ENCLOSURE 4 SHINE MEDICAL TECHNOLOGIES, INC.

MEETING SLIDES FOR THE JANUARY 29 AND 30, 2019 MEETING BETWEEN SHINE MEDICAL TECHNOLOGIES, INC. AND THE NRC SHINE CONSTRUCTION PLANNING PUBLIC VERSION 7 pages follow

Construction Planning Arie Cowne, Construction Manager Health. llluminated 1

Construction Planning - Introduction 11 SHINE is responsible and will provide oversight of Construction activities

  • SHINE intends to contract with Baker Concrete Construction as the GC for the project
  • Previous experience working at Part 50 facility (V.C. Summer)
  • Previous experience working with Baker at Urenco USA (Part 70)
  • Baker assisted SHINE with preconstruction efforts (2 years) 11 Baker is on SHINE's ASL for QL-1 Procurement and Construction 11 Baker will implement their Safety Program to manage Construction work activities 11 Baker will work under SHIN E's Corrective Action Program
  • Baker planning on peak staffing of 250-300; average around 150 111 Baker construction schedule is 24 months SHINE Medical Technologies I 2

Construction Planning - Building & Infrastructure Organization Chart SHI NE CEO I

SHINE COO SHI NE VP of

~

Regulatory Affairs SHI NE Construction SHINE SHINE Document SHINE Engineering Management Configuration ----*

Control

-1 SHINE QA/ QC Management I

I I

I I

+

I I

I I

Baker Project I

I Exec.

I 1-----* Baker QA/QC I

I I

I

__ J l

I "'---------.

Baker Baker Baker Baker Baker Enginee ring Construct ion Procurement Safety Document Control Management I

I I

Baker Subcontractors I

+

SHINE Medical Technologies I 3

Construction Planning - Procurement 11 SHINE will purchase the majority of plant process equipment

  • Baker will purchase: concrete, structural steel, architectural finishes, auxiliary system components (i.e., HVAC, electrical power distribution, etc.) and related infrastructure (i.e., cable trays, pipe supports, etc.)
  • SHINE contractually flows down Design requirements to Baker 11 Baker will use SHIN E's Document Control for Design Input
  • Baker will use internal Document Control for Procurement and Construction documentation 11 Concrete and rebar will be Commercial Grade Dedicated 11 Structural steel will be purchased QL-1 11 SHINE/ AE of record review and approve Building shop drawings and submittals SHINE Medical Technologies I 4

Construction Planning - Construction

  • Baker will subcontract with local (regional) specialty contractors:
  • Excavator
  • Concrete
  • Steel Erectors
  • Mechanical
  • Electrical
  • Building Finishes
  • Baker will indoctrinate subcontractors under their QL-1 program
  • Through SHINE assessed QL-1 work control program, Baker initiates and controls work package development, implementation, and close-out for all QL-1 Construction activities
  • Baker provides QC oversight of their subcontractors
  • SHINE assesses Baker's QA/ QC program SHINE Medical Technologies I 5

Construction Planning - Construction (cont.)

  • Baker responsible for implementing and managing Site Access Control program
  • Baker responsible for site Material & Test Equipment (M& TE)
  • Baker will contract with 3rd Party Independent Testing agency
  • Soils Testing
  • Concrete Testing
  • Weld Testing Electrical Testing (UPS)

SHINE Medical Technologies I 6

Proprietary Information - Withheld from Public Disclosure Under 1 O CFR § 2.390(a)(4)

Construction Planning - 2019 Schedule Proprietary Information SHINE Medical Technologies I 7

ENCLOSURE 5 SHINE MEDICAL TECHNOLOGIES, INC.

MEETING SLIDES FOR THE JANUARY 29 AND 30, 2019 MEETING BETWEEN SHINE MEDICAL TECHNOLOGIES, INC. AND THE NRC SHINE IDENTIFICATION OF SAFETY-RELATED CONTROLS NON-PUBLIC VERSION Enclosures 1 and 5 contain security-related information.

Withhold from public disclosure under 10 CFR 2.390.

Upon removal of Enclosures 1, 3, and 5, this letter is uncontrolled.

11 pages follow