September 14, 2018 MEMORANDUM TO:
Jennifer Dixon-Herrity, Chief Licensing Branch 4 Division of Licensing, Siting, and Environmental Analysis Office of New Reactors FROM:
Paul Kallan, Senior Project Manager
/RA/
Licensing Branch 4 Division of Licensing, Siting, and Environmental Analysis Office of New Reactors
SUBJECT:
AUDIT PLAN FOR VOGTLE ELECTRIC GENERATING PLANT UNITS 3 AND 4, REQUEST FOR LICENSE AMENDMENT:
CREDITING PREVIOUSLY COMPLETED FIRST PLANT AND FIRST THREE PLANT TESTS (LAR 18-019)
By letter dated August 3, 2018 (Agencywide Documents Access and Management System (ADAMS) Accession Number ML18215A382), Southern Nuclear Operating Company (the licensee) requested an amendment to Combined License Numbers NPF-91 and NPF-92, for Vogtle Electric Generating Plant (VEGP) Units 3 and 4.
The requested amendment requires changes to the Updated Final Safety Analysis Report (UFSAR) in the form of departures from the incorporated plant-specific Design Control Document (DCD) Tier 2* and Tier 2 information and related changes to the VEGP Units 3 and 4 Combined License (COL) and COL Appendix C (and corresponding plant-specific DCD Tier 1) information.
The requested amendment includes changes to credit previously completed first plant only and first three plant only testing as described in the licensing basis documents, including COL Condition 2.D.(2)(a) and plant-specific Tier 1 Section 2.1.3. Specifically, the proposed changes would revise the COL to delete conditions requiring the following tests: In-Containment Refueling Water Storage Tank (IRWST) Heatup Test, Reactor Vessel Internals Vibration Testing and Core Makeup Tank Heated Recirculation Tests. The documentation to establish a valid prototype reactor internals in accordance with Regulatory Guide 1.20, Comprehensive Vibration Assessment Program for Reactor Internals During Preoperational and Startup Testing is also included.
CONTACT:
Paul Kallan, NRO/DLSE/LB4 301-415-2809
J. Dixon-Herrity The Reactor Systems, Nuclear Performance & Code Review Branch (NRO/SRSB), the Containment and Ventilation Branch (NRO/SCVB), the Mechanical Engineering Branch (NRO/MEB), and the Quality Assurance Vendor Inspection Branch (NRO/QVIB) staff plan to conduct an audit to gain a better understanding of the proposed changes and to review related documentation and non-docketed information in order to evaluate conformance with the Standard Review Plan or technical guidance.
Docket Nos.: 52-025 and 52-026
Enclosure:
Regulatory Audit Plan cc: See next page
ML18256A323 NRO-008 OFFICE DLSE/LB4/PM DLSE/LB4/LA DLSE/LB4/BC NAME PKallan RButler JDixon-Herrity DATE 9/14/18 9/14/18 9/14/18
Vogtle Units 3 & 4 Mailing List (Revised 01/09/2018) cc:
Southern Nuclear Operating Company Mr. Barty Simonton Document Control Coordinator Team Leader 42 Inverness Center Parkway, Bin 237 Environmental Radiation Program Birmingham, AL 35242 Air Protection Branch Environmental Protection Division Office of the Attorney General 4244 International Parkway, Suite 120 40 Capitol Square, SW Atlanta, GA 30354-3906 Atlanta, GA 30334 George B. Taylor, Jr.
