NRR RIDM Action Plan September 14, 2018
RIDM Action Plan - Background Commission direction
- SRM-M170511, June 2017; ML17177A397
- SECY-17-0112, November 2017; ML17270A192 NRR Office Director Memorandum
- Tasking to Continue the Development and Inclusion of Risk Considerations in Licensing Reviews,June 29, 2017; ML17180A061 2
Mission Statement Enhance the integration of risk information into the organizations decision-making practices and processes to improve the technical basis for regulatory activities, increase efficiency, and improve effectiveness.
NRR RIDM Project - Overview The NRR RIDM project uses a systematic phased approach to complete the tasks
- Phase 1: evaluation and analysis of the tasks to generate a findings and recommendations report
- Phase 2: implementation of the recommendations, including a trial program of the proposed changes to guidance documents
5 strategies I.
Evaluate and Update Guidance II. Develop a Graded Approach for Using Risk Information in Licensing Reviews III. Enhance Mandatory Training Requirements Related to RIDM for Managers and Staff IV. Advance Risk-Informed Initiatives V. Enhance Communication on Risk-Informed Activities
Enhance the integration of risk information into the organizations decision making practices and processes to improve the technical basis for regulatory activities, increase efficiency, and improve effectiveness NRR RIDM Mission SECY Paper Strategies Strategy IV Advance Risk-Informed Initiatives Strategy III Enhance Mandatory Training Tasks PHASE 1 Evaluate tasks to generate findings and recommendations PHASE 2 Implement recommendations Strategy I Evaluate/Update Guidance Strategy II Develop Graded Approach Cross-Cutting Communication Strategy V Enhance Communication NRR RIDM Action Plan Framework
PHASE 1 Completed in June 2018 with publication of Findings and Recommendations Report ML18169A205
NRR RIDM Tasks 1 and 3 Integrated Review Team (IRT) Process
- Expand use of license review teams that would team up risk analysts with technical staff vice relying on sequential or independent reviews. In addition, evaluate the roles/responsibilities for the technical reviewer, risk analyst, and project manager.
Develop a graded approach for using risk information more broadly in licensing reviews.
- Guidelines for considering risk information when reviewing applications that are not submitted per RG 1.174.
NRR RIDM Task 2 Identified how the concepts of risk and risk insights are currently understood and used in NRR
- Cafés with staff and managers
- Focused interviews
- Online questionnaires
NRR RIDM Task 4 Review of Branch Technical Position (BTP) 8-8, Onsite (Emergency Diesel Generators) and Offsite Power Sources Allowed Outage Time [AOT] Extensions Developed an interim expectation memorandum on using BTP 8-8 for AOT extension requests Recommended changes to BTP 8-8 that will eventually be incorporated into the guidance document.
NRR RIDM Tasks 5, 6, 7, 8 (complete)
NRR RIDM Task 5 Evaluate DPO Recommendations 5 (use insights from independent risk tools; e.g., SPAR models) and 6 (lessons-learned review after first-of-a-kind licensing actions)
NRR RIDM Task 6 Evaluate the guidance in four documents (RG 1.174, RG 1.177, RG 1.200, and NUREG-1855) to determine if better harmonization is appropriate.
NRR RIDM Task 7 With the impending revision to RG 1.174, determine if any other documents/procedures should be updated NRR RIDM Task 8 Evaluate the use of Large Early Release Frequency (LERF) in various regulatory applications and determine if different approaches are supported.
PHASE 2 July 2018 - December 2018 RIDM Action Plan, August Revision ML18211A439
NRR RIDM Team A Integrated Review Team Process
Principles of Risk-Informed Decision-making 15
Traditional Design Basis vs. Risk-Informed Reviews 16
Recent Licensing Experience Non-RG 1.174 licensing actions:
- Use of risk insights
- communicate the safety context of proposed changes
- increase staffs confidence in its decisions
- increase staffs understanding of system and component importance and interactions
- How to integrate risk insights into engineering judgement
- How to document use of risk insights in safety evaluations RG 1.174 licensing actions
- Scope of technical staff reviews
- Integrating engineering and risk reviews 17
RIDM Action Plan Phase 1 Tasks 1 & 3 Task 1
- Expand use of license review teams that would team up risk analysts with technical staff vice relying on sequential or independent reviews. In addition, evaluate the roles/responsibilities for the technical reviewer, risk analyst, and project manager.
- Task 3
- Develop a graded approach for using risk information more broadly in licensing reviews.
