MONTHYEARML21260A0072021-09-0909 September 2021 Ametek Solidstate Controls, Notification of Potential Defect - 10CFR Part 21 Report Re Omron Timer Relay ML18191B1712018-07-0505 July 2018 Emerson - Submittal of Information Notice, (FIN) 2018-02, Licensees or Purchaser of Deviations or Failures to Comply ML18022A2822018-01-0505 January 2018 Engine Systems, Inc., Submittal of Defects and Non-Compliance Thermostatic Valve Assembly, P/N 6BOCF14001 ML17194A8252017-07-11011 July 2017 Part 21 Report Re Wedge Pin Failure in Anchor Darling Motor Operated Double Disc Gate Valves with Threaded Stem to Upper Wedge Connections ML17090A3972017-03-28028 March 2017 Part-21 Notification - Willful Misconduct and Falsification of Records ML17081A4532017-03-20020 March 2017 Part 21 - Plastic Jar Dedication Sampling ML17026A4142017-01-20020 January 2017 C&D Technologies, Inc. - Part 21 - Plastic Jar Dedication Sampling ML16209A0502016-07-13013 July 2016 Part 21 - Furmanite Nuclear Grade Leak Seal Material FSC-N-1B ML15103A4852015-04-0707 April 2015 Itt Engineered Valves - 2nd Interim Report to the NRC of 10 CFR 21 Event 50285, Reported by Itt 07/18/14 Concerning M I Diaphragms, Customer Testing ML15022A6502015-01-20020 January 2015 Letter from Steven R. Eisenberg USNRC 10CFR Part 21 Notification ML14274A0522014-09-22022 September 2014 Final Report 10CFR Part 21 Evaluation Regarding Misaligned Separators in LCR-25 Standby Batteries, Revision 1 - Original Letter Did Not Include the List of Affected Utilities ML14261A1502014-09-17017 September 2014 Interim Report to the NRC of 10 CFR 21 Event 50285, Reported by Itt 07/18/14 Concerning M1 Diaphragms, Customer Testing ML14113A3982014-04-17017 April 2014 Part 21 - Bearing Defect ML14079A3532014-03-17017 March 2014 Notification of Part 21 Re Bearing Defect ML14042A2022014-02-0505 February 2014 Part 21 Report Regarding Unqualified Material Used in Electrical Penetration Assemblies ML13277A0102013-09-23023 September 2013 Interim Report Update for Component ASME Material Supplied by Mirion Technologies (Conax Nuclear), Inc. (Mtcn), as Part of Containment Electric Penetration Assemblies (EPA) ML13246A0842013-08-23023 August 2013 Notification of Potential Defect & Interim Report Regarding a Potential Defect of Materials Supplied to Operating Us Nuclear Power Plants by Mirion Technologies (Conax Nuclear) Inc. (Mtcn) with Containment Electric Penetration Assemblies ML13211A1682013-07-26026 July 2013 Westinghouse, Notification of Potential Existence of Defects Pursuant to 10 CFR Part 21 Inconsistency Between the Intended Design Functionality of the Shield Passive Thermal Shutdown Seal (SDS) and That Observed During Post-Service Testing ML13165A3422013-06-12012 June 2013 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers ML13064A0122013-02-25025 February 2013 Notification of Potential Part 21 Report Re Wedge Pin Failure of an Anchor/Darling Double-Disc Gate Valve ML12352A1232012-12-13013 December 2012 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers ML12348A1362012-12-13013 December 2012 Part 21 60-Day Interim Report Notification: Adequacy of Design Change in Am Magne-Blast Circuit Breakers ML12318A0412012-11-0808 November 2012 Part 21 Report - Commercial Grade Dedication Not Properly Applied to Butterfly Valves ML12075A1062012-03-14014 March 2012 Notification of Potential Part 21 Re Defect on Arvan Electrical Terminal Blocks ML12097A3162012-03-0202 March 2012 Part 21 Report - Rosemont Pressure Tranmitters Out of Tolerance Condition ML12066A1182012-03-0202 March 2012 Part 21 Report - Rosemount Pressure Transmitters with Nonzero Based Calibrations ML1015305642010-05-28028 May 2010 Part 21 Notification from C & D Technologies, Inc., Post Corrosion on Dcu Batteries ML1015301082010-05-28028 May 2010 Notification of Potential Part 21 Re Interim Report - Inability to Complete 10 CFR Part 21 Evaluation Regarding Post Corrosion for Dcu Batteries ML0907611882009-03-11011 March 2009 Part 21 Notification - Defective Hk and K-Line Circuit Breaker Tension Springs ML0903502172009-01-27027 January 2009 Notification of Potential Part 21 Report from Fisher Controls International - Water Quality Deficiency ML0831900172008-11-12012 November 2008 Notification of Potential Part 21 on All Dimensionally Verified Commercial Grade Items Processed Per Fisher Manufacture Procedure Fmp 2K28 ML0823901062008-08-25025 August 2008 