Resident Manager 2100 East Exchange Pl Oglethorpe Power Corporation Atlanta, GA 30084-5336 Alvin W. Vogtle Nuclear Plant 7821 River Road Brian H. Whitley Waynesboro, GA 30830 Regulatory Affairs Director Southern Nuclear Operating Company Anne F. Appleby 42 Inverness Center Parkway, BIN B237 Olgethorpe Power Corporation Birmingham, AL 35242 2100 East Exchange Place Tucker, GA 30084 Mr. Michael Yox Site Regulatory Affairs Director County Commissioner Vogtle Units 3 & 4 Office of the County Commissioner 7825 River Road, Bin 63031 Burke County Commission Waynesboro, GA 30830 Waynesboro, GA 30830 Mr. Wayne Guilfoyle Commissioner District 8 Augusta-Richmond County Commission 4940 Windsor Spring Rd Hephzibah, GA 30815 Gwendolyn Jackson Burke County Library 130 Highway 24 South Waynesboro, GA 30830 Mr. Reece McAlister Executive Secretary Georgia Public Service Commission Atlanta, GA 30334 Resident Inspector Vogtle Plant Units 3 & 4 8805 River Road Waynesboro, GA 30830 Page 1 of 3
Vogtle Units 3 & 4 Mailing List Email acchambe@southernco.com (Amy Chamberlian) agaughtm@southernco.com (Amy Aughtman)
ALPUGH@southernco.com (Amanda Pugh) annacom@westinghouse.com (Michael J. Annacone) awc@nei.org (Anne W. Cottingham) becky@georgiawand.org (Becky Rafter) bhwhitley@southernco.com (Brian Whitley)
Bill.Jacobs@gdsassociates.com (Bill Jacobs) bjadams@southernco.com (Brad Adams) bwwaites@southernco.com (Brandon Waites) castelca@westinghouse.com (Curtis Castell) comerj@westinghouse.com (James Comer) crenshjw@westinghouse.com (John Crenshaw) crpierce@southernco.com (C.R. Pierce) dahjones@southernco.com (David Jones) david.hinds@ge.com (David Hinds) david.lewis@pillsburylaw.com (David Lewis) dgbost@southernco.com (Danny Bost) dlfulton@southernco.com (Dale Fulton) drculver@southernco.com (Randy Culver) durhamdc@westinghouse.com (David Durham) ed.burns@earthlink.net (Ed Burns) edavis@pegasusgroup.us (Ed David) erg-xl@cox.net (Eddie R. Grant) fdhundle@southernco.com (Forrest Hundley) fhwillis@southernco.com (Fred Willis)
G2NDRMDC@southernco.com (SNC Document Control) graysw@westinghouse.com (Scott W. Gray) jadwilli@southernco.com (J.D. Williams) james1.beard@ge.com (James Beard) jannina.blanco@pillsburylaw.com (Jannina Blanco) jantol1dj@westinghouse.com (David Jantosik) jenmorri@southernco.com (Jennifer Buettner)
JHaswell@southernco.com (Jeremiah Haswell) jim@ncwarn.org (Jim Warren)
John.Bozga@nrc.gov (John Bozga)
Joseph_Hegner@dom.com (Joseph Hegner) jpredd@southernco.com (Jason R. Redd) jranalli@meagpower.org (Jerry Ranalli) jtgasser@southernco.com (Jeff Gasser) karen.patterson@ttnus.com (Karen Patterson) karlg@att.net (Karl Gross) kdfili@southernco.com (Karen Fili)
Page 2 of 3
Vogtle Units 3 & 4 Mailing List kmstacy@southernco.com (Kara Stacy)
KSutton@morganlewis.com (Kathryn M. Sutton) kwaugh@impact-net.org (Kenneth O. Waugh) lchandler@morganlewis.com (Lawrence J. Chandler) markus.popa@hq.doe.gov (Markus Popa) mdmeier@southernco.com (Mike Meier) mdrauckh@southernco.com (Mark Rauckhorst) media@nei.org (Scott Peterson)
Melissa.Smith@Hq.Doe.Gov (Melissa Smith)
Michael.Kuca@hq.doe.gov (Michael Kuca) mike.price@opc.com (M.W. Price) mlgraves@southernco.com (Michelle Graves)
MSF@nei.org (Marvin Fertel) myox@southernco.com (Mike Yox) nirsnet@nirs.org (Michael Mariotte)
Nuclaw@mindspring.com (Robert Temple) patriciaL.campbell@ge.com (Patricia L. Campbell)
Paul@beyondnuclear.org (Paul Gunter) pbessette@morganlewis.com (Paul Bessette) r.joshi15@comcast.net (Ravi Joshi) rjarrett@southernco.com (Robyn Jarrett)
RJB@NEI.org (Russell Bell)
Ronald.Jones@scana.com (Ronald Jones) rwink@ameren.com (Roger Wink) sabinski@suddenlink.net (Steve A. Bennett) sara@cleanenergy.org (Sara Barczak) sblanton@balch.com (Stanford Blanton)
Shiva.Granmayeh@hq.doe.gov (Shiva Granmayeh) sjackson@meagpower.org (Steven Jackson) skauffman@mpr.com (Storm Kauffman) sroetger@psc.state.ga.us (Steve Roetger) stephan.moen@ge.com (Stephan Moen) stephen.burdick@morganlewis.com (Stephen Burdick) tom.miller@hq.doe.gov (Tom Miller)
TomClements329@cs.com (Tom Clements)
Vanessa.quinn@dhs.gov (Vanessa Quinn) vcsummer2n3@gmail.com (Brian McIntyre) wasparkm@southernco.com (Wesley A. Sparkman) wayne.marquino@gmail.com (Wayne Marquino) weave1dw@westinghouse.com (Doug Weaver) x2gabeck@southernco.com (Gary Becker) x2kmseib@southernco.com (Kristin Seibert)
Page 3 of 3
Enclosure AUDIT OF REPORTS AND CALCULATIONS IN SUPPORT OF A REQUEST FOR A LICENSE AMENDMENT RELATED TO CREDITING PREVIOUSLY COMPLETED FIRST PLANT AND FIRST THREE PLANT TESTS SOUTHERN NUCLEAR OPERATING COMPANY VOGTLE ELECTRIC GENERATING PLANT, UNITS 3 AND 4 Docket Nos.52-025 and 52-026 The purpose of the audit is to review the reports and calculations needed by staff to verify the information and conclusions in the Request for License Amendment: Crediting Previously Completed First Plant and First Three Plant Tests (LAR 18-019) submitted by Southern Nuclear Operating Company (SNC) for the Vogtle Electric Generating Plant (VEGP), Units 3 and 4 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML18215A382).
