Draft Environmental RAIs for Surry Subsequent License Renewal Application Date:
Friday, April 05, 2019 11:23:03 AM Attachments:
surry rais 4-4-19 r1.pdf image001.png Mr. Banks,
By letter dated October 15,2018, (Agencywide Documents Access and Management System (ADAMS) Accession No.ML18291A842), Dominion Energy submitted an application for subsequent license renewal of Renewed Facility Operating License Nos.
DPR-32 and DPR-37 for the Surry Power Station, Unit Nos. 1 and 2 (Surry) to the U.S.
Nuclear Regulatory Commission (NRC) pursuant to Section 103 of the Atomic Energy Act of 1954, as amended, and part 54 of title 10 of the Code of Federal Regulations, Requirements for renewal of operating licenses for nuclear power plants.
The NRC staff is in the process of reviewing your application. Based on our review, the NRC staff has identified the attached draft requests for additional information (RAIs).
Please contact the following at your earliest convenience to schedule a clarification call, if needed.
Mr. Tam Tran, Project Manger Division of Materials and License Renewal Office of Nuclear Reactor Regulation (NRR)
U.S. Nuclear Regulatory Commission
Sincerely,
Eric R. Oesterle / Chief License Renewal Project Branch (MRPB)
Division of Materials and License Renewal (DMLR)
Office of Nuclear Reactor Regulation (NRR) 301-415-1014