r~ i,: E ! V rn fHSTRilam'lijff
..ne b
1 1980 D1STRH3UTION SERVrC.1:.c~-cem er BRANCH Mr. James P. O'Reilly, Director Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Region II 101 Marietta Street, Suite 3100 Atlanta, Georgia 30303
Dear Mr. O'Reilly:
Serial No. 957 NO/RGS:jmj Docket Nos:
50-280 50-281 50-338 License Nos : DPR-32 DPR-37 NPF-4 IE BULLETIN 79-0lB (DECEMBER 1, 1980 REVISION)
SURRY POWER STATION *UNIT NOS. 1 AND 2
.:rJ NORTH ANNA POWER STATION UNIT NO. 1 > b 6 ff D This is in response to IE Bulletin 79-0lB:
"Enviromnental Qualification of Class lE Equipment" and the NRC "Order for Modification of License" dated August 29, 1980 on enviromnental qualification of electrical equipment.
This revision to the November 1, 1980, submittal provides the results of further evaluation on the qualification of equipment with insufficient information and the schedule for corrective action.
The results of this review are provided in the enclosed revision packages for our previous submittals of IE Bulletin 79-0lB:
VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION UNIT 1 IE BULLETIN 79-0lB DAY REVIEW REVISION 2 DECEMBER 1, 1980 VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION UNIT 2 IE BULLETIN 79-0lB 90-DAY REVIEW REVISION 2 DECEMBER 1, 1980
.* -------~-**--*-------*'-'-*-------------------.-----
~
....... __ *--*- --*~~-- *-............. --***
VIBOlNIA Eucrmc AND POWEB CoKPANY TO.
Mr. James P. O'Reilly VIRGINIA ELECTRIC AND POWER COMPANY NORTH ANNA POWER STATION UNIT 1 IE BULLETIN 79-0lB 90 DAY REVIEW REVISION 2 DECEMBER 1, 1980 The revisions to the 90-Day reports are outlined on the enclosed "Tabulation of Changes" list which should guide you in updating your 90 DAY REVIEW copies.
Our comments on Supplement 2 to IE Bulletin 79-0lB are supplied in the text of this report. Review of the Cold Shutdown and future TMI Action Plan requirements in Supplement 2 will be submitted by February 1, 1981, as specified in Supplement 3 to IE Bulletin 79-0lB _dated October 24, 1980.
Qualification information for installed TMI equipment is provided for your review in the following supplements to the IE Bulletin 79-0lB reports:
VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION UNIT 1 IE BULLETIN 79-0lB REVISION 2 TMI REVIEW SUPPLEMENT 3 VIRGINIA ELECTRIC A.i,"qD POWER COMPANY SURRY POWER STATION UNIT 2 IE BULLETIN 79-0lB REVISION 2 TMI REVIEW SUPPLEMENT 3 VIRGINIA ELECTRIC AND POWER COMPANY NORTH ANNA POWER STATION UNIT 1 IE BULLETIN 79-0lB REVISION 2 TMI REVIEW SUPPLEMENT 3 2
On October 1, 1980, we received a request from the NRC Office of Nuclear Reactor Regulation to provide pertinent information relative to enviromnental qualifi-cation tests to be conducted within the next two years on equipment used or to be used in our facilities.
We indicated in our November 7, 1980 response that a determination would be made by December 1, 1980 whether certain cable installed in our Surry facility would be tested or replaced. Based on our present schedule, this activity will not be completed until the first quarter of 1981.
- --- l VIHOlNIA. ELBCTHIC A];1) PowzH COXPANY TO*
Mr. James P. O'Reilly 3
.If we can be of assistance in clarifying or interpreting this revision to the 90-Day reports, please advise.
Very truly yours,
~
Manager - Nuclear Operations and Maintenance Enclosures (6) cc: Mr. Victor Stello, Director (Enclosures-48)
NRC Office of Inspection and Enforcement Division of Reactor Operations Inspection Washington, D.C.
20555 Dr. Zoltan R. Rosztoczy, Branch Chief (Enclosures-6)
NRC Equipment Qualification Branch Division of Engineering Washington, D.C.
20555
. -.. _____... _,..~- -~0--................. _~ '-=-"-.:..--
\\..._....
COMMONWEALTH OF VIRGINIA
) ) s. s.
CITY OF RICHMOND
)
Before me, a Notary Public, in and for the City and Common-wealth aforesaid, today personally appeared B. R. Sylvia, who being duly sworn, made oath and said (1) that he is Manager-Nuclear Operations and Maintenance of the Virginia Electric and Power Company, (2) that he is duly authorized to execute and file the foregoing statements in behalf of that Company, and (3) that the statements are true to the best of his knowledge and belief.
,~
D Given under my hand and notarial seal this.L._____ day of
_gC&fY'4~
, 1q8'0.
My Co11Dllission expires ~
(SEAL)