C./

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND,V:CBGINXA 23261 November 2,: 1977,.

Mr. Robert.A. Clark, Chief Reactor Saf.eguards Licensing Branch Division of Operating Reactors Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D. C.

20555

Dear Mr. Clark:

Serial No. 428B PO&M/TAP:wbh Docket Nos. 50-280 50-281 License Hos. DPR-32 DPR-37 Several construction projects are to be resolved at our Surry Power Station in the next two weeks.

These decisions may affect security related protected area boundaries.

In an effort to eliminate an immediate revision to the Security Plan, we are requesting a delay of 30 days on our submittal date to November 30, 1977.

cc:

Mr. James P. O'Reilly Very truly yours,

~Jl?. \\~~,~F C. M. Stallings Vice President-Power Supply and Production Operations