WPPSS Nuclear Project No. 2 Response to Questions, Sacrificial Shield Wall Design
ML18191A237
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 02/11/1975
From: Stein J
Washington Public Power Supply System
To: Anthony Giambusso
Office of Nuclear Reactor Regulation
References
G02-75-37
Download: ML18191A237 (6)


Text

NRC DISTRIBUTION FOR PART 50 DOCKET MATERIAL (TEMPORARY FORM)

CONTROL NO:

FILE'ROM.

Washington Public Pwr Sy

Richland, Wash, 99352 Hr. J.J.

Stein 2-11-75 2-18-75 tDATE OF DOC DATE REC D LTR TWX RPT OTHER TO:

A, Giambusso ORIG none signed CC OTHER SENT AEC PDR SENT LOCALPDR CLASS UNCLASS PROP INFO INPUT NO CYS REC'D 40 DOCKET NO:

50>>397 D E SC R I PTION:

Ltr re our 7-8-74 ltr...trans the follow-ingo

~ ~ ~

Dist Per Orndoff 5 cys adv to Orndoff PLANT NAME.

LVPSS Untt 82 ENCLOSURES:

Responses to Questions...Sacrificial Shield Design...o..

~..

(40 cys encl rec'd)

WBUTLER (L)

W/ICopies CLARK (L)

W/ Copies PARR (L)

W/ Copies KNIEL(L)

W/ Copies SCHWENCER (L)

W/ Copies STOLZ (L)

W/ Copies VASSALLO (L)

W/ Copies PURPLE (L)

W/ Copies ZlEMANN (L)

W/ Copies DICKER (E)

W/ Copies KNIG H TON (E)

W/ Copies YOUNGBLOOD (E)

W/ Copies REGAN (E)

W/ Copies LEAR (L)

W/ Copies SPELS W/ Copies W/ Copies INTERNALDISTRIBUTION FOR ACTION/INFORMATION 2-18>>75 JB

~NRC PDR OGC, ROOM P-506A GOSSI CK/STAFF CASE GIAMBUSSO BOYD MOORE (L) v'DEYOUNG (L)

SKOVHOLT (L)

GOLLER (L) (Ltr)

P. COLLINS DENISE

~EG OPR FILE 5 REGION (2)

T.R. WILSON STEELE TECH REVIEW SCHROEDER

~ACCARY KNIGHT PAWLICK I SHAO STELLO HOUSTON NOVAK ROSS IPPOLITO v TEDESCO LONG LAINAS BENAROYA VOLLMER LIC ASST DIGGS (L)

GEARIN (L)

GOULBOURNE (L)

KREUTZER (E)

LEE (L)

MAIGRET (L)

REED (E)

SERVICE (L)

SHEPPARD (L)

SLATER (E)

SMITH (L)

TEETS (L)

WILLIAMS(E)

WI LSON (L)

INGRAM (L)

DENTON GRIMES R.

GAMMI LL H.

KASTNER E.

BALLARD P.

SPANG LE R J.

v-M.

ENVIRO S.

MULLER M.

DICKER S.

KN IG HTON M,

YOUNGB LOOD H.

REGAN S.

PROJECT LDR G.

V.

HARLESS R.

EXTERNALDISTRIBUTION A/T IND

~

BRAITMAN SALTZMAN MELTZ PLANS MCDONALD CHAPMAN DUBE (Ltr)

E. COUPE PETERSON HARTFIELD (2)

KLECKER EISENHUT WIGGINTON

~DAMP>M6aygg 1 LOCALPDR gj,M~ @+4 v 1 TIC (ABERNATHY)

(1)(2)(10) NATIONALLABS M1 NSIC (BUCHANAN) 1 W. PENNINGTON, Rm E-201 GT 1 ASLB 1

CONSULTANTS

,1 Newton Anderson NEWMARK/8LUME/AGBABIAN v'$. ACRS H&t~&/SENT 1 P DR-SAN/LA/NY 1 BROOKHAVEN NAT LAB 1 G. ULRIKSON, ORNL

~

1 AGMED (RUTH GUSSMAN)

R m B-127 GT 1 J. D. RUNKLES, Rm E-201 GT

$ 1 N

~

II '

~

~

~ ~,

L 1

3 l,

~

~

~

~ ~

~

~

~

~

~

~

~ a F

QaP RI,O

/~AM(ig Doe((et

-~

A JOINT OPERATING AGENCY Washington Public Power Supply System R. Q, OOII 969 3QQQ GEO, WASHINGTON WAY RICHLAND, WASHINCYON 89852 PHONC I 509) 946.960l Docket 50-397 5

6 4'

Ict@~~

gg',I Mr. A. Giambusso, Diiector SN'8>>

Division of Reactor Licensing Office of Nuclear Reactor Regula iO 0

U. S. Nuclear Regulatory Commissio c I 0 Washington, D.C.

-20555

Subject:

WPPSS NUCLEAR PROJECT NO.

2

RESPONSE

TO QUESTIONS SACRIFICIAL SHIELD WALL DESIGN

-February ll, 1975 G02-75-37

Reference:

Letter, W.R, Butler to J.J.

Stein, transmitting Request for Additional Information dated July 8, 1974.

(GI2-74-11)

Dear Mr. Giambusso:

The attachment provides information requested in the referenced letter.

This information includes results of pressure response analyses and structural information for the Sacrificial Shield Wall base design but does not include design information,about the Sacrificial Shield Wall itself.

We are supplying the information in two parts in order that our Contractors may proceed with-out delay with the completion of the upper pedestal and wetwell-drywell floor construction.

The remaining information will be provided May 15, 1975, so that the Sacrificial Shield Wall itself may be constructed according to schedule.

As discussed with your Dr. John Orndorf, WPPSS is requesting an expedited NRC review of the attached report.

In order that we may quickly eliminate any concerns the Staff may have on our responses, WPPSS will be contacting you regarding a meeting to explain this report and resolve any of your concerns.

Forty (40) copies of the attachment are being submitted 'for your review.

Very truly yours, J

J STEIN Managing Director JJS:GLG:am Attachment cc:

JJ Byrnes - Burns and

Roe, Inc.

BW Kennedy - Bonneville Power Administration JJ Verderber - Burns and

Roe, Inc.

e Q ~l~g

STATI: OF WASHINGTON

)

)

ss COUNTY OF BENTON

Subject:

WPPSS NUCLEAR PROJECT NO.

2

RESPONSE

TO QUESTIONS SACRIFICIAL SHIELD WALL DESIGN Ltr to A, Giambusso, Director, Div. of Reactor Licensing from JJ Stein, Managing Director-WPPSS J. J.

STEIN, Being first duly sworn, deposes and says:

That he is the Managing Directorof the WASHINGTON PUBLIC POWER SUPPLY SYSTEM, the applicant herei n; that he is authorized to submit the foregoing on behalf of said applicant; that he has read the foregoing and knows the contents thereof; and believes the same to be true to the best of his knowledge.

DATED J..

EIN 197 5.

On this day personally appeared before me, J. J. Stein to me known to be the individual who executed the foregoing instrument and acknowledged that he signed the same as,'his free act and deed for the uses and purposes therein mentioned.

GIVEN under my hand

'and seal this M day of Notary Public in an) for t e State of Washington >-~c'~

Residing at

~~ ~g

'L~ir