70-1312-gil, Yuseong-daero, Yuseong-gu, Daejeon, 34101, KOREA Tel: +82-42-870-5400 / Fax: +82-42-870-5449 http://www.khnp.co.kr June 4, 2018 Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attention: Mr. William Ward Docket No.52-046 Division of New Reactor Licensing MKD/NW-18-0082L
Subject:
Revised Response to RAI 297-8309 for Question 19.03-1 (Rev.2)
References:
- 1) NRC Request for Additional Information 297-8309, dated November 9, 2015
- 3) KHNP Letter MKD/NW-17-0058L, Revised Response to RAI 297-8309 for Question 19.03-1, dated March 3, 2017 KHNP is hereby submitting the revised response to RAI 297-8309, dated November 9, 2015. The revised response addresses Question 19.03-1 relating to change from mobile GTG to mobile generator. The enclosure provides the revised response to RAI 297-8309 for Question 19.03-1 (Rev.2) (Non-Proprietary).
If additional information or clarification is required, please contact Daegeun Ahn, Director of KHNP Washington DC Center at ahn.daegeun@khnp.co.kr or 703-388-0592.
Sincerely, Han-gon Kim Project Manager Advanced Reactors Development Laboratory Korea Hydro & Nuclear Power Co., Ltd.
Enclosure:
Revised Response to RAI 297-8309 for Question 19.03-1 (Rev.2) (Non-Proprietary)
Enclosure Revised Response to RAI 297-8309 for Question 19.03-1 (Rev.2)
(Non-Proprietary)