Annual Assessment for Period Jan 1, 2022 Through December 31, 2022 ML22270A2042022-09-30030 September 2022 Summary of Meeting Regarding a Potential Request to Modify the Reactor Vessel Surveillance Capsule Withdrawal Schedule for VC Summer ML22151A3332022-05-31031 May 2022 Public Meeting Summary 2021 Annual Assessment Meeting Regarding the V.C. Summer Nuclear Station, Docket No. 50-395, Meeting Number 20220449 ML21131A1612021-05-11011 May 2021 Public Meeting Summary - 2020 Annual Assessment Meeting Regarding Virgil C. Summer Nuclear Station, Docket No. 50-395; North Anna Power Station, Docket Nos. 50-338 and 50-339; and Surry Power Station, Docket Nos. 50-280 and 50-281, Meeting ML20213B1672020-08-13013 August 2020 July 23, 2020, Summary Regarding Second Pre-Application Meeting to Discuss Proposed Technical Specification Task Force-425 License Amendment Request ML20181A0052020-07-13013 July 2020 June 24, 2020, Summary Regarding Pre-Application Meeting to Discuss Proposed Technical Specification Task Force-425 License Amendment Request (EPID-L-2020-LRM-0049) ML20105A1482020-04-10010 April 2020 Public Meeting Summary Virgil C. Summer Nuclear Station ML19196A2112019-08-0202 August 2019 July 23, 2019, Meeting Summary Regarding National Fire Protection Association 805 Supplement License Amendment Request ML19123A1332019-05-0101 May 2019 Public Meeting Summary - V.C. Summer Nuclear Station, Docket No. 50-395 to Provide Opportunities to Discuss Annual Assessment of V.C Summer Nuclear Station with the Public for Period of January 01, 20018 - December 31-2018 ML19086A0272019-04-12012 April 2019 April 4, 2019, Meeting Summary Regarding Pre-application Meeting to Discuss Two Proposed Relief Requests ML18144A1482018-05-24024 May 2018 Public Meeting Summary - Virgil C. Summer Nuclear Station Docket No. 50-395 ML18068A0272018-03-22022 March 2018 Summary of March 15, 2018, Pre-Application Meeting with South Carolina Electric and Gas Company to Discuss a Future NFPA-805 Amendment (EPID-L-2018-LRM-0015) ML17103A5222017-04-12012 April 2017 Annual Assessment Meeting Summary 2017 ML15126A1962015-05-0505 May 2015 April 16, 2015 Public Meeting Summary - Category 1 - Virgil C. Summer Nuclear Station Units 2 and 3 Annual Assessment ML15119A5102015-04-29029 April 2015 Meeting Summary with Members of the Public Concerning the Annual Assessment of of Virgil C. Summer Nuclear Station, Unit 1, in Blair, S.C ML14106A4762014-04-16016 April 2014 End of Cycle 2013 Public Meeting Memo ML13225A2932013-08-12012 August 2013 7/23-24/2013, Summary of Meeting 2013 U.S. Nuclear Regulatory Commission (NRC) Initial Exam Writers' Workshop ML13199A1772013-07-31031 July 2013 Summary, June 20, 2013 Category 1 Meeting with South Carolina Electric and Gas Company, to Discuss Voluntary Fire Protection Risk Initiative Self-Assessment ML13123A1472013-05-0303 May 2013 Summary of Category 1 Public Meeting with South Carolina Electric and Gas,Virgil C. Summer Nuclear Station, Units 2 and 3, Annual Assessment ML13119A4112013-04-29029 April 2013 Summary of Category 3 Public Meeting, Virgil C. Summer Nuclear Station, Unit 1, Annual Assessment ML13098A8442013-04-11011 April 2013 Summary of Meeting with South Carolina Electric & Gas to Discuss Proposed Emergency Plan Changes ML12157A0452012-06-0404 June 2012 5/24/2012 - Summary of Category 3 Public Meeting - Virgil C. Summer Nuclear Station Unit 1 Annual Assessment and NRC Construction Oversight of Units 2 and 3 Combined Licenses ML1120707482011-07-26026 July 2011 July 20, 2011, Meeting Summary Pre-Application Meeting with South Carolina Electric and Gas Regarding General License Independent Spent Fuel Storage Installation Plans (TAC No. L24544) ML11152A0802011-06-14014 June 2011 Summary of March 31, 2011, Meeting with South Carolina Electric and Gas Company to Discuss NFPA-805 License Amendment ML1115204542011-06-0101 June 2011 Summary of