ML18227D344

From kanterella
Jump to navigation Jump to search
Letter Furnishing Additional Information to Reactor Pressure Vessel Supports
ML18227D344
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 07/13/1976
From: Robert E. Uhrig
Florida Power & Light Co
To: Lear G
Office of Nuclear Reactor Regulation
References
Download: ML18227D344 (5)


Text

NltC r.OBM 106 12 70)

U.S. NUCLI:ABBI:OUI ATOBY CO SION QOCKET NUM 0-o NRC DISTRIBUTION FDB PART 60 DOCI(ET MATERIAL I-ILE NUMOEA TO:

MR LEAR LETTEB QOBIGINAL QCOPY QNOTOAIZED UNC LASS IF I E D PROP INPUT FOAM F"OM'rXORIDA mVER a'LION CO MIAIIIp I'IA R E UHHIG DAIl Ol'OCUMENT

- Ls-"l4 DATE BECEIVED

't-II -"t4 NUMOEA OF COPIES BCCEIVED L Gi C ~c'b DESCBIPTION LTR RE OUR 6<<10-76 LTH..;..~~

ADDL.INFO TO REACTOR PRESSURE VESSEL SUPPORTS ENCLOSU AE PLANT i"IA>E:N ~gQ~<<

O sWLQ I

DXSTRXBUTXON FOR REACTOR VESSEL SUPPORT INFO FOR OPERATING REACTORS PER MR TRAMPLL 7~12 7

PITY FOR ACTION/INFORMATION 4 S $ TQ'.V.~D

~

MHC~1IIE PRO lY.(;'t~S~N< gg.

LXC ASST:

EGF T'RC PDR v KNXGIIT ROS7TOCZY CHECK C ~

TRAMIKLL SIIAO P ~ MIIANOHSKY

'o DORIAN RE BOSNAK.

VS NOONAN INTERNALD ISTR I BUTION PI)lt:Qag~

EXTEftNALDISTIIIUUTION CONTROL NUIVIOER

. BOX 013100, MIAMI, FLORIDA 33101

@l~lafo, fthm FLORIDA POWER 5 l.1QHT COMPANY July 13, 1976 L-76-257

+(9 Ipp"

,. wg//>>

",- i

Dear Mr. Lear:

~SUI e )gas,

+oil g 0"Iii Cg f Office of Nucle~ Reactor Regulation Attention:

Mr. igeogge Lear, Chief Operati~geKctors Branch I3 Division of Operating Reactors U.

S. Nuclear Regulatory Commission Washington, D. C.

3.0555 Re:

TURKEY POINT UNITS 3 and 4

DOCKET NOS.

50-250 and 50-251 REACTOR PRESSURE VESSEL SUPPORTS Your letter of June 10, 1976 requested that Florida Power and Light Company (FPL) inform you of our schedule for providing an evaluation of the adequacy of the reactor pressure vessel supports at Turkey Point Units 3 and 4.

Our response was to be based on a Request for Additional

~ Xnformation which was attached to the letter.

Your request was a followup to your letter of October 17, 1975 which informed us that you were initiating a generic evaluation of reactor pressure vessel supports.

Since October

1975, FPL and several other utilities with operating Westinghouse PWRs have met to discuss how to address the adequacy of reactor pressure vessel supports in operati'ng plants.

This "owners group" considered performing analyses similar to those suggested in your Request for Additional Information either for each individual design or for several typical designs which would envelope most of the plants in the owners group.

Discussions with Westinghouse Electric Corporation have indicated that such analyses would require a significant effort and, in fact, would take more than one year but probably less than three years to complete.

Plants in the design stage can include those design 'features which reduce the amount of analysis needed to demonstrate acceptable consequences from postulated events.

Operating

plants, on the'other
hand, cannot easily change structural configurations.

.Thus, events which were previously analyzed in accordance with approved techniques and found acceptable will now, because of recently developed analytical methods, require costly state-of-the-art techniques to demonstrate that the consequences remain within acceptable limits.

We have therefore concluded that our most reasonable course of action in response to your questions is to propose 7XM <

HELPING SUILD FLORIDA

o,, ~

'gr.>;

v j ',1 N

Office of Nuclear Reactor Regulation Page 2

implementation of an augmented inservice inspection program to preclude a reactor coolant pipe break near the reactor vessel nozzles.

This program will have a positive impact on plant safety and eliminate the need to perform extensive and lengthy analyses which would have minimal impact on the real margin of safety existing in our plants.

Representatives of the owners group and the Westinghouse Electric Corporation met with menbers of the Nuclear Regulatory Commission Staff on, May,25, 1976 to discuss the efforts the group has made up to that. time.

The discussions included justification for an augmented inservice inspection program and the technical merits of such a program.

A report detailing the discussions held at that meeting is now being prepared and.should be completed by September 1, 1976.

Upon completion, it will be formally transmitted to you as tech-nical justification for our selection of the augmented inservice inspection program.

Very truly yours, Robert E. Uhrig Vice President REU/bfp CC: