A NAC INTERNATIONAL April 3, 2019 U.S. Nuclear Regulatory Commission 11555 Rockville Pike Rockville, MD 20852-2738 Attn:
Document Control Desk Atlanta Corporate Headquarters 3930 East Jones Bridge Road, Suite 200 Norcross, GA 30092 Phone 770-447-1144 Fax 770-447-1797 www.nacintl.com
Subject:
Correction to Dates to the Submission of Final Safety Analysis Report (FSAR), Revision 10, for the NAC MAGNASTOR Cask System
References:
Docket No. 72-1031
- 1. ED20170082, Submission of Final Safety Analysis Report (FSAR), Revision 9, for the NAC MAGNASTOR Cask System, October 17, 2017
- 2. ED20190001, Submission of Final Safety Analysis Report (FSAR), Revision 10, for the NAC MAGNASTOR Cask System, January 31, 2019 NAC International (NAC) submitted its NAC MAGNASTOR Cask System partial biennial update on January 31, 2019. The dates listed for the biennial update period in the last sentence of the second paragraph should have been "October 3, 2017 and February 1, 2019" instead of "October 3, 2017 and February 1, 2017".
NAC submitted its biennial update in two parts. The first part occurring on October 17, 2017 (Reference 1) which covered February 5, 2017 through October 3, 2017. The second part was submitted on January 31, 2019 (Reference 2) and covered the period of October 3, 2017 through February 1, 2019. These two submittals (Reference 1 and 2) satisfy the requirements for the 10 CFR 72.48 biennial update.
If you have any comments or questions regarding this submittal, please contact me on my direct line at 678-328-1236.
Since'M-Wren Fowler Director, Licensing Engineering