Southern Nuclear JUL 112018 Docket Nos.:

52-025 52-026 Michael J. Yox Regulatory Affairs Director Vogtle 3 & 4 7825 River Road Waynesboro, GA 30830 706-848-6459 tel 410-474-8587 cell myox @southernco.com ND-18-0817 10CFR 52.99(c)(3)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 and Unit 4 Resubmittal of Notice of Uncompleted ITAAC 225-davs Prior to Initial Fuel Load Ladies and Gentlemen:

Pursuantto 10 CFR 52.99(c)(3), Southern Nuclear Operating Company hereby notifies the NRC that as ofApril 10, 2018, Vogtle Electric Generating Plant(VEGP) Unit 3 and Unit 4 Uncompleted Inspections, Tests, Analyses, and AcceptanceCriteria (ITAAC) Items have not been completed greater than 225-days priorto initial fuel load:

ITAAC 3.3.00.07d.ii.c [Index Number 802]

ITAAC 3.3.00.07d.iii.c [Index Number 805]

ITAAC 3.3.00.07d.iv.c [Index Number 808]

ITAAC 3.3.00.07d.v.c [Index Number 811]

The Enclosuresdescribe the plans forcompleting these ITAAC. Southern Nuclear Operating Company will, at a later date, provide additional notifications for ITAAC that have notbeen completed 225-days prior to initial fuel load.

Southern Nuclear Operating Company (SNC) previously submitted Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load for Items 3.3.00.07d.ii.c; iii.c; iv.c; v.c; [Index Numbers 802, 805, 808, 811] ND-18-0511 [ML18106A755, ML18106A756, ML18106A757, ML18106A758], dated April 13,2018. This resubmittal supersedes ND-18-0511 in itsentirety.

Thisnotification is informed bythe guidancedescribed in NEI 08-01, Industry Guideline forthe ITAAC Closure Process Under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215. In accordance with NEI 08-01, this notification includes ITAAC for which required inspections, tests, oranalyses have not been performed or have been only partially completed.

All ITAAC will be fully completed and all Section 52.99(c)(1) ITAAC Closure Notifications will be submitted to NRC to supportthe Commission finding that all acceptance criteria are met prior to plant operation, as required by 10 CFR 52.103(g).

This letter contains no new NRC regulatory commitments.

If there are any questions, please contact Tom Petrak at 706-848-1575.

U.S. Nuclear Regulatory Commission ND-18-0817 Page 2 of 4 Respectfully submitted, Michael J. Vox Regulatory Affairs Director Vogtle 3 & 4 ;

Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Docket No.: 52-025 & 52-026 Completion Plan for Uncompleted ITAAC 3.3.00.07d.ii.c [Index Number 802] :

Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Docket No.: 52-025 & 52-026 Completion Plan for Uncompleted ITAAC 3.3.00.07d.iii.c [Index Number 805] :

Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Docket No.: 52-025 & 52-026 Completion Plan for Uncompleted ITAAC 3.3.00.07d.iv.c [Index Number 808] :

Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Docket No.: 52-025 & 52-026 Completion Plan for Uncompleted ITAAC 3.3.00.07d.v.c [Index Number 811]

MJY/LBP/amw

U.S. Nuclear Regulatory Commission ND-18-0817 Page 3 of 4 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. D. A. Bost (w/o enclosures)

Mr. M. D. Meier Mr. D. H. Jones (w/o enclosures)

Mr. D. L. McKinney Mr. M. J. Yox Mr. D. L. Fulton Mr. J. B. Klecha Mr. G. Chick Ms. A. L. Pugh Mr. A. 8. Parton Mr. W. A. Sparkman Mr. C. E. Morrow Ms. K. M. Stacy Mr. M. K. Washington Ms. A. C. Chamberlain Mr. T. G. Petrak Document Services RTYPE; VND.LI.L06 File AR.01.02.00 cc; Nuclear Reaulatorv Commission Mr. W. Jones (w/o enclosures)

Ms. J. M. Heisserer Mr. C. P. Patel Mr. M. E. Ernstes Mr. G. J. Khouri Mr. T. E. Chandler Ms. S. E. Temple Ms. P. Braxton Mr. N. D. Karlovich Mr. A. J. Lerch Mr. C. J. Even Mr. F. D. Brown Mr. B. J. Kemker Ms. A. E. Rivera-Varona Mr. P. B. Donnelly Ms. N. C. Coovert Qqlethorpe Power Corporation Mr. R. B. Brinkman Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Daiton Utilities Mr. T. Bundros

U.S. Nuclear Regulatory Commission ND-18-0817 Page 4 of 4 Westlnqhouse Electric Company. LLC Dr. L. Orlani (w/o enclosures)

Mr. D. 0. Durham (w/o enclosures)

Mr. M. M. Corletti Ms. L. G. Iller Mr. D. Hawkins Ms. J. Monahan Mr. J. L. Coward Ms. N. E. Deangelis Other Mr. J. E. Hesler, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, inc.

Mr. 8. Roetger, Georgia Public Service Commission Ms. 8. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Baich Bingham