18
Task 1 Develop a review team framework that provides for:
- Integrating risk and traditional engineering insights
- Teaming risk analysts with technical staff instead of relying on sequential or independent reviews
- Enabling decisions about the use of risk insights early in the review process
- Developing joint conclusions and a consolidated safety evaluation (SE) developed by the team 19
Task 3 Establish a repeatable framework for integrating technical and risk analyst licensing reviews Develop tools for reviewers
- Deciding whether to use risk insights
- Describing risk insights that may be considered
- Documenting the staffs consideration of risk insights in safety evaluations 20
Tasks 1 & 3 Recommendations Report-Phase 1 Focuses on a subset of amendments, relief requests, and exemptions Routine, emergency/exigent, multiple risk-informed licensing actions Contains six recommendations Define application type based on level of PRA information Define roles and responsibilities Implement draft IRT process for a trial period Update guidance and training after a trial period Update project management software after a trial period Evaluate applicability to other NRR processes Describes process for forming IRTs and consolidated RAIs/SEs Contains review tools (checklists and SE language guidance) for using risk insights (i.e., graded approach) 21
IRT Decision for Routine Actions 22
IRT Decision - Non-RG 1.174
Risk-Informed Decision Making in Licensing Actions 25 Traditional Analysis Traditional Analysis with Risk Insights Risk-Informed (RG 1.174)
Block 5 Block 6 & 7 Block 8 Integrated Review: Principles of Risk-Informed Decision Making
Phase 2 - Trial Period
- July - October 2018
- Obtaining staff feedback on IRT decision process, use and documentation of risk insights, and use of consolidated approach
- For Type 1 or 2 applications, risk analyst effort expected to be minimal compared to RG 1.174 application reviews
- Develop plan to create formal guidance and provide training in 2019
- Continual learning and process improvements will occur after initial implementation 26
NRR RIDM Team B Recommending changes to position descriptions and updates to performance appraisal elements to encourage use of risk information and risk insights.
Supporting the regional offices in their development and running of regional Risk Cafés, and assessing the impact of their results on the guidance and training updates coming out of the NRR RIDM project.
NRR RIDM Team C Producing a RIDM Roadmap that contains guidance for the use of risk principles in licensing reviews, and establishes the hierarchy of RIDM documents.
Producing a Desktop Guide that contains a glossary of risk-related terms and an overview of the Integrated Review Team process.
Assessing draft updates to existing guidance to facilitate the broadening of the use of risk in licensing reviews.
This flowchart shows the decision route for four types of regulatory decisions.
30
No final decisions have been made regarding training.
31
Training would likely include an overview for all staff 32
Training will be developed for PMs to support the Block 2 decision.
33
Integrated review team training for PMs, Tech Reviewers, Risk Analysts for Block 3.
34
Block 3 is expected to get most of the attention.
35
Block 4 represents RG 1.174 reviews, and supporting training is expected to be developed.
36
There are two audiences for two contexts of training.
37 IRT Non-1.174 TR RA 1.174 TR RA IRT - Integrate Review Team 1.174 - Reviews IAW RG 1.174 TR - Technical Reviewer RA - Risk Analyst
The current trial period of the IRT will inform training needs.
38
NRR RIDM Team E - Additional Processes In Phase I of the project, the NRR RIDM Task 1 working group focused on a subset (in bold text) of licensing activities requiring SEs that could involve consideration of risk:
License amendments
- Emergency/exigent
- Routine
- Improved Standard Technical Specifications conversions
- Security, emergency preparedness (EP), quality assurance (QA) plans Relief requests and proposed alternatives License exemptions Environmental reviews (environmental assessments and impact statements)
License renewals and associated commitment reviews Orders/backfits Technical Specification Task Force (TSTF) Travelers Topical reports
NRR RIDM Team E - Additional Processes Team E will support NRR divisions in determining whether their processes that were not covered within the IRT trial basis could be enhanced using the IRT approach or a similar process.
NRR divisions will develop separate plans for updating those processes, if applicable and allowed by their regulatory structures, consistent with the Commissions policy.
NRR RIDM Team F Revising Branch Technical Position 8-8 to determine if clarification is needed regarding acceptability of long duration Completion Times (CT) for one-time extensions and maximum Allowed Outage Times (AOT), even when supported with risk information.
Revising Standard Review Plan Section 16.1, Risk-Informed Decision-making: Technical Specification to include key points of the expectation memorandum, and to reference the current version of Regulatory Guide (RG) 1.177.
Revising RG 1.177, An Approach for Plant-Specific, Risk-Informed Decision-making: Technical Specification to address long duration CT for one-time extensions and backstop CT.
NRR RIDM Team G - Metrics How do you know if you are making progress if you dont measure it?
Team G is developing metrics for measuring the implementation of the Phase 1 recommendations.
Metrics will facilitate identifying trends and areas for improvement.