Structural Reconciliation Discussion Points for Public Meeting on October 1, 2018
ML18241A141
Person / Time
Issue date: 10/01/2018
From: James Gaslevic
Human Performance, Operator Licensing & ITAAC Branch
To:
Gaslevic J
References
Download: ML18241A141 (2)


Text

Structural reconciliation discussion points for public meeting on Oct 1, 2018 The staff would like SNC to address the following reconciliation topics during the Oct 1 public meeting:

1. How are the changes in loads & configuration to structures tracked and processed into the design reconciliation process as mentioned in the ITAAC acceptance criteria (preferably walk through a completed or in-process example).
2. Explain the content and provide a high level outline (what can we expect to see) of the design report that will be developed in support of the reconciliation report.
3. Discuss the actions that will be undertaken by SNC to meet license conditions 2D12(g)1; 2D12(g)2; and 2D(13) during the reconciliation process to close out ITAAC.
4. When, relative to the scheduled fuel load date, is the reconciliation report expected to be made available to the NRC staff for review?

Structural Reconciliation ITAAC: