In Response to Letter of 8/12/1976 Concerning Plant Operation & Equipment Failure During Degraded Grid Voltage Condition, Advising, Thorough Evaluation Is in Progress & Request Deadline as 10/1/1976
ML19094A904
Person / Time
Site: Surry  Dominion icon.png
Issue date: 09/15/1976
From: Stallings C
Virginia Electric & Power Co (VEPCO)
To: Rusche B
Office of Nuclear Reactor Regulation
References
Serial No. 197 /081276
Download: ML19094A904 (1)


Text

VIRGINIA ELECTRIC.A.ND POWER COMP.A.NY RIOHMOND,VIRGINIA 23261 September.15, 1976 Mr. Benard C. Rusche Director of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D. C.

20555 Attn:

Mr. Robert W. Reid, Chief Operating Reactors Branch 4

Dear Mr. Rusche:

Serial No. 197 /081276 PO&M/ALH:clw Docket Nos. 50-280 50-281 License Nos. DPR-32 DPR-37 This is in response to your letter of August 12, 1976 concerning plant operation and equipment failures during a degraded grid voltage condition.

A thorough evaluation of the problem is in progress, but it will not be possible for us to submit a formal report within the 30-day period required in your letter.

We, therefore, request that a deadline of October 1, 1976 be assigned to this project.

Very truly yours, z!J.m. '0iaa:.r C. M. Stallings Vice President-Power Supply and Production Operations