November 15, 2018 EA-18-104 Mr. Bryan C. Hanson Senior VP, Exelon Generation Company, LLC President and CNO, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
CLINTON POWER STATIONREGULATORY CONFERENCE
Dear Mr. Hanson:
This letter confirms our plans, as discussed between members of our staffs, to hold a Regulatory Conference to discuss a preliminary White finding. The details regarding the issue were conveyed to you in NRC Inspection Report 05000461/2018051 dated November 6, 2018.
The meeting will begin at 1:00 p.m. (CST) on Friday, November 30, 2018, at the U.S. Nuclear Regulatory Commission (NRC) Region III Office, 2443 Warrenville Road, Suite 210, Lisle, IL 60532-4352. This meeting will be open to the public.
The Regulatory Conference is being held to obtain information to assist the NRC in determining the safety significance of the finding and apparent violation detailed in the referenced inspection report. The conference will provide an opportunity for you to present your perspective on the facts and assumptions used by the NRC to arrive at the finding, your assessment of the significance of the finding, and any other information that you believe the NRC should take into consideration in making an enforcement decision.
The NRC would appreciate receiving any supporting documents no later than Friday, November 23, 2018, in order to make the conference more effective and efficient.
Following the conference, you will be advised by separate correspondence of the results of our deliberations on this matter.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
If you have any questions regarding this meeting, please contact me at 630-829-9628 Sincerely,
/RA Karla Stoedter Acting for/
Kenneth Riemer, Chief Branch 1 Division of Reactor Projects Docket No. 50-461 License No. NPF-62 cc: Distribution via LISTSERV
Letter to Bryan C. Hanson from Kenneth Riemer dated November 15, 2018
SUBJECT:
CLINTON POWER STATIONREGULATORY CONFERENCE DISTRIBUTION:
Christopher Cook RidsNrrDorlLpl3 RidsNrrPMClinton Resource RidsNrrDirsIrib Resource Steven West Darrell Roberts Jamnes Cameron Allan Barker DRSIII DRPIII ROPassessment.Resource@nrc.gov ADAMS Accession Number: ML18319A304 OFFICE RIII NAME KStoedter for KRiemer:bw DATE 11/15/2018 OFFICIAL RECORD COPY