ENCLOSURE 4 SHINE MEDICAL TECHNOLOGIES, INC.
MEETING SLIDES FOR THE JANUARY 29 AND 30, 2019 MEETING BETWEEN SHINE MEDICAL TECHNOLOGIES, INC. AND THE NRC SHINE CONSTRUCTION PLANNING PUBLIC VERSION 7 pages follow
Construction Planning Arie Cowne, Construction Manager Health. llluminated 1
Construction Planning - Introduction 11 SHINE is responsible and will provide oversight of Construction activities
- SHINE intends to contract with Baker Concrete Construction as the GC for the project
- Previous experience working at Part 50 facility (V.C. Summer)
- Previous experience working with Baker at Urenco USA (Part 70)
- Baker assisted SHINE with preconstruction efforts (2 years) 11 Baker is on SHINE's ASL for QL-1 Procurement and Construction 11 Baker will implement their Safety Program to manage Construction work activities 11 Baker will work under SHIN E's Corrective Action Program
- Baker planning on peak staffing of 250-300; average around 150 111 Baker construction schedule is 24 months SHINE Medical Technologies I 2
Construction Planning - Building & Infrastructure Organization Chart SHI NE CEO I
~
Regulatory Affairs SHI NE Construction SHINE SHINE Document SHINE Engineering Management Configuration ----*
Control
-1 SHINE QA/ QC Management I
I I
I I
+
I I
I I
Baker Project I
I Exec.
I 1-----* Baker QA/QC I
I I
I
__ J l
I "'---------.
Baker Baker Baker Baker Baker Enginee ring Construct ion Procurement Safety Document Control Management I
I I
Baker Subcontractors I
+
SHINE Medical Technologies I 3
Construction Planning - Procurement 11 SHINE will purchase the majority of plant process equipment
- Baker will purchase: concrete, structural steel, architectural finishes, auxiliary system components (i.e., HVAC, electrical power distribution, etc.) and related infrastructure (i.e., cable trays, pipe supports, etc.)
- SHINE contractually flows down Design requirements to Baker 11 Baker will use SHIN E's Document Control for Design Input
- Baker will use internal Document Control for Procurement and Construction documentation 11 Concrete and rebar will be Commercial Grade Dedicated 11 Structural steel will be purchased QL-1 11 SHINE/ AE of record review and approve Building shop drawings and submittals SHINE Medical Technologies I 4
Construction Planning - Construction
- Baker will subcontract with local (regional) specialty contractors:
- Excavator
- Concrete
- Steel Erectors
- Mechanical
- Electrical
- Building Finishes
- Baker will indoctrinate subcontractors under their QL-1 program
- Through SHINE assessed QL-1 work control program, Baker initiates and controls work package development, implementation, and close-out for all QL-1 Construction activities
- Baker provides QC oversight of their subcontractors
- SHINE assesses Baker's QA/ QC program SHINE Medical Technologies I 5
Construction Planning - Construction (cont.)
- Baker responsible for implementing and managing Site Access Control program
- Baker responsible for site Material & Test Equipment (M& TE)
- Baker will contract with 3rd Party Independent Testing agency
- Soils Testing
- Concrete Testing
SHINE Medical Technologies I 6
Proprietary Information - Withheld from Public Disclosure Under 1 O CFR § 2.390(a)(4)
Construction Planning - 2019 Schedule Proprietary Information SHINE Medical Technologies I 7
ENCLOSURE 5 SHINE MEDICAL TECHNOLOGIES, INC.
MEETING SLIDES FOR THE JANUARY 29 AND 30, 2019 MEETING BETWEEN SHINE MEDICAL TECHNOLOGIES, INC. AND THE NRC SHINE IDENTIFICATION OF SAFETY-RELATED CONTROLS NON-PUBLIC VERSION Enclosures 1 and 5 contain security-related information.
Withhold from public disclosure under 10 CFR 2.390.
Upon removal of Enclosures 1, 3, and 5, this letter is uncontrolled.
11 pages follow