Washington Public Power Supply System A JOINT OPERATING AGENCY io
~ Wllrp nfl;ll/I"P OCT ~>r) >g). ';-
RE~>IPg Ig N~zcnpg g
~ay ENfpnp~E P
Q~ BO)I 9BB 3000 GEO WASHINOTON WAY RICHI ANO WASHINGTON 03353 PHONE ( 509 ) 946 966 I October 22, 1976 G02-76-472 Mr. R.
H. Engelken Director of Regulatory Operations Nuclear Regulatory Commission, Region V
1990 N. California Boulevard Walnut Creek Plaza Suite 202 Walnut Creek, California 94596
Subject:
'. 0.
2808 WPPSS NUCLEAR PROJECT,NO.
2 (DOCKET 50-397)
IE CIRCULAR NO. 76-01
Reference:
- Letter, R.H. Engelken to J.J.
- Stein, same subject, 7-28-..76'ear Mr. Engelken:
The referenced letter transmitted IE Circular No. 76-01.
In response to the questions asked in the circular, the manufacturer of our reactor building crane (Whiting Corporation) was asked to review their design for applicability to IE Circular No. 76-01.
The crane for WPPSS Nuclear Project No.
2 has AC control and AC Brakes compared to the DC brakes addressed in IE Circular 76-01.
This crane does not have the same type contactor which caused the problem referred to and therefore the WNP-2 crane design is not affected by this situation.
Whiting Corporation has made a review of the design and assures us of the design adequacy of the crane as provided.
No modifications are planned to add slow speed capability.
In addition, a field test is planned to assure that the brake power contactors are adequate for service.
Very truly yours,
~Q rA. Y<>grd~.~"AW D. L.
RENBERGER Assistant Director Generation and Technology DLR:GLC:ho cc:
Mr. D. Smithpeter, Bonneville Power'dministration (Portland)
NRC - Office of Inspection 8 Enforcement (Washington D.C.)