Public Meeting with South Carolina Electric & Gas Co., V. C. Summer to Discuss the NRC Reactor Oversight Process and Annual Assessment ML1023804682010-08-26026 August 2010 08/18/10 Summary of Meeting NRC Initial Exam Writer'S Workshop ML1016704282010-06-17017 June 2010 Meeting Summary Notice ML0930005732009-11-0505 November 2009 Summary of September 14, 2009, Public Conference Call to Discuss Responses to Generic Letter 2004-02 Requests for Additional Information ML0923803922009-08-26026 August 2009 08/11-12/2009-Summary of Meeting Re 2009 Us NRC Initial Exam Development Workshop ML0911000692009-04-17017 April 2009 Summary of Meeting with Public/Open House to Discuss NRC Reactor Oversight Process and the Annual Assessment of the Virgil C. Summer Nuclear Station ML0835204162008-12-16016 December 2008 Public Meeting Summary, Virgil C. Summer Nuclear Station, Docket No. 05-395 IR 05000395/20075022007-07-30030 July 2007 Summary of Public Meeting - Virgil C. Summer Nuclear Station, to Discuss Significance on Apparent Violation Documented in Inspection Report 50-395-07-502 ML0713500592007-05-11011 May 2007 Summary of Public Meeting with South Carolina Electric & Gas Company to Brief the Licensee'S Post Outage Review of Refueling Outage 16 at Virgil C. Summer Nuclear Station IR 05000395/20070022007-04-30030 April 2007 IR 05000395-07-002; on 01/01/2007 - 03/31/2007 for South Carolina Electric & Gas Company; Virgil C. Summer Nuclear Station, Integrated Inspection Report and Annual Assessment Meeting Summary ML0627605282006-10-24024 October 2006 September 13, 2006, Summary of Meeting with South Carolina Electric & Gas Re Generic Letter 96-06 (TAC No. M96872) ML0627800022006-10-0404 October 2006 Summary for Meeting Between NRC and South Carolina Electric & Gas Company Refueling Outage 16 at Virgil Summer ML0621305672006-08-0101 August 2006 Summary of 07/19 - 07/20/2006 Meeting - 2006 Initial Exam Development Workshop ML0609601222006-04-0303 April 2006 Summary of Meeting with South Carolina Electric & Gas Company to Discuss the Results of the Root Cause Evaluation for the High Failure Rate on the January 10, 2006, Operator Licensing Initial Written Examination ML0601705522006-01-17017 January 2006 Comment Card Responses During January 9 Through 10, 2006, NRC Public Workshop ML0600304322005-12-30030 December 2005 Public Meeting Summary - Oct. 18, 2005 Category 1 Public Meeting-Summer, Docket # 50-395 ML0509704712005-04-0707 April 2005 Meeting Summary - Public Meeting - Virgil C. Summer Nuclear Power Station ML0504901422005-02-17017 February 2005 Summary of January 13, 2005, Meeting Between the U.S. Nuclear Regulatory Commission (NRC) and Nuclear Energy Institute (NEI) on Updating the License Renewal Guidance Documents 2024-08-16 Category:Memoranda MONTHYEARML24222A6992024-08-16016 August 2024
[Table view]August 6, 2024, Summary of Regarding Potential License Amendment Request Change to Surveillance Requirements for Moderator Temperature Coefficient for Millstone, Unit No. 3, North Anna, Unit Nos. 1 and 2, and Summer, Unit No. 1 - ML24124A1272024-05-0606 May 2024 April 22, 2024 Public Meeting Summary - 2023 Annual Assessment Meeting Re Virgil C. Summer Nuclear Station ML23325A2022024-01-16016 January 2024 CFR Part 52 Construction Lessons-Learned Report ML23331A7912023-12-0606 December 2023 Nov. 2023 Enviro Scoping Meetings Related to the V.C. Summer Subsequent License Renewal Application Meeting Summary Memo ML23171A9172023-06-20020 June 2023 Summary of Meeting Concerning the V.C. Summer Nuclear Station, to Discuss Annual Assessment for Period Jan 1, 2022 Through December 31, 2022 ML22270A2042022-09-30030 September 2022 Summary of Meeting Regarding a Potential Request to Modify the Reactor Vessel Surveillance Capsule Withdrawal Schedule for VC Summer ML21160A0312021-07-12012 July 2021 10 CFR Part 52 Lessons-Learned with Construction at Vogtle 