Notification of Potential Part 21 on Failure of F and G Switches ML0809906342008-04-0404 April 2008 Part 21 Notification Regarding Failure to Comply with the Requirements for Dedication of Commercial Grade Items ML0808104312008-03-20020 March 2008 Part 21 Report Involving Potential Failure of Certain Rosemount Pressure Transmitters ML0732000862007-11-0909 November 2007 Notification of Potential Part 21 Report Conval Valves Weld Qualifications ML0713703092007-03-0707 March 2007 Velan, Inc., Piston Check Cv Information ML0609504012006-04-0303 April 2006 Director Office of Inspection & Enforcement Reference: 10 CFR 21 Notification of 3/30/06 Rev1 ML0603303452006-01-23023 January 2006 10CFR21 Reporting of Defects and Non-Compliance - Engine Systems, Inc. Report No. 10CFR21-0091, Rev. 0., Woodward DRU Controls (Manufactured Between November 2000 and November 2005) ML0501102232005-01-0707 January 2005 Non-Emergency Event Report, Overstress Condition on Single Failure Proof Crane Trolleys ML0411403352004-04-21021 April 2004 Part 21 Notification Involving Voltage Monitoring Relays ML0312001162003-04-21021 April 2003 10CFR21 Reporting of Defects and Non-Compliance - Engine Systems, Inc. Report No. 10CFR 21-0086, Rev. 0 ML0215102952002-05-15015 May 2002 10 CFR 21 Notification - Potential Defect Fan Assemblies for UPS Systems ML0215502492002-05-10010 May 2002 Letter from W. G. Hampton Subject: 10CFR Part 21 Notification-Potenial Defect Involving Fan Assemblies Used in Forced Air Cooled Uninterruptible Power Supply Systems 2021-09-09
[Table view] Category:Letter
MONTHYEARIR 05000315/20240032024-10-31031 October 2024 Integrated Inspection Report 05000315/2024003 05000316/2024003 07200072/2024001 and Exercise of Enforcement Discretion AEP-NRC-2024-77, U2C28 Steam Generator Tube Inspection Report2024-10-21021 October 2024 U2C28 Steam Generator Tube Inspection Report AEP-NRC-2024-80, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask2024-10-15015 October 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-79, Unit 2, Independent Spent Fuel Storage Installation - Registration of Dry Spent Storage Cask2024-09-26026 September 2024 Unit 2, Independent Spent Fuel Storage Installation - Registration of Dry Spent Storage Cask AEP-NRC-2024-78, Reply to a Notice of Violation: EA-24-0472024-09-23023 September 2024 Reply to a Notice of Violation: EA-24-047 05000316/LER-2024-002-01, Manual Reactor Trip Following Rapid Downpower for Steam Leak2024-09-12012 September 2024 Manual Reactor Trip Following Rapid Downpower for Steam Leak IR 05000315/20244022024-09-10010 September 2024 Security Baseline Inspection Report 05000315/2024402 and 05000316/2024402, Independent Spent Fuel Storage Installation Security Inspection Report 07200072/2024401 AEP-NRC-2024-69, Core Operating Limits Report2024-09-0909 September 2024 Core Operating Limits Report IR 05000315/20243012024-09-0505 September 2024 NRC Initial License Examination Report 05000315/2024301 and 05000316/2024301 ML24225A0022024-09-0303 September 2024 Issuance of Amendment Nos. 363 and 344 Revising Technical Specifications Section 3.8.1, AC Sources-Operating, for a One-Time Extension of a Completion Time IR 05000315/20240112024-08-30030 August 2024 NRC Inspection Report 05000315/2024011 and 05000316/2024011 and Notice of Violation AEP-NRC-2024-76, Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-08-28028 August 2024 Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-51, Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes2024-08-28028 August 2024 Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes 05000316/LER-2024-003, Plant Shutdown Required by Technical Specifications Due to Reactor Coolant System Identified Leakage2024-08-22022 August 2024 Plant Shutdown Required by Technical Specifications Due to Reactor Coolant System Identified Leakage IR 05000315/20240052024-08-21021 August 2024 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2024005 and 05000316/2024005) AEP-NRC-2024-61, Unit 2 - Response to Request for Additional Information for Neutron Flux Instrumentation License Amendment Request2024-08-15015 August 2024 Unit 2 - Response to Request for Additional Information for Neutron Flux Instrumentation License Amendment Request ML24221A2702024-08-0808 August 2024 Unit 2 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-62, Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask2024-08-0707 