ML18248A263

From kanterella
Jump to navigation Jump to search
Transmittal of Final Perry Nuclear Power Plant Accident Sequence Precursor Report (Licensee Event Report 440 2016 003 01)
Date released: 09/25/2018 Download: ML18248A263


Transmittal of Final Perry Nuclear Power Plant Accident Sequence Precursor Report (Licensee Event Report 440-2016-003-01)
ML18248A262
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 09/25/2018
From: Kimberly Green
Plant Licensing Branch III
To: Hamilton D B
FirstEnergy Nuclear Operating Co
Green K J
References
Download: ML18248A262 (40)
Final Accident Sequence Precursor Analysis - Perry Nuclear Power Plant, Loss of Safety-Related Electrical Bus Results in a Loss of Shutdown Cooling (LER 440-2016-003-01) - Precursor
ML18228A845
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 08/23/2018
From: Christopher Hunter
NRC/RES/DRA/PRB
To:
References
LER 440-2016-003-01
Download: ML18228A845 (36)