PS~G e REGULATORY DOCKET f!l£90?Y Public Service Electric and Gas Company 80 Park Place Newark, N.J. 07101 Phone 201/430-7000 t.J September 8, 1978
,._)
-*.I C.:..i
-::..:. ~;~~
-,(._
U. s. Nuclear Regulatory Commission Washington, D.C.
20555 Attention:
Mr. D. B. Vassallo, Assistant Director For Light Water Reactors Division of Project Management Gentlemen:
APPENDIX I TECHNICAL SPECIFICATIONS SALEM NUCLEAR GENERATING STATION DOCKET NOS. 50-272 AND 50-311 C-)
Pl
(/"*
On August 1, 1978, you wrote to PSE&G requesting that we submit the proposed Appendix I Technical Specifications for Salem Unit No. 2 utilizing guidance enclosed in your letter within sixty days.
Previously, on July 11, 1978, the Assistapt Director for Engineering and Projects of the Division of Operating Reactors wrote a similar letter requesting that we submit proposed Appendix I Technical Specifications for Salem Unit No. 1.
We were requested to respond within 180 days of the July 11, 1978 date.
In as much as Salem 1 and Salem 2 are located on the same site and are essentially duplicates of each other, we propose that a common submittal be made by PSE&G to comply with both requests from NRC.
We propose that the 180 day schedule established for Salem Unit No. 1 should be the basis of our combined submittal.
The Energy People
--~
- 9/8/78 We would be pleased to meet with you and your staff to discuss our submittal schedule if there are any questions.
Please contact Mr. E. A. Liden, the Project Licensing Manager for Salem, if you have any additional questions on this matter.
Very truly yours, R1¥:~
R. L. Mittl General Manager -