Draft AMT Action Plan Deliverables and Schedule Table 01-25-2019
ML19029B372
Person / Time
Issue date: 01/25/2019
From: David Rudland
Division of Materials and License Renewal
To:
David Rudland, NRR/DMLR, 415-1896
References
Download: ML19029B372 (2)


Text

DRAFT 01/25/2019 DRAFT DRAFT Action Plan Table:

Advanced Manufacturing Technologies, Deliverables and Schedule Problems/Gaps that Need to be Addressed:

To prepare the NRC staff for regulatory submittals containing parts and components manufactured using Advanced Manufacturing Technologies (AMTs). To identify and rectify regulatory challenges and gaps associated with the review of AMT submittals. To provide guidance and tools for review consistency, communication and knowledge management for the efforts associated with AMT approvals. To provide transparency to stakeholders on the process of AMT approval.

Task1 Description Lead Actions/Deliverables2 Schedule3 Completion Status 1

Near Term Need -

Initial AMT NRR 1.1 Public meeting on the action plan 1 months NRR/RES 1.2 Short term interactions - RIC, Materials meetings, prior interactions (RAR) 2 months NRR 1.3 Memo to Division Directors on candidate AMT method and timeframe for use 3 months NRR/RES 1.4 Information gathering for initial AMT: Prior knowledge, Site visits, contractor support, public meetings, training 4 months NRR/RES 1.5 Develop document on the essential safety differences between the proposed initial AMT and traditional manufacturing and the aspects of the technology not addressed by codes, standards and regulations 4 months NRR 1.6 Develop presentations/documents on initial AMT pertaining to 50.59 (or 72.48) implementation 4 months 2

Continuing Need RES 2.1 External interaction plan development 2 months 1 Some activities are directly dependent on information from external organizations. Staff may have to make assumptions to provide deliverables.

2 The bold items represent the major deliverables identified in the action plan 3 The current schedule assumes that an AMT component will be installed within 12 months. The ongoing activities listed are assumed to be occurring over that time. This action plan will be revisited and revised periodically.

DRAFT 01/25/2019 DRAFT Task1 Description Lead Actions/Deliverables2 Schedule3 Completion Status NRR/RES 2.2 Continued external communication with vendors, licensees and EPRI for future AMTs Ongoing NRR 2.3 Update Task 1.3 Memo as other AMTs are proposed As needed NRR/RES 2.4 Continued Information gathering for future AMTs: Site visits, contractor support, public meetings, training Ongoing NRR/RES 2.5 Continued interaction in Codes and Standards Ongoing NRR 2.6 Continued internal interactions between the AMT agency team Ongoing NRR/RES 2.7 Develop a document that describes the generic technical information needed in AMT submittals.

6 months NRR 2.8 Public meeting 7 months 3

Determine if guidance update is necessary NRR 3.1 Determine if any changes are needed Ongoing NRR 3.2 Develop a memo to Division Directors recommending a path forward on guidance development or modification 8 months 4

Knowledge management RES 4.1 Develop plan for Knowledge Management 6 months 5

Update action plan NRR 5.1 Evaluate the need to update plan and revise accordingly 6 months and ongoing