Department of the Army, Acceptance of Financial Assurance, Control No. 608931
ML18194A428
Person / Time
Site: 04007354
Issue date: 07/09/2018
From: Lawyer D R
NRC/RGN-I/DNMS/CRDB
To: Bodrick M L
US Dept of the Army, Aberdeen Proving Ground, US Dept of the Army, Aberdeen Testing Ctr
References
608931
Download: ML18194A428 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BLVD. KING OF PRUSSIA, PA 19406-2713 July 9, 2018 COL Morris L. Bodrick, AC, Commander Department of the Army U.S. Army Aberdeen Test Center TEDT-AT-COS 400 Colleran Road Aberdeen Proving Ground, MD 21005-5059

SUBJECT:

DEPARTMENT OF THE ARMY, ACCEPTANCE OF FINANCIAL ASSURANCE, MAIL CONTROL NO. 608931

Dear COL Brodrick:

We have reviewed the letter received May 30, 2018, to meet the financial assurance requirements for your license. We have no further questions at this time. The following documents currently provide your financial assurance:

Certification of Financial Assurance received May 30, 2018 [ML 18155A568]

Statement of Intent received May 30, 2018 [ML 18155A568]

Decommissioning Funding Plan received May 30, 2018 [ML 18155A568]

Your organization uses a Decommissioning Funding Plan (DFP) to determine the amount of financial assurance necessary to fund all decommissioning activities.

10 CFR 40.36(d)(2) requires that, at the time of license renewal and at intervals not to exceed three years, the DFP must be resubmitted with adjustments as necessary to account for changes in costs and the extent of contamination.

Your currently approved DFP was received on May 30, 2018; therefore, your DFP must be re-submitted with your license renewal on or before February 28, 2019. The DFP must update the information submitted with the original or prior approved DFP, and must specifically consider the effect of the following events on decommissioning costs: (1) spills of radioactive material producing additional residual radioactivity in onsite subsurface material; (2) waste inventory increasing above the amount previously estimated; (3) waste disposal costs increasing above the amount previously estimated; (4) facility modifications; (5) changes in authorized possession limits; (6) actual remediation costs that exceed the previous cost estimate; (7) onsite disposal; and (8) use of a settling pond. If the amount of the financial assurance instrument will be adjusted to match the DFP, this cannot be done until the updated DFP is approved by the NRC. If the financial assurance instrument is revised (amended) to change the amount of financial assurance obligated, then you will need to also submit a revised Certificate of Financial Assurance (CFA) with the new amount. We will return the original copies of superseded documents under separate cover M. Bodrick Your cooperation is appreciated.

License No. SUB-834 Docket No. 04007354 Mail Control No. 608931 cc: Stephen Acker, Radiation Safety Officer 2 Sincerely, Dennis R. Lawyer, Health Physicist Commercial, Industrial, R&D and Academic Branch Division of Nuclear Materials Safety Region I

" M. Bodrick Your cooperation is appreciated.

License No. SUB-834 Docket No. 04007354 Mail Control No. 608931 cc: Stephen Acker, Radiation Safety Officer 2 Sincerely, Dennis R. Lawyer, Health Physicist Commercial, Industrial, R&D and Academic Branch Division of Nuclear Materials Safety Region I DOCUMENT NAME: G:\WBL Documents\WBL License Cover Letter\LSUB-834.608931.docx

[LAT to enter ADAMS Accession No.] SUNSI Review Complete:

Dlawyer After declaring this document "An Official Agency Record" it will be released to the Public. T f C C o receive a copy o this document, indicate in the box: " " = Copy w/o attach/encl "E"= opy w/ attach/encl "N" = No copy OFFICE Rl:DNMS "(\ IN I I I Dlawyer j~ NAME 7/9/2018 /). DATE OFFICIAL RECORD COPY