August 2024 Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask ML24256A1482024-08-0202 August 2024 2024 Post Examination Submittal Letter AEP-NRC-2024-47, Form OAR-1, Owners Activity Report2024-07-30030 July 2024 Form OAR-1, Owners Activity Report ML24183A0162024-07-25025 July 2024 Review of Reactor Vessel Material Surveillance Program Capsule W Technical Report ML24169A2142024-07-25025 July 2024 Issuance of Amendment No. 362 Regarding Change to Technical Specification 3.4.12, Low Temperature Overpressure Protection System IR 05000315/20240022024-07-24024 July 2024 Integrated Inspection Report 05000315/2024002 and 05000316/2024002 05000316/LER-2024-002, Manual Reactor Trip Following Rapid Downpower for Steam Leak2024-07-15015 July 2024 Manual Reactor Trip Following Rapid Downpower for Steam Leak ML24197A1262024-07-15015 July 2024 Unit 2 - Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating ML24191A0692024-07-0909 July 2024 Operator Licensing Examination Approval - Donald C. Cook Nuclear Power Plant, July 2024 AEP-NRC-2024-56, Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask2024-07-0808 July 2024 Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-48, Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-07-0202 July 2024 Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating ML24176A1012024-06-21021 June 2024 57143-EN 57143 - Paragon Energy Solutions - Update 1 (Final) - 10CFR Part 21 Final Notification: P21-05242024-FN, Rev. 0 AEP-NRC-2024-45, Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring2024-06-13013 June 2024 Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring ML24163A0132024-06-12012 June 2024 Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000315/2024012 and 05000316/2024012 ML24159A2522024-05-30030 May 2024 10 CFR 50.71(e) Update and Related Site Change Reports AEP-NRC-2024-23, Core Operating Limits Report2024-05-23023 May 2024 Core Operating Limits Report ML24141A2162024-05-20020 May 2024 —Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection 05000316/LER-2024-001, Reactor Trip Due to Main Turbine Trip from a High-High Thrust Bearing Position Trip2024-05-20020 May 2024 Reactor Trip Due to Main Turbine Trip from a High-High Thrust Bearing Position Trip AEP-NRC-2024-40, Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-05-16016 May 2024 Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-41, Annual Radiological Environmental Operating Report2024-05-15015 May 2024 Annual Radiological Environmental Operating Report AEP-NRC-2024-26, Transmittal of Donald C. Cook Nuclear Plant, Emergency Plan Revision 492024-05-14014 May 2024 Transmittal of Donald C. Cook Nuclear Plant, Emergency Plan Revision 49 IR 05000315/20244012024-05-14014 May 2024 – Security Baseline Inspection Report 05000315/2024401 and 05000316/2024401 AEP-NRC-2024-07, Unit 2 - Transmittal of Report of Changes to the Emergency Plan2024-05-14014 May 2024 Unit 2 - Transmittal of Report of Changes to the Emergency Plan IR 05000315/20240012024-05-14014 May 2024 Integrated Inspection Report 05000315/2024001 and 05000316/2024001 ML24115A2152024-05-0707 May 2024 LTR: CNP Non-Acceptance with Opportunity TS 3-8-1 AEP-NRC-2024-24, Form OAR-1, Owners Activity Report2024-05-0707 May 2024 Form OAR-1, Owners Activity Report ML24256A1472024-05-0606 May 2024 DC Cook 2024 NRC Examination Submittal Letter: Submittal ML24116A0002024-05-0202 May 2024 – Regulatory Audit in Support of Review of the Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors AEP-NRC-2024-35, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-04-30030 April 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations AEP-NRC-2024-28, 2023 Annual Radioactive Effluent Release Report2024-04-29029 April 2024 2023 Annual Radioactive Effluent Release Report AEP-NRC-2024-31, Annual Report of Individual Monitoring2024-04-24024 April 2024 Annual Report of Individual Monitoring AEP-NRC-2024-29, (CNP) Unit 2 - Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-072024-04-0303 April 2024 (CNP) Unit 2 - Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-07 AEP-NRC-2024-02, Unit 2 License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-04-0303 April 2024 Unit 2 License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating 2024-09-09
[Table view] |
Text
EMERSON .*
Process Management Fisher Controls International LLC 301 South First Ave.
