ML19092A162

From kanterella
Jump to navigation Jump to search
Transmittal of Final Clinton Power Station Accident Sequence Precursor Report
Date released: 04/05/2019 Download: ML19092A162


Transmittal of Final Clinton Power Station Accident Sequence Precursor Report (Licensee Event Report 461 2017 010)
ML19092A159
Person / Time
Site: Clinton Constellation icon.png
Issue date: 04/03/2019
From: Joel Wiebe
Plant Licensing Branch III
To: Stoner T R
Exelon Generation Co
Wiebe J S 415-6606
References
Download: ML19092A159 (4)
Final Accident Sequence Precursor Analysis - Clinton Power Station, Division 1 Transformer Failure Leads to Instrument Air Isolation to Containment Requiring a Manual Reactor Scram (LER 461-2017-010) - Precursor
ML19050A510
Person / Time
Site: Clinton Constellation icon.png
Issue date: 03/21/2019
From:
NRC/RES/DRA
To:
Chris Hunter 415-1394
References
LER 2017-010-002
Download: ML19050A510 (20)