A.
Background:
In License Amendment Request (LAR)18-019, SNC requires changes to the Updated Final Safety Analysis Report (UFSAR) in the form of departures from the incorporated plant-specific Design Control Document (DCD) Tier 2* and Tier 2 information and related changes to the VEGP Units 3 and 4 Combined License (COL) and COL Appendix C (and corresponding plant-specific DCD Tier
- 1) information.
The LAR includes changes to credit previously completed first plant only and first three plant only testing as described in the licensing basis documents, including COL Condition 2.D.(2)(a) and plant-specific Tier 1 Section 2.1.3. Specifically, the proposed changes would revise the COL to delete conditions requiring the following tests: In-Containment Refueling Water Storage Tank (IRWST) Heatup Test, Reactor Vessel Internals Vibration Testing, and Core Makeup Tank Heated Recirculation Test. The documentation to establish a valid prototype reactor internals in accordance with Regulatory Guide 1.20, Comprehensive Vibration Assessment Program for Reactor Internals During Preoperational and Startup Testing is also included.
B.
Regulatory Audit Basis This regulatory audit is based on the following:
VEGP Unit 3, Current Facility Combined License NPF-91, Revised 09/11/2018, License Condition 2.D.(2)(a) (ADAMS Accession No. ML14100A106).
VEGP Unit 4, Current Facility Combined License NPF-92, Revised 09/11/2018, License Condition 2.D.(2)(a) (ADAMS Accession No. ML14100A135).
VEGP Units 3 and 4 Updated Final Safety Analysis Report, Revision 6 and Tier 1, Revision 5, August 11, 2017, Section 14.2.9.1.3 (ADAMS Accession No. ML17172A218).
C.
Regulatory Audit Scope and Methodology The audit team will view the calculations that provide the technical support for LAR-18-019. In addition, the audit team may potentially request to meet with subject matter expert(s) to discuss (1) potential differences between VEGP Units 3 and 4, and the plants for which testing has been
2 conducted, (2) quality assurance of the test data, and (3) physical phenomena observed in the test data.
D.
Information and Other Material Necessary for the Regulatory Audit The staff requests that the following documents, organized by review area, be made available to the staff either at a local office or in the electronic reading room:
General ND-EN-006-F01, Sanmen 1&2 and Haiyang 1 First Plant Only and First 3 Plant Only Passive Core Cooling and Reactor System Tests ND-EN-006-F01, NRC IP 70367 Comparison to Sanmen and Haiyang Admin Procedures HY1-PXS-T2R-504, Partial Pre-Op Test Report for HY1-PXS-T1P-504 HY1-PXS-T2R-504S01, Partial Pre-Op Test Report for HY1-PXS-T1P-504 SM1-PXS-T2R-504, SM1-PXS-T1P-504 PXS HFT Report IRWST Heatup Test HY1-PXS-T2C-012, HY1-PXS-T1P-504 Section 7.2 PRHR HX Heat Transfer Capability of IST Test Heat Transfer and Flow Calculation HY1-PXS-T2C-013, HY1-PXS-T1P-504 Section 7.4 PRHR HX Heat Removal Performance Test Heat Transfer and Flow Calculation HY1-PXS-T2P-001, Haiyang Unit 1 PXS HFT Results Validation for PRHR Performance SM1-PXS-T2C-010, SM1-PXS-T1P-504 Section 7.2 PRHR HX Force Flow Heat Transfer Capability Test SM1-PXS-T2C-011, SM1-PXS-T1P-504 Section 7.4 PRHR HX Natural Circulation Test SM1-PXS-T2P-001, Sanmen Unit 1 HFT Results Validation for PRHR Performance Reactor Vessel Internals Vibration Testing APP-CVAP-GER-003 (WCAP-17984), CVAP Vibration Analysis Program for the AP1000 Plant APP-CVAP-GER-004 (WCAP-17983), CVAP Measurement and Inspection Programs for the AP1000 Plant SM1-CVAP-T2R-100, Sanmen 1 Pre-FT Visual Inspection Report of the AP1000 of AP1000 RVI APP-GW-GLR-179, CVAP Preliminary Report for the Sanmen 1 AP1000 Plant
3 APP-GW-GLR-181, CVAP Final Report for the Sanmen 1 AP1000 Plant SM1-CVAP-T2R-400, Sanmen Unit 1 Post HFT Visual Inspection Report of the AP1000 RVI SM1-RXS-T2R-50007, SM1-RXS-T1P-502 RV Vibration Test Pre-Op Test Report A comparison of as built dimensions must be made available.
