January 22, 2019 Cyrus Afshar Supervisor Regulatory Affairs NuScale Power, LLC 1100 NE Circle Blvd. Suite 200 Corvallis, OR 97330
SUBJECT:
QUALITY ASSURANCE IMPLEMENTATION INSPECTION OF NUSCALE POWER, LLC
Dear Mr. Afshar:
This letter documents the Nuclear Regulatory Commission (NRC) staffs plan to perform a Quality Assurance implementation inspection at NuScale Power, LLC (NuScale), as it pertains to design and testing activities conducted for the NuScale Design Certification Application. As discussed in a telephone call on January 9, 2019, the inspectors plan to be on site at your facility beginning Monday, February 25, 2019, and will conduct the inspection through Friday, March 1, 2019. Subsequent to the inspection, an inspection report will be issued and transmitted to you via letter. The lead inspector for this effort is Mr. Paul Prescott; you may contact him at (301) 415-3026 or via electronic mail at paul.prescott@nrc.gov.
This inspection activity has been assigned the following docket number: 05200048.
Please reference this number on any correspondence relating to this inspection activity sent to the NRC.
Sincerely, Kerri A. Kavanagh, Chief /RA/
Quality Assurance Vendor InspectionBranch-2 Division of Construction Inspection and Operational Programs Office of New Reactors Docket No.: 99902072
ML19016A474 NRO-002 OFFICE NRO/DCIP NRO/DCIP NAME PPrescott KKavanagh DATE 01/22/2019 01/22/2019