ML18270A362

From kanterella
Jump to navigation Jump to search
Public Meeting Slide Regarding Industry Reponses to Flowserve Part 21 on Anchor Darling Double Disk Gate Valves and NRC Staff Next Steps
ML18270A362
Person / Time
Issue date: 10/10/2018
From: James Drake
NRC/NRR/DLP/PLPB
To:
Drake J, NRR/DLP, 415-8378
References
Download: ML18270A362 (12)


Text

Industry Response to Flowserve Part 21 on Anchor Darling Double Disk Gate Valves and NRC Staff Next Steps Public Meeting 10/10/2018 1

Overview

  • Operating Experience has identified failures of Anchor/Darling (A/D) Double Disk Gate Valves (DDGVs)
  • Significant progress has been made

- Industry has developed guidance

- All licensees have submitted information on the affected valves, including commitments for valve repairs

- Industry provided information on valves repaired through end of spring 2018 refueling outages

  • The NRC staff has drafted an inspection procedure
  • The NRC staff continues to assess the need for a Generic Communication, but does not plan one at this time 2

Background

  • Failure of A/D DDGV at Browns Ferry in 2013 revealed that threaded stem-to-wedge connection had not been properly torqued
  • Flowserve Part 21 notification February 25, 2013

- Recommended assessing wedge pin susceptibility to shear and rework the valve if needed

  • BWROG developed guidance to address Part 21 to include:

- Prioritization and Screening Criteria

- Evaluation Methods

- Inspection and Diagnostics

- Repair Methods 3

Background (cont.)

  • NRC staff evaluated 2013 Part 21 and determined the issue would be monitored with no generic communication
  • Additional failures occurred at LaSalle Unit 2 and Columbia
  • LaSalle event elevated to NRC special inspection
  • Information Notice (June 2017)
  • BWROG updated guidance to Rev. 4 (August 2017)
  • NRC staff considered need for generic communication due to larger population of failures and limited information readily available to the staff 4

Progress to Date

  • NRC staff held public meetings on guidance and licensee corrective actions

- Staff requested clarification of guidance (October 2017)

- NEI provided clarification (November 2017)

  • All licensees submitted information (December 2017)

- Valve population

- Valve characteristics (susceptible, non susceptible, risk category)

- Rework status and commitments for future repairs

- Public Data Compilations are in ML18053A023 and ML18053A904

  • NRC staff held public meeting February 15, 2018

- Staff discussed guidance document, licensee corrective actions, and future plant inspections. Staff has concerns on credit for thread friction and limited effectiveness of diagnostic testing 5

Progress to Date (cont.)

  • NRC staff held public meeting May 16, 2018

- Staff discussed draft Temporary Instruction (TI)

- Industry representatives expressed concerns that the draft TI goes above and beyond the regulatory requirements

  • NRC staff explained the TI serves two purposes:

- Evaluate industry progress on addressing Part 21 issue

- Allow NRC staff to assess the need for further regulatory action

  • Industry representative agreed to send NRC staff data from the repairs made to date. Data was received July 13, 2018 6

Staff Assessment of Data

  • NRC staff has reviewed the submitted industry data and observed the following:

- 78 valves reported reworked with 2 valves having sheared pins and 1 valve with pin degraded. Remainder reported no pin damage

- 22 valves reported stem/wedge joint was found tight and 56 valves reported stem/wedge joint was found loose

- Collar reported damaged in 5 valves with 2 of 5 having pin sheared

- 47 valves reworked were size 3 inch (5 total) and 4 inch (42 total).

Almost all of the 47 valves had pin margins less than -100%. All 47 valves were found with no pin damage.

- Valves 6 inch and larger with a valve class greater than 150 tend to have much larger negative pin margins (-300% and greater)

- 3 valves reported as found diagnostic test anomalies. 1 had a sheared pin while the other 2 valves had loose stem/wedge joint 7

Staff Assessment of Data (cont.)

  • NRC staff assessment of the industry repair and test data:

- Appears that valves 4 inch and smaller make up the majority of the valve population and do not present a problem. Additional data is needed to complete the assessment

- Appears that stem/wedge thread friction does play a part in assisting the pin with resisting the force being applied. Additional data is needed to support developing acceptance criteria for crediting stem/wedge thread friction.

- Data needed to support - actuator capability (motor size, motor curve stall value, overall actuator ratio, motor speed), stem diameter, stem thread diameter, stem thread half angle, stem/wedge material, stem/wedge pitch and lead, wedge pin size, wedge pin material, stem/wedge/wedge pin yield & ultimate stress values, stem/stemnut coefficient of friction, stem/wedge coefficient of friction, shear factor applied, and tested torque & or thrust values 8

Next Steps

  • Discuss the feasibility of forming a working group consisting of NRC staff and industry MOV experts to evaluate the data and establish acceptance criteria for crediting stem/wedge thread friction, material margins based on component attributes (size, service, material strength, etc.)

- Criteria could be used for addressing the remainder of the valve population. (e.g., rework/repair, monitor, no rework needed)

  • Discuss path forward

- NRC staff concur on final acceptance criteria and updated industry guidance document?

- NRC update temporary instruction and conduct inspection?

9

Milestones

  • Working group formed - Fall 2018
  • Plant participation identified - Fall 2018
  • Working group kickoff meeting to discuss necessary data and objectives - Fall 2018
  • Data collection - Fall 2018?
  • Review data and develop criteria - Fall 2018?
  • Next steps 10

Assumptions

  • Actuator capability based on industry standard equations
  • Stem/wedge thread shear capability based on ASME B1.1 Unified Inch Screw Threads (Class 2 unless other specified)
  • Wedge pin shear capability based on basic equation for pin shear torque (as detailed in BWROG revision 4 guidance document)
  • Assume 0.08 stem to stem nut coefficient of friction if data does not exist 11

Discussion Future Questions Stewart.Bailey@nrc.gov 301-415-1321 Michael.Farnan@nrc.gov 301-415-1486 12