Korea Hydro & Nuclear Power Co., Ltd - Transmittal of Revised Response to RAI 557-9199 for the Question 03.08.05-20 (Rev. 2)
ML18162A343
Person / Time
Site: 05200046
Issue date: 06/11/2018
From: Kim H
Korea Hydro & Nuclear Power Co, Ltd
To: William Ward
Document Control Desk, Office of New Reactors
Shared Package
ML18162A342 List:
References
MKD/NW-18-0089L
Download: ML18162A343 (3)


Text

70-1312-gil, Yuseong-daero, Yuseong-gu, Daejeon, 34101, KOREA Tel: +82-42-870-5400 / Fax: +82-42-870-5449 http://www.khnp.co.kr June 11, 2018 Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attention: Mr. William Ward Docket No.52-046 Division of New Reactor Licensing MKD/NW-18-0089L

Subject:

Revised Response to RAI 557-9199 for the Question 03.08.05-20 (Rev.2)

References:

1) NRC Request for Additional Information 557-9199, dated December 1, 2017
2) KHNP Letter MKD/NW-18-0043L, Response to RAI 557-9199 for the Question 03.08.05-20, dated March 23, 2018
3) KHNP Letter MKD/NW-18-0079L, Revised Response to RAI 557-9199 for the Question 03.08.05-20, dated May 30, 2018 KHNP is hereby submitting the response to RAI 557-9199, dated December 1, 2017. The revised response addresses Question 03.08.05-20 in response to reflect a few editorial changes. provides the revised response to RAI 557-9199 for the Question 03.08.05-20 (Rev.2)

(Security Related Information). Enclosure 2 revised provides the response to RAI 557-9199 for the Question 03.08.05-20 (Rev.2) (Non-Security Related Information).

If additional information or clarification is required, please contact Daegeun Ahn, Director of KHNP Washington DC Center at ahn.daegeun@khnp.co.kr or 703-388-0592.

Sincerely, Han-gon Kim Project Manager Advanced Reactors Development Laboratory Korea Hydro & Nuclear Power Co., Ltd.

Enclosures:

1. Revised Response to RAI 557-9199 for the Question 03.08.05-20 (Rev.2) (Security Related Information)
2. Revised Response to RAI 557-9199 for the Question 03.08.05-20 (Rev.2) (Non-Security Related Information)

Enclosure 1 Revised Response to RAI 557-9199 for the Question 03.08.05-20 (Rev.2)

(Security Related Information)

June 11, 2018

Enclosure 2 Revised Response to RAI 557-9199 for the Question 03.08.05-20 (Rev.2)

(Non-Security Related Information)