Vogtle Construction Update CIP Task Force Thomas Petrak Southern Nuclear Operating Company October 1, 2018

July 2017 June 2018 Unit 3 CA55 - April 2018 Unit 4 Main Transformer - May 2018 Unit 4 Q233 - May 2018 Unit 4 CA32 -June 2018 First Structural Steel Floor Module

Unit 3 Final EPA Installed - July 2018 Cooling Water System Pumps - August 2018 EDS-1 Testing - August 2018 Unit 4 Steam Generator - August 2018 Unit 4 Accumulator - September 2018 QUESTIONS