3 & 4 and V.C. Summer 2 & 3 ML21131A1612021-05-11011 May 2021 Public Meeting Summary - 2020 Annual Assessment Meeting Regarding Virgil C. Summer Nuclear Station, Docket No. 50-395; North Anna Power Station, Docket Nos. 50-338 and 50-339; and Surry Power Station, Docket Nos. 50-280 and 50-281, Meeting ML20105A1482020-04-10010 April 2020 Public Meeting Summary Virgil C. Summer Nuclear Station ML19123A1332019-05-0101 May 2019 Public Meeting Summary - V.C. Summer Nuclear Station, Docket No. 50-395 to Provide Opportunities to Discuss Annual Assessment of V.C Summer Nuclear Station with the Public for Period of January 01, 20018 - December 31-2018 ML18144A1482018-05-24024 May 2018 Public Meeting Summary - Virgil C. Summer Nuclear Station Docket No. 50-395 ML17103A5222017-04-12012 April 2017 Annual Assessment Meeting Summary 2017 ML16218A4722016-08-0505 August 2016 Wectec, LLC, Commitment for Ongoing Compliance to Confirmatory Order EA-12-189 and EA-13-196 ML16068A3882016-03-0909 March 2016 Memo Ico Staff Review of V.C. Summer Nuclear Station Physical Security Plan Rev. 15 (NS113625) for Verification of ASM Order (EA-13-228) Implementation (CAC L25088) ML16061A5252016-02-26026 February 2016 Memo T Mossman, NSIR, Technical Assistance Request - Review of Physical Security Plan for the Virgil C. Summer Nuclear Station ISFSI (72-1038, 50-395) (L25088) ML15119A5102015-04-29029 April 2015 Meeting Summary with Members of the Public Concerning the Annual Assessment of of Virgil C. Summer Nuclear Station, Unit 1, in Blair, S.C ML14106A4762014-04-16016 April 2014 End of Cycle 2013 Public Meeting Memo ML13275A3102013-11-25025 November 2013 Cover Memo from Robert Caldwell to Robert Pascarelli, RAI for V C Summer Revision 10 Security Plan Review ML13142A1572013-05-29029 May 2013 Update for 06/20/13 Meeting Notice with South Carolina Electric & Gas Company Regarding Voluntary Fire Protection Risk Initiative Self Assessment ML13122A1782013-05-13013 May 2013 Notice of Forthcoming Meeting with South Carolina Electric & Gas Company Regarding Voluntary Fire Protection Risk Initiative Self Assessment ML13067A2592013-03-11011 March 2013 Forthcoming Meeting with South Carolina Electric & Gas Company Regarding Proposed Emergency Plan Change for Virgil C. Summer Nuclear Station, Unit No. 1 ML12325A4322012-11-26026 November 2012 Verbal Approval of Alternative for Overlay Repair of Reactor Vessel Head Penetrations ML12333A1252012-11-0808 November 2012 FEMA Memo from C. Burnside to Regional Assistance Committee Discussing the VC Summer Nuclear Station 10-Mile EPZ Boundary Change Request ML1120707482011-07-26026 July 2011 July 20, 2011, Meeting Summary Pre-Application Meeting with South Carolina Electric and Gas Regarding General License Independent Spent Fuel Storage Installation Plans (TAC No. L24544) ML1106800552011-03-0909 March 2011 Notice of Forthcoming Meeting with South Carolina Electric & Gas Company, (Sce&G), to Discuss NFPA 805 License Amendment for Virgil C. Summer Nuclear Station, Unit 1 ML1016704282010-06-17017 June 2010 Meeting Summary Notice ML1009200352010-05-17017 May 2010 Staff Review of WCAP-16571-P Referenced in Virgil C. Summer'S GL 2004-02 Supplemental Response for Downstream Effects Evaluations of Components ML1009105332010-04-0505 April 2010 U.S. Nuclear Regulatory Commission Staff Review of the Department of Homeland Security Consultation Reports ML0924606222009-09-0303 September 2009 Forthcoming Conference Call with South Carolina Electric & Gas, to Discuss the Licensee'S Planned Response to the Nrc'S Request for Additional Information Pertaining to Generic Letter 2004-02, Potential Impact of Debris ML0807400842008-03-14014 March 2008 Draft Regulatory Guide for Comment ML0617805592006-07-10010 July 2006 Revised Closeout Letter for Bulletin 2003-01, Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized-Water Reactors. ML0618101822006-07-0707 