~.-. ' L Public Service Electric and Gas Company 80 Park Place Newark, N.J. 07101 Pho11e 201 /622-7000 Mr. A. Gia.mbusso Deputy Director for Reactor Projects Directorate of Licensing U. S. Atomic Energy Commission Washington, D. C.

20545

Dear Mr. Giambusso:

CHANGE IN FUEL DESIGN NO. 1 AND 2 UNITS DOCKET NOS. 50-272 April 13, 1973 In view of the current emergency core cooling and fuel densification issues, we have evaluated the schedule and cost effects associated with changing to the 17 x 17 fuel design for the Salem units.

We have elected to utilize the Westinghouse 17 x 17 fuel design for the initial cores of Salem Units 1 and 2.

The new fuel load dates are estimated to be January, 1975 for Unit 1 and October, 1975 for Unit 2.

.,~

CC Dr. J. M. Hendrie Very truly yours, F. W. Schneider Manager of Engineering Electric Engineering Department Deputy Director for Technical Review The Energy People 25:11 95-?001 14DnMl 7-72