ML18270A362
ML18270A362 | |
Person / Time | |
---|---|
Issue date: | 10/10/2018 |
From: | James Drake NRC/NRR/DLP/PLPB |
To: | |
Drake J, NRR/DLP, 415-8378 | |
References | |
Download: ML18270A362 (12) | |
Text
Industry Response to Flowserve Part 21 on Anchor Darling Double Disk Gate Valves and NRC Staff Next Steps Public Meeting 10/10/2018 1
Overview
- Operating Experience has identified failures of Anchor/Darling (A/D) Double Disk Gate Valves (DDGVs)
- Significant progress has been made
- Industry has developed guidance
- All licensees have submitted information on the affected valves, including commitments for valve repairs
- Industry provided information on valves repaired through end of spring 2018 refueling outages
- The NRC staff has drafted an inspection procedure
- The NRC staff continues to assess the need for a Generic Communication, but does not plan one at this time 2
Background
- Failure of A/D DDGV at Browns Ferry in 2013 revealed that threaded stem-to-wedge connection had not been properly torqued
- Flowserve Part 21 notification February 25, 2013
- Recommended assessing wedge pin susceptibility to shear and rework the valve if needed
- BWROG developed guidance to address Part 21 to include:
- Prioritization and Screening Criteria
- Evaluation Methods
- Inspection and Diagnostics
- Repair Methods 3
Background (cont.)
- NRC staff evaluated 2013 Part 21 and determined the issue would be monitored with no generic communication
- Additional failures occurred at LaSalle Unit 2 and Columbia
- LaSalle event elevated to NRC special inspection
- Information Notice (June 2017)
- Flowserve updated Part 21 (July 2017)
- BWROG updated guidance to Rev. 4 (August 2017)
- NRC staff considered need for generic communication due to larger population of failures and limited information readily available to the staff 4
Progress to Date
- NRC staff held public meetings on guidance and licensee corrective actions
- Staff requested clarification of guidance (October 2017)
- NEI provided clarification (November 2017)
- All licensees submitted information (December 2017)
- Valve population
- Valve characteristics (susceptible, non susceptible, risk category)
- Rework status and commitments for future repairs
- Public Data Compilations are in ML18053A023 and ML18053A904
- NRC staff held public meeting February 15, 2018
- Staff discussed guidance document, licensee corrective actions, and future plant inspections. Staff has concerns on credit for thread friction and limited effectiveness of diagnostic testing 5
Progress to Date (cont.)
- NRC staff held public meeting May 16, 2018
- Staff discussed draft Temporary Instruction (TI)
- Industry representatives expressed concerns that the draft TI goes above and beyond the regulatory requirements
- NRC staff explained the TI serves two purposes:
- Evaluate industry progress on addressing Part 21 issue
- Allow NRC staff to assess the need for further regulatory action
- Industry representative agreed to send NRC staff data from the repairs made to date. Data was received July 13, 2018 6
Staff Assessment of Data
- NRC staff has reviewed the submitted industry data and observed the following:
- 78 valves reported reworked with 2 valves having sheared pins and 1 valve with pin degraded. Remainder reported no pin damage
- 22 valves reported stem/wedge joint was found tight and 56 valves reported stem/wedge joint was found loose
- Collar reported damaged in 5 valves with 2 of 5 having pin sheared
- 47 valves reworked were size 3 inch (5 total) and 4 inch (42 total).
Almost all of the 47 valves had pin margins less than -100%. All 47 valves were found with no pin damage.
- Valves 6 inch and larger with a valve class greater than 150 tend to have much larger negative pin margins (-300% and greater)
- 3 valves reported as found diagnostic test anomalies. 1 had a sheared pin while the other 2 valves had loose stem/wedge joint 7
Staff Assessment of Data (cont.)
- NRC staff assessment of the industry repair and test data:
- Appears that valves 4 inch and smaller make up the majority of the valve population and do not present a problem. Additional data is needed to complete the assessment
- Appears that stem/wedge thread friction does play a part in assisting the pin with resisting the force being applied. Additional data is needed to support developing acceptance criteria for crediting stem/wedge thread friction.
- Data needed to support - actuator capability (motor size, motor curve stall value, overall actuator ratio, motor speed), stem diameter, stem thread diameter, stem thread half angle, stem/wedge material, stem/wedge pitch and lead, wedge pin size, wedge pin material, stem/wedge/wedge pin yield & ultimate stress values, stem/stemnut coefficient of friction, stem/wedge coefficient of friction, shear factor applied, and tested torque & or thrust values 8
Next Steps
- Discuss the feasibility of forming a working group consisting of NRC staff and industry MOV experts to evaluate the data and establish acceptance criteria for crediting stem/wedge thread friction, material margins based on component attributes (size, service, material strength, etc.)
- Criteria could be used for addressing the remainder of the valve population. (e.g., rework/repair, monitor, no rework needed)
- Discuss path forward
- NRC staff concur on final acceptance criteria and updated industry guidance document?
- NRC update temporary instruction and conduct inspection?
9
Milestones
- Working group formed - Fall 2018
- Plant participation identified - Fall 2018
- Working group kickoff meeting to discuss necessary data and objectives - Fall 2018
- Data collection - Fall 2018?
- Review data and develop criteria - Fall 2018?
- Next steps 10
Assumptions
- Actuator capability based on industry standard equations
- Stem/wedge thread shear capability based on ASME B1.1 Unified Inch Screw Threads (Class 2 unless other specified)
- Wedge pin shear capability based on basic equation for pin shear torque (as detailed in BWROG revision 4 guidance document)
- Assume 0.08 stem to stem nut coefficient of friction if data does not exist 11
Discussion Future Questions Stewart.Bailey@nrc.gov 301-415-1321 Michael.Farnan@nrc.gov 301-415-1486 12