P.O. Box 190 Marshalltown, Iowa 50158-0190 USA T (641) 754-3011 F (641) 754-2830 July 5, 2018 To Whom It May Concern:
Attached is a Fisher Information Notice, (FIN) 2018-02 Emerson Process Management - Fisher Valves complies with the reporting requirements of 10 CFR Part 21 Section 21.21 (b) and 10 CFR Part 50.55 (e) by informing the U.S. Nuclear Regulatory Commission Licensees or Purchaser of deviations or failures to comply.
Please review the attached FIN notice for applicability to your facility.
George Baitinger Director, Quality Americas Attachments
[FISHER]
Fisher Controls International LLC 301 South First Ave P.O. Box 190 EMERSON. Marshalltown, Iowa 50158-0190 USA T (641) 754-3011 F (641) 754-2830 Fisher Information Notice: FIN 2018-02 2 July 2018
Subject:
Vee-Ball Valve Body-Bracket Bolting Dedication Equipment Affected by this Fisher Information Notice:
Items subject to this Fisher Information Notice (FIN) are confined to those serial numbers and customer orders referred to in the table below. Specifically, affected items are studs, nuts, and cap screws used for securing the Vee-Ball Valve Body to an actuator on only the below listed Customer Purchase Orders. Other orders for Vee-Ball valve body assemblies are not affected by this FIN.
Customer Plant Site Customer Fisher Order Part Number(s) Valve Serial Ship Date Purchase Order Number Number(s)
American Electric D.C. Cook 190-0000031389 011 -A005109581 1A3433X0422 16653827 27 Oct 2003 Power (AEP) Nuclear Plant (Hex Nut) 16654241 (Qty. 4 per valve) 16654242 I 16654570 29 Oct 2003 !
1R4436X0062 16654571 (Cap Screw) 16654572 (Qty. 4 per valve)
Korea Hydro & Wolsong 253-KF34466SR O??X-38201159 1A544424052 18926897 26 Feb 2010 Nuclear Power (Cap Screw) 18926898 (KHNP) (Qt. 4 per valve)
Purpose:
The purpose of this FIN is to alert affected customers that, as of 07 May 2018, Fisher became aware of a situation which may affect the performance of the aforementioned equipment, including its safety-related function. Fisher is informing affected customers of this circumstance in accordance with Section 21.21 (b) of 10 CFR 21.
Applicability:
This FIN applies only to the subject equipment supplied by Fisher as identified above.
Discussion:
Upon review of an order for replacement parts of a valve assembly, an individual was reviewing the parts originally selected for dedication and drew into question the processing level of supplied mounting parts, specifically the bolting used to secure a Vee-Ball valve body to an actuator. An investigation was opened to determine if the bolting had been provided in the previous order and if the bolting should have been classified as a basic component.
Flshor Controls International LLC 301 South First Ave P.O. Box 190 EMERSON . Marshalltown, Iowa 50158-0190 USA T {641) 754-3011 F (641) 754-2830 Extent of Condition:
An investigation was opened to examine all safety-related rotary valve orders between 1990 and the present to identify any other orders that may have had an identical issue. The investigation revealed a total of (2) customer orders contained body-to-actuator mounting bolting that had not been selected for commercial grade dedication. All other orders of similar construction had bolting correctly selected for commercial grade dedication.
Action Required:
Fisher will work with affected customers to replace any affected parts discussed within this FIN.
10 CFR 21 Implications:
Fisher requests that the recipient of this FIN review it and take appropriate action in accordance with 10 CFR 21. If there are any technical questions, please contact:
Jacob Clos Quality Manager Emerson Automation Solutions Fisher Controls International LLC 301 South First Avenue Marshalltown, IA 50158 Phone: (641 ) 754-2108 Jacob.Clos@Emerson.com Tim Parrie Director, North America Nuclear Business Unit Fisher Controls