Letter- Termination of Construction Authorization (CAMOX-001) for the Mixed Oxide Fuel Fabrication Facility
ML18318A135
Person / Time
Site: 07003098
Issue date: 02/08/2019
From: Andrew Pretzello
Division of Fuel Cycle Safety, Safeguards, and Environmental Review
To: Gwyn D
CB&I AREVA MOX Services
Tiktinsky D
Shared Package
ML18324A665 List:
References
Download: ML18318A135 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 8, 2019 Mr. Ben Parks, Project Engineer CB&I AREVA MOX Services P.O. Box 7097 Aiken, SC 29804-7097

SUBJECT:

TERMINATION OF CONSTRUCTION AUTHORIZATION (CAMOX-001)

FOR THE MIXED OXIDE FUEL FABRICATION FACILITY (DOCKET NUMBER: 07-3098)

Dear Mr. Parks:

By letter dated November 1, 2018 (Agencywide Documents Access and Management System

[ADAMS] Accession Number ML18305A356), you notified the U.S. Nuclear Regulatory Commission (NRC) that as of October 12, 2018 that CB&I AREVA MOX Services (MOX Services) ceased NRC regulated construction activities on the Mixed Oxide Fuel Fabrication Facility (MFFF). This followed receipt of a Notice of Termination from the U.S. Department of Energy, National Nuclear Security Administration of the contract to design, build and operate the MFFF. Due to the cessation of NRC regulated activities and the Notice of Termination, MOX Services requested the NRC to terminate the Construction Authorization (CA).

Revision 5 of the CA which terminates NRC regulated activities at the MFFF, is provided in to this letter. The NRC staff report documenting its review for this licensing action is provided in Enclosure 2 to this letter.

In accordance with title 10 of the Code of Federal Regulations Section 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publically Available Records component of the NRCs ADAMS. ADAMS is accessible from the NRC Web Site at http://www.nrc.gov/reading-rm/adams.html.

If you have any questions regarding this communication please contact Mr. David Tiktinsky, Senior Project Manager, at 301-415-8740 or via e-mail to David.Tiktinsky@nrc.gov.

Sincerely,

/RA/

Andrew J. Pretzello, Deputy Director Division of Fuel Cycle Safety, Safeguards and Environmental Review Office of Nuclear Material Safety and Safeguards Docket No. 70-3098

Enclosures:

1. Revision 5 of CAMOX-001
2. NRC Staff Evaluation cc: See next page

B. Parks 2 cc:

Mr. Scott Cannon, Federal Project Director Mr. Glenn Carroll NA-262.1 Nuclear Watch South P.O. Box A P.O. Box 8574 Aiken, SC 29802 Atlanta, GA 30306 Ms. Joyce Connery, Chairman Ms. Diane Curran Defense Nuclear Facilities Safety Board Harmon, Curran, 625 Indiana Ave., NW, Suite 700 Spielburg & Eisenberg, LLP Washington, DC 20004 1726 M St., NW, Suite 600 Washington, DC 20036 Ms. Susan Jenkins Division of Radioactive Waste Management Mr. Louis Zeller Bureau of Health and Environmental Control Blue Ridge Environmental Defense League 2600 Bull St. P.O. Box 88 Columbia, SC 29201 Glendale Springs, NC 28629 Ms. Kathryn M. Sutton Morgan, Lewis, & Bockius 1111 Penn. Ave., NW Washington, DC 20004

ML18324A665 *via email OFFICE FCSE/LOB FCSE FCSE/LOB OGC* FCSE NAME DTiktinsky *AWalker- MKotzalas LClark APretzello Smith DATE 11/20/18 11/28/18 11/2718 1/30/19 2/08/19