ML19095A275

From kanterella
Jump to navigation Jump to search
Response to Request for Additional Information on Steam Generator Replacement, Schedule to Submit by 4/14/1978
ML19095A275
Person / Time
Site: Surry  
Issue date: 03/14/1978
From: Stallings C
Virginia Electric & Power Co (VEPCO)
To: Case E, Schwencer A
Office of Nuclear Reactor Regulation
References
Serial No. 132
Download: ML19095A275 (1)


Text

,Ii. -- ~,

l.*

Mr. Edson G. Case, Acting Director Office of Nuclear Reactor Regulation Attn:

Mr. Albert Schwencer, Chief Serial No.

  • T32*;

LQA/DWSjr:jdt Operating Reactors Branch No. 1 Division of Reactor Licensing U.S. Nuclear Regulatory Commission Washington, D. C.

20555 Docket Nos.

50-280 50-281 License Nos. DPR-32 DPR-37

Dear Mr. Case:

Related to the Nuclear Regulatory Commission's review of the Surry Power Station steam generator replacement originally submitted*

August 8, 1977, we have-received four sets of requests for additional information.. The 1 etters of transmitta 1 for these sets of questions were dated December 27, 1977, January 20, 1978, February 1, 1978, and February 2, 1978 and had varying requested target dates for response.

Due to rescheduling of the replacement outage as discussed in our February 14, 1978 letter, we have also rescheduled the submittal of the additional information.

It is currently our schedule to provide the information re-quested in the four sets of questions by April 14, 1978.

cc:

Mr. James P. O'Reilly, Director Very truly yours, Zp,_}11 J~z;i,r C. M. Sta 11 i n gs Vice President-Power Supply and Production Operations Office of Inspection & Enforcement Region II

' '