Final Dco RIC 2019 Presentation Clean
ML19077A312
Person / Time
Issue date: 03/18/2019
From: Nicole Coovert
NRC/RGN-II
To:
Sakadales A
References
Download: ML19077A312 (8)


Text

NRC Preparations for Transition from Construction to Operations Nicole Coovert Chief (Acting), Division of Construction Oversight, Inspection Branch-1 U.S. Nuclear Regulatory Commission (NRC),

Region II

Key Messages

  • Construction program lessons learned are improving inspection efficiency and maintaining effectiveness
  • Innovative project oversight and planning are ensuring NRC readiness for construction completion and test activities Vogtle Unit 3 Containment December 2018 Courtesy of Georgia Power Company
  • NRC startup test observations at Sanmen Nuclear Power Station support inspection readiness

Agenda

  • Effectively meeting construction and operational inspection challenges
  • Implementing innovative project oversight
  • Leveraging international experience Vogtle Unit 4December 2018 Courtesy of Georgia Power Company

Effectively Meeting Construction and Operational Inspection Challenges

  • NRC organizational structure established the foundation for transition to operations
  • The NRC is effectively implementing inspections using well-qualified staff Inspector Observing Accumulator Lift Inspector Performing Safety-Related Rebar Inspection

Effectively Meeting Construction and Operational Inspection Challenges (cont.)

  • Well-established programs and processes
  • Integrated use of metrics
  • Diverse communication tools NRC Public Web Site Link:

https://www.nrc.gov/reactors/new-reactors/new-licensing-files/vog3-itaac-dshbrd.pdf https://www.nrc.gov/reactors/new-reactors/new-licensing-files/vog4-itaac-dshbrd.pdf

Implementing Innovative Project Oversight

  • Vogtle Readiness Group establishes oversight, guidance, and resources for the transition to operations
  • Integrated Project Plan (IPP) supports agency action consistent with the licensees schedule

Leveraging International Experience

  • The NRC observed AP1000 startup program implementation
  • NRC readiness is enhanced through knowledge transfer Top of Steam Generator Sanmen Unit 2 Technical Training Center AP1000 Simulator

Questions?