July 2006 Presentation Materials: Crack Growth Rates in a PWR Environment of Nickel-Base Alloy Welds from the Davis-Besse and V.C. Summer Plants, by Bogdan Alexandreanu, Omesh Chopra, and Bill Shack ML0615302842006-06-0505 June 2006 Notice of Meeting with South Carolina Electric & Gas Company Online Monitoring of Instrument Channel Performance at V. C. Summer ML0608000022006-03-22022 March 2006 Memo, Response to TIA 2005-04 Tornado Missile Vulnerability ML0516505112005-08-16016 August 2005 Closeout Letter for Bulletin 2003-01, Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized-water Reactors. ML0514604012005-05-25025 May 2005 Ltr., Correction of License Authority ML0504901422005-02-17017 February 2005 Summary of January 13, 2005, Meeting Between the U.S. Nuclear Regulatory Commission (NRC) and Nuclear Energy Institute (NEI) on Updating the License Renewal Guidance Documents ML0421003322004-06-30030 June 2004 Close-out of Tacs Relating to the Review of 35-day Letters Submitted in Response to the April 29, 2003, Orders Revising the Design Basis and Security Guard Force Training Enhancements and Physical Fitness Requirements ML0408600142004-04-28028 April 2004 Renewal of Full-Power Operating License for Virgil C. Summer Nuclear Station, Unit 1 - Memo to Comm. from W. Travers ML0404104222004-02-0404 February 2004 Request Approval of Excused Absence for Employees Affected by Inclement Weather Conditions ML0327900132003-10-0303 October 2003 Summary of Telecommunication (Telecon) with South Carolina Electric and Gas (Sce&G) Company Representatives to Discuss Staff Questions on 10 CFR 54.4(a)(2) Criteria, and Responses to Requests for Additional Information Pertaining to the Lic ML0326810252003-09-24024 September 2003 Results of the Virgil C. Summer SDP Phase 2 Notebook Benchmarking Visit ML0307805472003-03-19019 March 2003 Revisions to ESFAS Technical Specifications Request for Additional Information ML0229703632002-10-23023 October 2002 Meeting with NEI, Surry & North Anna Units 1 & 2, McGuire & Catawba Units 1 & 2, Peach Bottom Units 2 & 3, St. Lucie Units 1 & 2, Fort Calhoun, H. B. Robinson Unit 2, R.E. Ginna, and Virgil C. Summer. the Proposed Agenda Is Attached ML0227704612002-09-27027 September 2002 Evaluation of Reactor Pressure Vessel Nozzle to Hot-leg Piping Bimetallic Weld Joint Integrity for the V.C. Summer Nuclear Power Plant, Figures 21 - 70 ML0227602642002-09-27027 September 2002 Evaluation of Reactor Pressure Vessel Nozzle to Hot-leg Piping Bimetallic Weld Joint Integrity for the V.C. Summer Nuclear Power Plant, Memorandum Dated 09/27/02 - Figure 20 ML0215706002002-06-0606 June 2002 V. C. Summer - Telephone Conference Reactor Vessel Head Inspection Results NRC Generic Letter 1989-111989-06-30030 June 1989 NRC Generic Letter 1989-011: Resolution of Generic Issue 101 Boiling Water Reactor Water Level Redundancy 2024-08-16 |
Contents
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 May 1, 2019 MEMORANDUM TO: Randall A. Musser, Chief Rector Projects Branch 3 Division of Reactor Projects FROM: Ryan C. Taylor, Senior Project Engineer /RA/
Reactor Projects Branch 3 Division of Reactor Projects
SUBJECT:
PUBLIC MEETING
SUMMARY
- V.C. SUMMER NUCLEAR STATION, DOCKET NO. 50-395 On April 25, 2019, the Nuclear Regulatory Commission staff met with members of the public concerning the annual assessment of V.C. Summer Nuclear Station, Unit 1. The meeting was held at McCrory-Liston Elementary School in Blair, SC. The purpose of the meeting/open house session was to provide opportunities to discuss the annual assessment of the V.C. Summer Nuclear Station with the public for the period of January 1, 2018 -
December 31, 2018. Enclosed are a list of attendees.
Docket Nos.: 50-395 License Nos.: NPF-12
Enclosure:
As stated CONTACT: Ryan Taylor, RII/DRP 404-997-4630
ML19123A133 OFFICE RII:DRP NAME R Taylor DATE 05/01/19 Enclosure