Acceptance for Review of the Pressurized Water Reactor Owners Group Topic Report PWROG-17011-NP, Rev 1, Update for Subsequent License Renewal: WCAP-14535A, Topical Report on Reactor Coolant Pump Flywheel Inspection Elimination and WCAP-1566
ML18163A039
Person / Time
Site: 99902037
Issue date: 06/21/2018
From: Dennis Morey
NRC/NRR/DLP/PLPB
To: Nowinowski W
Westinghouse
Benney B, NRR,DLP, 415-2767
References
PWROG-17011-NP, REV 1, WCAP-14535A, WCAP-15666-A
Download: ML18163A039 (3)


Text

June 21, 2018 Mr. W. Anthony Nowinowski Program Manager PWR Owners Group, Program Management Office Westinghouse Electric Company 1000 Westinghouse Drive, Suite 380 Cranberry Township, PA 16066

SUBJECT:

ACCEPTANCE FOR REVIEW OF THE PRESSURIZED WATER REACTOR OWNERS GROUP TOPICAL REPORT PWROG-17011-NP, REV 1, "UPDATE FOR SUBSEQUENT LICENSE RENEWAL: WCAP-14535A, "TOPICAL REPORT ON REACTOR COOLANT PUMP FLYWHEEL INSPECTION ELIMINATION" AND WCAP-15666-A, "EXTENSION OF REACTOR COOLANT PUMP MOTOR FLYWHEEL EXAMINATION"

Dear Mr. Nowinowski:

By letter dated May 15, 2018 (Agencywide Documents Access and Management System Accession No. ML18143B465, the Pressurized Water Reactor Owners Group (PWROG) submitted Topical Report (TR) PWROG-17011-NP, Rev 1, "Update for Subsequent License Renewal: WCAP-14535A, "Topical Report on Reactor Coolant Pump Flywheel Inspection Elimination" and WCAP-15666-A, "Extension of Reactor Coolant Pump Motor Flywheel Examination," to the U.S. Nuclear Regulatory Commission (NRC) staff for review.

The NRC staff has found that the material presented is sufficient to begin our review. The NRC staff expects to issue its request for additional information by October 15, 2018, and issue its draft safety evaluation (SE) in March 1, 2019. This schedule information takes in consideration the NRCs current review priorities and available technical resources and may be subject to change. If modifications to these dates are deemed necessary, we will provide appropriate updates to this information.

The NRC staff estimates that the review will require approximately 300 staff hours including project management time. The review schedule milestones and estimated review costs were discussed and agreed upon via phone between Chad Holderbaum, Program Director, PWROG, and the NRC staff on June 18, 2018. Section 170.21 of Title 10 of the Code of Federal Regulations requires that TRs are subject to fees based on the full cost of the review.

As with all TRs, the SE will be reviewed by the NRCs Office of the General Counsel (OGC) to determine whether it falls within the scope of the Congressional Review Act (CRA). During the course of this review, OGC considers whether any endorsement or acceptance of a TR by the NRC amounts to a rule as defined in the CRA. If this initial review concludes that the SE, with its accompanying TR, may be a rule, the NRC will forward the package to the Office of Management and Budget (OMB) for further review and consideration. Any review by OMB would impact the schedule for the issuance of the final SE.

W. A. Nowinowski If you have questions regarding this matter, please contact Brian Benney at (301) 415-2767.

Sincerely,

/RA/

Dennis Morey, Chief Licensing Processes Branch Division of Licensing Projects Office of Nuclear Reactor Regulation Docket No. 99902037

ML18163A039; *concurred via e-mail NRR-106 OFFICE NRR/DLP/PLPB/PM NRR/DLP/PLPB/LA* NRR/DMLR/EVIB/BC NRR/DLP/PLPB/BC NAME BBenney DHarrison DAlley DMorey DATE 6/20//2018 6/19/2018 6/20/2018 6/21/2018