o Differences in as built dimensions in flow gaps that are significant may need to have CVAP data adjusted / extrapolated to account for the disparities.
Core Makeup Tank Heat Recirculation Tests APP-SSAR-GSC-810, NOTRUMP Predictive Analysis of the CMT Recirculation, CMT Draindown, and ADS Blowdown Pre-Operational Tests HY1-PXS-T2C-016, HY1-PXS-T1P-504 Section 7.5 CMT Recirculation Test Results Comparison to Predictive Analysis HY1-PXS-T2C-018, HY1-PXS-T1P-504 Section 7.5 CMT Recirculation Test Flow Rate SM1-PXS-T2C-012, SM1-PXS-T1P-504 Section 7.5 CMT Recirculation Test Results Comparison to Predictive Analysis SM1-PXS-T2C-013, SM1-PXS-T1P-504 Section 7.5 CMT Recirculation Test Flow Rate SM2-PXS-T2C-012, SM2-PXS-T1P-504 Section 7.5 CMT Recirculation Test Results Comparison to Predictive Analysis SM2-PXS-T2C-013, SM2-PXS-T1P-504 Section 7.5 CMT Recirculation Test Flow Rate HY1-PXS-T2C-019, HY1-PXS-T1P-504 Section 7.7 CMT Draindown Test Results SM1-PXS-T2C-014, SM1-PXS-T1P-504 Section 7.7 CMT Draindown Test Results SM2-PXS-T2C-014, SM2-PXS-T1P-504 Section 7.7 CMT Draindown Test Results Other documents may be requested based on the staffs review of the above documents.
Appropriate handling and protection of proprietary information shall be acknowledged and observed throughout the audit.
E.
Audit Team The following are the NRC audit team members:
Paul Kallan, Senior Project Manager (NRC), Lead Timothy Drzewiecki, Reactor Systems Engineer (NRC), Technical Reviewer Boyce Travis, Reactor Systems Engineer (NRC), Technical Reviewer
4 Chakrapani Basavaraju, Mechanical Engineer (NRC), Technical Reviewer Jeff Jacobson, Senior Reactor Operations Engineer (NRC), Technical Reviewer Aaron Armstrong, Reactor Operations Engineer (NRC), Technical Reviewer Yuken Wong, Senior Mechanical Engineer (NRC), Technical Reviewer Michael Breach, Mechanical Engineer (NRC), Technical Reviewer The following are the licensee contacts:
Steve Leighty (SNC)
Amy Chamberlain (SNC)
F.
Logistics Date: September 17, 2018 - October 5, 2018 Location:
Westinghouse Electric Company, LLC Washington Operations 11333 Woodglen Drive, Suite 203 Rockville, Maryland 20852 Telephone: 301-881-7040/7042 Additionally, the review of documents supporting LAR-18-019, and identified in Section D of this audit plan, can be conducted at NRC Headquarters via the licensees electronic reading room.
Location:
NRC Headquarters Two White Flint North 11545 Rockville Pike Rockville, MD 20852-2738 G.
Special Requests If necessary, the staff requests that subject matter expert(s) be made available to discuss the (1) potential differences between VEGP Units 3 and 4, and the plants for which testing has been conducted, (2) quality assurance of the test data, and (3) physical phenomena observed in the test data.
Paul Kallan (NRC) is the lead for this audit. He can be reached at 301-415-2809 or Paul.Kallan@nrc.gov.
H.
Deliverables At the completion of the audit, the staff will prepare an audit report within 45 days that will be declared and entered as an official agency record in ADAMS. The audit outcome may be used to identify any additional information to be submitted for making regulatory decisions, and will assist the staff in the issuance of RAIs (if necessary) in completing its review of LAR-18-019.