70-1312-gil, Yuseong-daero, Yuseong-gu, Daejeon, 34101, KOREA Tel: +82-42-870-5400 / Fax: +82-42-870-5449 http://www.khnp.co.kr June 4, 2018 Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attention: Mr. William Ward Docket No.52-046 Division of New Reactor Licensing MKD/NW-18-0085L
Subject:
Revised Response to RAI 61-7984 for Question 08.03.01-5 (Rev.1)
References:
- 1) NRC Request for Additional Information 61-7984, dated July 6, 2015
- 2) KHNP Letter MKD/NW-15-0131L, Response to RAI 61-7984 for Questions on a 60-Day Response Cycle, dated September 8, 2015 KHNP is hereby submitting the revised response to RAI 61-7984, dated July 6, 2015. The revised response addresses Question 08.03.01-5 relating to change from mobile GTG to mobile generator. The enclosure provides the revised response to RAI 61-7984 for Question 08.03.01-5 (Rev.1) (Non-Proprietary).
If additional information or clarification is required, please contact Daegeun Ahn, Director of KHNP Washington DC Center at ahn.daegeun@khnp.co.kr or 703-388-0592.
Sincerely, Han-gon Kim Project Manager Advanced Reactors Development Laboratory Korea Hydro & Nuclear Power Co., Ltd.
Enclosure:
Revised Response to RAI 61-7984 for Question 08.03.01-5 (Rev.1) (Non-Proprietary)
Enclosure Revised Response to RAI 61-7984 for Question 08.03.01-5 (Rev.1)