EPID:L-2017-LLA-0066, Package: Revision 19 of Certificate of Compliance No. 9235 for the Model No. NAC-STC Package (Approved, Closed) |
|
MONTHYEARML17353A0262017-12-0808 December 2017 NAC International, Submittal of Request to Revise the NAC-STC Certificate of Compliance No. 9235, Revision 18 to Include Adding an Optional Shield Ring on the Top Forging Project stage: Request ML18067A1332018-03-0606 March 2018 Submittal of NACs Request for a Revision to Certificate of Compliance (CoC) No. 9235 for the NAC-STC (Submittal 18A) Project stage: Request ML18145A2362018-03-31031 March 2018 NAC-STC Safety Analysis Report, Partial RAI Responses, Revision 18A Project stage: Request ML18152A6812018-05-31031 May 2018 Letter to W. Fowler Application for the Model No. NAC-STC - Request for Additional Information (W/Enclosure) Project stage: RAI ML18158A1922018-06-0505 June 2018 NACs Responses to NRCs Request for Additional Information (NAC-STC Submittal 17D) Project stage: Request ML18176A0992018-06-21021 June 2018 NACs Responses to NRCs Request for Additional Information (NAC-STC Submittal 18D) Project stage: Request ML18289A3892018-06-30030 June 2018 Safety Analysis Report: Non-Proprietary Version of NAC-STC NAC Storage Transport Cask, Safety Analysis Report, Partial RAI Responses, Revision 18B - Redacted Project stage: Request ML18201A2042018-07-18018 July 2018 Transmittal of Responses to NRC Request for Additional Information for NACs Request for a Revision to Certificate of Compliance No. 9235 for the NAC-STC Project stage: Response to RAI ML18235A5032018-08-21021 August 2018 Supplement to NACs Responses to NRCs Request for Additional Information (NAC-STC Submittal 18D) Project stage: Supplement ML18264A2312018-09-19019 September 2018 Submission of Replacement Pages for NAC-STC Submittal 18B, Responses to the NRC Request for Additional Information for NACs Request for a Revision to Certificate of Compliance (CoC) No. 9235 Project stage: Request ML18289A3982018-10-12012 October 2018 NAC International, Inc., Submittal of Replacement Pages for NAC-STC Submittal 18B, Responses to the NRC Request for Additional Information for NACs Request for a Revision Project stage: Request ML18299A0962018-10-26026 October 2018 E-Mail from W. Fowler STC Shielding Ring Project stage: Request ML18311A0202018-11-0707 November 2018 Enclosure 2: Safety Evaluation Report (Letter to W. Fowler Revision 19 of Certificate of Compliance No. 9235 for the Model No. NAC-STC Package) Project stage: Approval ML18311A0162018-11-0707 November 2018 Package: Revision 19 of Certificate of Compliance No. 9235 for the Model No. NAC-STC Package Project stage: Request ML18311A0182018-11-0707 November 2018 Letter to W. Fowler Revision 19 of Certificate of Compliance No. 9235 for the Model No. NAC-STC Package Project stage: Other ML18311A0172018-11-0707 November 2018 Enclosure 1: Certificate of Compliance No. 9235, Revision No. 19 (Letter to W. Fowler Revision 19 of Certificate of Compliance No. 9235 for the Model No. NAC-STC Package) Project stage: Other 2018-05-31
[Table View] |
Text
From:
Fowler, Samuel To:
White, Bernard Cc:
Chapman, Deborah; Baldner, Heath; Carver, George; Pfeifer, Holger; Archibald, Ryan
Subject:
[External_Sender] STC Shield Ring Date:
Friday, October 26, 2018 10:00:18 AM
- Bernie,
For all accident conditions, the dose rate evaluations were performed without the shield ring present and this is reflected in the shielding models we submitted. We will make an editorial change to SAR as part of the consolidation making this statement so it is clear to anyone in the future who reads those SAR sections.
Wren Fowler Director, Licensing NAC International Inc.